1. What is the expected (estimated) time for each activity? 2. Based on the calculation of estimated times, what is the critical path? 3. What is the estimated time of the critical path?

Purchasing and Supply Chain Management
6th Edition
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
ChapterC: Cases
Section: Chapter Questions
Problem 5.3SD: Scenario 4 Sharon Gillespie, a new buyer at Visionex, Inc., was reviewing quotations for a tooling...
icon
Related questions
icon
Concept explainers
Topic Video
Question
Ross Hopkins, president of Hopkins Hospitality, has developed the tasks,
durations, and predecessor relationships in the following table for building new
motels. Draw the AON network and answer the questions that follow.
Time Estimates (In weeks)
Optimistic(a) Most
Activity
Immediate
predecessor(s)
Pessimistic
likely(b) | (m)
A
4
8.
10
В
A
8.
24
C
A
8.
12
16
D
A
4
6.
10
E
B
1
2
3
F
E,C
8.
20
G
E,C
F
3
4
2
2
F
6.
6.
6.
J
D,J,H
4
6.
12
K
I,J
2
3
1. What is the expected (estimated) time for each activity?
2. Based on the calculation of estimated times, what is the critical path?
3. What is the estimated time of the critical path?
4. What is the activity variance along the critical path?
5. What is the probability of completion of the project before a week 46?
Transcribed Image Text:Ross Hopkins, president of Hopkins Hospitality, has developed the tasks, durations, and predecessor relationships in the following table for building new motels. Draw the AON network and answer the questions that follow. Time Estimates (In weeks) Optimistic(a) Most Activity Immediate predecessor(s) Pessimistic likely(b) | (m) A 4 8. 10 В A 8. 24 C A 8. 12 16 D A 4 6. 10 E B 1 2 3 F E,C 8. 20 G E,C F 3 4 2 2 F 6. 6. 6. J D,J,H 4 6. 12 K I,J 2 3 1. What is the expected (estimated) time for each activity? 2. Based on the calculation of estimated times, what is the critical path? 3. What is the estimated time of the critical path? 4. What is the activity variance along the critical path? 5. What is the probability of completion of the project before a week 46?
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps with 3 images

Blurred answer
Knowledge Booster
Inventory management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning