The slack times are: The activities on the critical path are The total project completion time for Dave = weeks. Activity LS LF H 15 G 11 F 9 E 8 D 14 C B A 802 Activity Slack A B C D E F G H Dave Fletcher was able to determine the activity times for constructing his laser scanning machine. Fletcher would like to determine ES, EF, LS, LF, and slack for each activity. The total project completion time and the critical path should also be determined. Here are the activity times: Activity Time (weeks) Immediate Predecessor(s) Activity Time (weeks) Immediate Predecessor(s) A 6 E 3 B B 8 F 6 B C 3 A G 11 C, E D 1 A H 7 D, F Dave's earliest start (ES) and earliest finish (EF) are: Activity ES .EF A 0 6 B 0 8 C 3 9 D 6 E F 8 G 22 H 21 Dave's latest start (LS) and latest finish (LF) are: Activity LS LF H 15 G 11 F 9

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 21P
icon
Related questions
Question
The slack times are:
The activities on the critical path are
The total project completion time for Dave = weeks.
Activity
LS
LF
H
15
G
11
F
9
E
8
D
14
C
B
A
802
Activity
Slack
A
B
C
D
E
F
G
H
Transcribed Image Text:The slack times are: The activities on the critical path are The total project completion time for Dave = weeks. Activity LS LF H 15 G 11 F 9 E 8 D 14 C B A 802 Activity Slack A B C D E F G H
Dave Fletcher was able to determine the activity times for constructing his laser scanning machine. Fletcher would like to determine ES, EF, LS, LF, and slack for each activity. The total project completion time
and the critical path should also be determined. Here are the activity times:
Activity Time (weeks) Immediate Predecessor(s) Activity Time (weeks) Immediate Predecessor(s)
A
6
E
3
B
B
8
F
6
B
C
3
A
G
11
C, E
D
1
A
H
7
D, F
Dave's earliest start (ES) and earliest finish (EF) are:
Activity
ES
.EF
A
0
6
B
0
8
C
3
9
D
6
E
F
8
G
22
H
21
Dave's latest start (LS) and latest finish (LF) are:
Activity
LS
LF
H
15
G
11
F
9
Transcribed Image Text:Dave Fletcher was able to determine the activity times for constructing his laser scanning machine. Fletcher would like to determine ES, EF, LS, LF, and slack for each activity. The total project completion time and the critical path should also be determined. Here are the activity times: Activity Time (weeks) Immediate Predecessor(s) Activity Time (weeks) Immediate Predecessor(s) A 6 E 3 B B 8 F 6 B C 3 A G 11 C, E D 1 A H 7 D, F Dave's earliest start (ES) and earliest finish (EF) are: Activity ES .EF A 0 6 B 0 8 C 3 9 D 6 E F 8 G 22 H 21 Dave's latest start (LS) and latest finish (LF) are: Activity LS LF H 15 G 11 F 9
Expert Solution
steps

Step by step

Solved in 2 steps

Blurred answer
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Principles of Management
Principles of Management
Management
ISBN:
9780998625768
Author:
OpenStax
Publisher:
OpenStax College
Management, Loose-Leaf Version
Management, Loose-Leaf Version
Management
ISBN:
9781305969308
Author:
Richard L. Daft
Publisher:
South-Western College Pub