The project management team of Solar Systems has developed a network consisting of the following list of activities in installing its solar panels. Times are given in weeks. Activity Most Preceding Optimistic( a) likely(m) Pessimistic(b) A 5 11 14 B 3 3 9 C - 6 10 14 D A, B 3 5 7 E B 4 6 11 F C 6 8 13 G D, E 2 4 6 H F 3. 3 9 Required: A. Draw the activity network for this problem (either AON or AOA). B. Determine the Expected Time and Variance for each activity. C. D. Show the activity schedule (ES, EF, LS, and LF) as well as slack (in table) Determine and state the critical path for this project. This must be based on your work in and not by inspection. (ii). What are the expected time and the variance of the project? What is the probability the project will be finished within 25 weeks?

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 21P
icon
Related questions
Question
The project management team of Solar Systems has developed a network consisting of the
following list of activities in installing its solar panels. Times are given in weeks.
Activity
Most
Preceding Optimistic( a) likely(m) Pessimistic(b)
A
5
11
14
B
3
3
9
C
-
6
10
14
D
A, B
3
5
7
E
B
4
6
11
F
C
6
8
13
G
D, E
2
4
6
H
F
3.
3
9
Required:
A.
Draw the activity network for this problem (either AON or AOA).
B.
Determine the Expected Time and Variance for each activity.
C.
D.
Show the activity schedule (ES, EF, LS, and LF) as well as slack (in table)
Determine and state the critical path for this project. This must be based on your work in
and not by inspection.
(ii). What are the expected time and the variance of the project?
What is the probability the project will be finished within 25 weeks?
Transcribed Image Text:The project management team of Solar Systems has developed a network consisting of the following list of activities in installing its solar panels. Times are given in weeks. Activity Most Preceding Optimistic( a) likely(m) Pessimistic(b) A 5 11 14 B 3 3 9 C - 6 10 14 D A, B 3 5 7 E B 4 6 11 F C 6 8 13 G D, E 2 4 6 H F 3. 3 9 Required: A. Draw the activity network for this problem (either AON or AOA). B. Determine the Expected Time and Variance for each activity. C. D. Show the activity schedule (ES, EF, LS, and LF) as well as slack (in table) Determine and state the critical path for this project. This must be based on your work in and not by inspection. (ii). What are the expected time and the variance of the project? What is the probability the project will be finished within 25 weeks?
Expert Solution
steps

Step by step

Solved in 2 steps with 1 images

Blurred answer
Similar questions
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Principles of Management
Principles of Management
Management
ISBN:
9780998625768
Author:
OpenStax
Publisher:
OpenStax College
MARKETING 2018
MARKETING 2018
Marketing
ISBN:
9780357033753
Author:
Pride
Publisher:
CENGAGE L
Management, Loose-Leaf Version
Management, Loose-Leaf Version
Management
ISBN:
9781305969308
Author:
Richard L. Daft
Publisher:
South-Western College Pub
Foundations of Business (MindTap Course List)
Foundations of Business (MindTap Course List)
Marketing
ISBN:
9781337386920
Author:
William M. Pride, Robert J. Hughes, Jack R. Kapoor
Publisher:
Cengage Learning