To complete the problem the following is necessary. 1) project network diagram (AON), 2) table that shows ES, EF, LS, LF, and Slack for each activity, 3) How long will the project take to be completed?,
To complete the problem the following is necessary. 1) project network diagram (AON), 2) table that shows ES, EF, LS, LF, and Slack for each activity, 3) How long will the project take to be completed?, 4) Which activities are critical?
Immediate Time
Activity Predecessors (weeks)
A none 8
B A 2
C A 3
D A 60
E B 60
F C 2
G D 2
H E, F 20
I G 10
J H, I 10
K J 12
L K 3