Concept explainers
Phono Company manufactures a plastic toy cell phone. The following standards have been established for the toys materials and labor inputs:
During the first week of July, the company had the following results:
The purchasing agent located a new source of slightly higher-quality plastic, and this material was used during the first week in July. Also, a new manufacturing layout was implemented on a trial basis. The new layout required a slightly higher level of skilled labor. The higher-quality material has no effect on labor utilization. Similarly, the new manufacturing approach has no effect on material usage. (Note: Round all variances to the nearest dollar.)
Required:
- 1. CONCEPTUAL CONNECTION Compute the materials price and usage variances. Assuming that the materials variances are essentially attributable to the higher quality of materials, would you recommend that the purchasing agent continue to buy this quality, or should the usual quality be purchased? Assume that the quality of the end product is not affected significantly.
- 2. CONCEPTUAL CONNECTION Compute the labor rate and efficiency variances. Assuming that the labor variances are attributable to the new manufacturing layout, should it be continued or discontinued? Explain.
- 3. CONCEPTUAL CONNECTION Refer to Requirement 2. Suppose that the industrial engineer argued that the new layout should not be evaluated after only one week. His reasoning was that it would take at least a week for the workers to become efficient with the new approach. Suppose that the production is the same the second week and that the actual labor hours were 13,200 and the labor cost was $132,000. Should the new layout be adopted? Assume the variances are attributable to the new layout. If so, what would be the projected annual savings?
1.
Calculate the value of material price variance and material usage variance. Identify whether the plant manger could continue to purchase this quality product or purchase the usual quality.
Explanation of Solution
Variance:
The amount obtained when actual cost is deducted from budgeted cost is known as variance. Variance is calculated to find whether the cost is over applied or under applied.
Use the following formula to calculate material price variance:
Substitute $1.55 for actual price, 44,250 units for actual quantity and $1.50 for standard price in the above formula.
Therefore, the material price variance is $2,213(U).
Use the following formula to calculate material usage variance:
Substitute $1.50 for standard price, 44,250 units for actual quantity and 45,000 for standard quantity in the above formula.
Therefore, the material usage variance is $1,125(F).
The total variance is $1,088(U)
Working Note:
1. Calculation of standard quantity:
2.
Calculate the value of labor rate variance and labor efficiency variance. Identify whether the labor variances are attributable to the new manufacturing process should be continued or discontinued.
Explanation of Solution
Use the following formula to calculate labor rate variance:
Substitute $138,000 for actual cost, 10,800 hours for actual hours and $10 for standard rate in the above formula.
Therefore, the labor rate variance is $4,000(U).
Use the following formula to calculate labor efficiency variance:
Substitute $10.00 for standard rate, 13,400 hours for actual hours and 13,500 hours for standard hours in the above formula.
Therefore, the labor efficiency variance is $1,000(F).
The total labor variance is $3,000 (U)
Working Note:
1. Calculation of standard hours:
3.
Calculate the value of labor rate variance and labor efficiency variance. Identify whether the new process should be adopted.
Explanation of Solution
Use the following formula to calculate labor rate variance:
Substitute $132,000 for actual cost, 13,200 hours for actual hours and $10 for standard rate in the above formula.
Therefore, the labor rate variance is $0.
Use the following formula to calculate labor efficiency variance:
Substitute $10 for standard rate, 13,200 hours for actual hours and 13,500 hours for standard hours in the above formula.
Therefore, the labor efficiency variance is $3,000(F).
The total labor variance is $3,000 (F)
Working Note:
1. Calculation of standard hours:
Want to see more full solutions like this?
