To complete the problem the following is necessary. 1) project network diagram (AON), 2) table that shows ES, EF, LS, LF, and Slack for each activity, 3) How long will the project take to be completed?,
To complete the problem the following is necessary. 1) project network diagram (AON), 2) table that shows ES, EF, LS, LF, and Slack for each activity, 3) How long will the project take to be completed?, 4) Which activities are critical?
Immediate Time
Activity Predecessors (weeks)
A none 8
B A 2
C A 3
D A 60
E B 60
F C 2
G D 2
H E, F 20
I G 10
J H, I 10
K J 12
L K 3
![](/static/compass_v2/shared-icons/check-mark.png)
Trending now
This is a popular solution!
Step by step
Solved in 2 steps with 7 images
![Blurred answer](/static/compass_v2/solution-images/blurred-answer.jpg)
![Practical Management Science](https://www.bartleby.com/isbn_cover_images/9781337406659/9781337406659_smallCoverImage.gif)
![Operations Management](https://www.bartleby.com/isbn_cover_images/9781259667473/9781259667473_smallCoverImage.gif)
![Operations and Supply Chain Management (Mcgraw-hi…](https://www.bartleby.com/isbn_cover_images/9781259666100/9781259666100_smallCoverImage.gif)
![Practical Management Science](https://www.bartleby.com/isbn_cover_images/9781337406659/9781337406659_smallCoverImage.gif)
![Operations Management](https://www.bartleby.com/isbn_cover_images/9781259667473/9781259667473_smallCoverImage.gif)
![Operations and Supply Chain Management (Mcgraw-hi…](https://www.bartleby.com/isbn_cover_images/9781259666100/9781259666100_smallCoverImage.gif)
![Business in Action](https://www.bartleby.com/isbn_cover_images/9780135198100/9780135198100_smallCoverImage.gif)
![Purchasing and Supply Chain Management](https://www.bartleby.com/isbn_cover_images/9781285869681/9781285869681_smallCoverImage.gif)
![Production and Operations Analysis, Seventh Editi…](https://www.bartleby.com/isbn_cover_images/9781478623069/9781478623069_smallCoverImage.gif)