Chapter 10 Solutions
Managerial Accounting: The Cornerstone of Business Decision-Making
- Cain Components manufactures and distributes various plumbing products used in homes and other buildings. Over time, the production staff has noticed that products they considered easy to make were difficult to sell at margins considered reasonable, while products that seemed to take a lot of staff time were selling well despite recent price increases. A summer intern has suggested that the cost system might be providing misleading information. The controller decided that a good summer project for the intern would be to develop, in one self-contained area of the plant, an alternative cost system with which to compare the current system. The intern identified the following cost pools and, after discussion with some plant personnel, appropriate cost drivers for each pool. There were: Cost Pools Costs Activity Drivers Receiving $ 600,000 Direct material cost Manufacturing 5,500,000 Machine-hours Machine setup 900,000 Production runs Shipping 1,000,000 Units shipped…arrow_forwardhow can i resolve this problem? Arona Corporation manufactures canoes in two departments, Fabrication and Waterproofing. In the Fabrication Department, fiberglass panels are attached to a canoe- shaped aluminum frame. The canoes are then transferred to the Waterproofing department to be coated with sealant. Arona uses a weighted-average process cost system to collect costs in both departments. All materials in the Fabrication Department are added at the beginning of the production process. On July 1, the Fabrication Department had 30 canoes in process that were 20% complete with respect to conversion cost. On July 31, Fabrication had 20 canoes in process that were 40% complete with respect to conversion cost. During July, the Fabrication Department completed 90 canoes and transferred them to the Waterproofing Department. What are the Fabrication Department's equivalent units of production related to conversion costs for July?arrow_forwardGrand Display is a manufacturer of large flower pots for urban settings. The company has these standards: (Click the icon to view the standards.) (Click the icon to view the actual results.) Read the requirements. Requirement 1. Compute the direct labor rate variance and the direct labor efficiency variance. (Enter the variances as positive numbers. Enter the currency amounts in the formulas to the nearest cent, then round the final variance amounts to the nearest whole dollar. Label the variance as favorable (F) or unfavorable (U). Abbreviations used: DL= Direct labor) Begin with the direct labor rate variance. First determine the formula for the rate variance, then compute the rate variance for direct labor. DL rate variance x ( x ( ) Requirements 1. Compute the direct labor rate variance and the direct labor efficiency variance. 2. What is the total variance for direct labor? 3. Who is generally responsible for each variance? 4. Interpret the variances. Print - X Donearrow_forward
- Albedo Incorporated manufactures high-end replacement telescope lenses for amateur and professional astronomers who are seeking to upgrade the performance of their telescopes. You have just become employed as a staff accountant at Albedo, and Jordan Coleman, the controller, has asked you to help with maintenance cost estimation for the lens manufacturing process. You review the manufacturing process and decide that the best cost driver for maintenance costs is machine hours. The data below are from the previous fiscal year for maintenance costs and machine hours: Month Maintenance Costs Machine Hours $ 3,210 4,650 5,175 3,350 3,100 1 2 3 4 5 6 7 8 9 10 11 12 2,950 2,900 2,900 4,120 4,350 3,500 3,775 2,750 3,900 4,050 2,690 2,500 2,580 2,300 2,500 3,160 3,325 2,780 3,000 Required: 1. What is the cost equation for maintenance costs using the high-low method? (Round "slope (unit variable cost)" to 2 decimal places. Negative amounts should be indicated by a minus sign.)arrow_forwardThe managers of Sandusky Inc. have decided to use the month of January to determine the cost of producing their widget for the year. This will help determine proper product pricing and is important for control purposes. Using the data from January, the managers can determine the costs associated with material and labor. However, fixed indirect costs must still be determined. Management intends to use the prior year’s data to determine overhead costs. It is assumed that management will allocate an equal amount of estimated costs each month. Is this an appropriate decision by management? Should January be used as the reference point for the whole year?arrow_forwardComfy Limited manufactures glass ornaments and housewares. The business makes use of unskilled labour and provides training to do hand crafting of the goods. In January, they decided to add a fruit bowl to the range. It took 45.60 hours to complete the first two fruit bowls. It was found that labour hours reduced as cumulative output increased, and it is expected that this trend will continue until 64 fruit bowls have been manufactured. The total number of hours to complete the next two fruit bowls was 41.04 hours. The labour and material costs to manufacture the first four fruit bowls, which have already been sold, were as follows: Direct materials: R1 360 Direct labour: R1 420Additional information: A gift shop owner saw these fruit bowls and has asked for a quotation for 12 to add to its range of products. Since the first four fruit bowls were manufactured, the price of material increased by 8%, and the cost of labour by 15%. Comfy Limited paid the designer of the fruit bowl R1…arrow_forward
- Barbara, the manager of Metlock, is analyzing the company's MOH costs from last year. Metlock had always followed an actual costing system when determining the costs of its customizable telescopes. Barbara wondered if it would be better to switch to a normal costing system, as she had heard a number of people talking about that at an industry conference she attended the previous month. Since Metlock has a highly machine-intensive operation, machine hours are used as its MOH cost driver. Here are the costs and other MOH information Barbara is analyzing: Budgeted MOH cost Actual MOH cost Budgeted machine hours Actual machine hours $426,240 Actual MOH rate $ 419,040 Determine the actual MOH rate and the budgeted MOH rate Metlock would have used last year under actual costing and normal costing, respectively. (Round answers to 2 decimal places, e.g. 52.75.) Budgeted MOH rate $ 96,000 108,000 /machine hour /machine hourarrow_forwardCommunications Jamarcus Bradshaw, plant manager of Georgia Paper Companys papermaking mill, was looking over the cost of production reports for July and August for the Papermaking Department. The reports revealed the following: Jamarcus was concerned about the increased cost per ton from the output of the department. As a result, he asked the plant controller to perform a study to help explain these results. The controller, Leann Brunswick, began the analysis by performing some interviews of key plant personnel in order to understand what the problem might be. Excerpts from an interview with Len Tyson, a paper machine operator, follow: Len: We have two papermaking machines in the department. I have no data, but I think paper machine No. 1 is applying too much pulp and, thus, is wasting both conversion and materials resources. We haven't had repairs on paper machine No. 1 in a while. Maybe this is the problem. Leann: How does too much pulp result in wasted resources? Len: Well, you see, if too much pulp is applied, then we will waste pulp material. The customer will not pay for the extra product; we just use more material to make the product. Also, when there is too much pulp, the machine must be slowed down in order to complete the drying process. This results in additional conversion costs. Leann: Do you have any other suspicions? Len: Well, as you know, we have two productsgreen paper and yellow paper. They are identical except for the color. The color is added to the papermaking process in the paper machine. I think that during August these two color papers have been behaving very differently. I don't have any data, but it just seems as though the amount of waste associated with the green paper has increased. Leann: Why is this? Len: I understand that there has been a change in specifications for the green paper, starting near the beginning of August. This change could be causing the machines to run poorly when making green paper. If this is the case, the cost per ton would increase for green paper. Leann also asked for a database printout providing greater detail on Augusts operating results. September 9 Requested by: Leann Brunswick Papermaking DepartmentAugust detail Prior to preparing a report, Leann resigned from Georgia Paper Company to start her own business. You have been asked to take the data that Leann collected, and write a memo to Jamarcus Bradshaw with a recommendation to management. Your memo should include analysis of the August data to determine whether the paper machine or the paper color explains the increase in the unit cost from July. Include any supporting schedules that are appropriate. Round any calculations to the nearest cent.arrow_forwardDura-Conduit Corporation manufactures plastic conduit that is used in the cable industry. A conduit is a tube that encircles and protects the underground cable. In the process for making the plastic conduit, called extrusion, the melted plastic (resin) is pressed through a die to form a tube. Scrap is produced in this process. Information from the cost of production reports for three months is as follows, assuming that inventory remains constant: Assume that there is one-half pound of resin per foot of the finished product. a. Determine the resin materials cost per foot of finished product for each month. Round to the nearest whole cent. b. Determine the ratio of the number of resin pounds output in conduit by the number of pounds input into the process for each month. Round percentages to one decimal place. c. Interpret the resin materials cost per foot for the three months. Use the information in (a) and (b) to explain what is happening. d. Determine the conversion cost per foot of finished product for each month and interpret the result.arrow_forward
- Calen Company manufactures and sells three products in a factory of three departments. Both labor and machine time are applied to the products as they pass through each department. The nature of the machine processing and of the labor skills required in each department is such that neither machines nor labor can be switched from one department to another. Calens management is attempting to plan its production schedule for the next several months. The planning is complicated by the fact that labor shortages exist in the community and some machines will be down several months for repairs. Following is information regarding available machine and labor time by department and the machine hours and direct labor hours required per unit of product. These data should be valid for at least the next six months. Calen believes that the monthly demand for the next six months will be as follows: Inventory levels will not be increased or decreased during the next six months. The unit cost and price data for each product are as follows: Required: 1. Calculate the monthly requirement for machine hours and direct labor hours for producing Products 401, 402, and 403 to determine whether or not the factory can meet the monthly sales demand. 2. Determine the quantities of 401, 402, and 403 that should be produced monthly to maximize profits. Prepare a schedule that shows the contribution to profits of your product mix. 3. Assume that the machine hours available in Department 3 are 1,500 instead of 2,700. Calculate the optimal monthly product mix using the graphing approach to linear programming. Prepare a schedule that shows the contribution to profits from this optimal mix. (CMA adapted)arrow_forwardBig Mikes, a large hardware store, has gathered data on its overhead activities and associated costs for the past 10 months. Nizam Sanjay, a member of the controllers department, believes that overhead activities and costs should be classified into groups that have the same driver. He has decided that unloading incoming goods, counting goods, and inspecting goods can be grouped together as a more general receiving activity, since these three activities are all driven by the number of receiving orders. The 10 months of data shown below have been gathered for the receiving activity. Required: 1. Prepare a scattergraph, plotting the receiving costs against the number of purchase orders. Use the vertical axis for costs and the horizontal axis for orders. 2. Select two points that make the best fit, and compute a cost formula for receiving costs. 3. Using the high-low method, prepare a cost formula for the receiving activity. 4. Using the method of least squares, prepare a cost formula for the receiving activity. What is the coefficient of determination?arrow_forwardAnderson Company has the following departmental manufacturing structure for one of its products: After some study, the production manager of Anderson recommended the following revised cellular manufacturing approach: Required: 1. Calculate the total time it takes to produce a batch of 20 units using Andersons traditional departmental structure. 2. Using cellular manufacturing, how much time is saved producing the same batch of 20 units? Assuming the cell operates continuously, what is the production rate? Which process controls this production rate? 3. What if the processing times of molding, welding, and assembly are all reduced to six minutes each? What is the production rate now, and how long will it take to produce a batch of 20 units?arrow_forward
- Managerial Accounting: The Cornerstone of Busines...AccountingISBN:9781337115773Author:Maryanne M. Mowen, Don R. Hansen, Dan L. HeitgerPublisher:Cengage LearningCornerstones of Cost Management (Cornerstones Ser...AccountingISBN:9781305970663Author:Don R. Hansen, Maryanne M. MowenPublisher:Cengage LearningManagerial AccountingAccountingISBN:9781337912020Author:Carl Warren, Ph.d. Cma William B. TaylerPublisher:South-Western College Pub
- Financial And Managerial AccountingAccountingISBN:9781337902663Author:WARREN, Carl S.Publisher:Cengage Learning,