Consider the following data for a project to install a new server at the Northland Pines High School: Activity A B G Activity Time (days) Immediate Predecessor(s) 3 5 56 6 A A

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
### Transcription:

**b. Calculate the critical path for this project.**

The critical path is [Dropdown] and the project duration is [Textbox] days. *(Enter your response as a whole number.)*

**c. How much slack is in each of the activities G, H, and I?**

| Activity | Activity Time (days) | On critical path? | Slack (days) |
|----------|----------------------|-------------------|--------------|
| G        | 3                    | [Dropdown]        | [Textbox]    |
| H        | 6                    | [Dropdown]        | [Textbox]    |
| I        | 5                    | [Dropdown]        | [Textbox]    |

### Description:

This section involves a critical path method (CPM) calculation for project management. 

- **b.** You are asked to calculate the critical path, the sequence of stages determining the minimum time needed for an operation. 
  - Enter the path in the dropdown and the project duration in the textbox.

- **c.** You need to determine the slack for each activity (G, H, I) and whether it is on the critical path.
  - For each activity, select from the dropdown to indicate if it's on the critical path, and enter the slack time in the textbox. Slack time is the amount of time that you can delay the task without delaying the project.
Transcribed Image Text:### Transcription: **b. Calculate the critical path for this project.** The critical path is [Dropdown] and the project duration is [Textbox] days. *(Enter your response as a whole number.)* **c. How much slack is in each of the activities G, H, and I?** | Activity | Activity Time (days) | On critical path? | Slack (days) | |----------|----------------------|-------------------|--------------| | G | 3 | [Dropdown] | [Textbox] | | H | 6 | [Dropdown] | [Textbox] | | I | 5 | [Dropdown] | [Textbox] | ### Description: This section involves a critical path method (CPM) calculation for project management. - **b.** You are asked to calculate the critical path, the sequence of stages determining the minimum time needed for an operation. - Enter the path in the dropdown and the project duration in the textbox. - **c.** You need to determine the slack for each activity (G, H, I) and whether it is on the critical path. - For each activity, select from the dropdown to indicate if it's on the critical path, and enter the slack time in the textbox. Slack time is the amount of time that you can delay the task without delaying the project.
### Project Data for New Server Installation at Northland Pines High School

The following table provides the necessary data for planning the installation of a new server:

| Activity | Activity Time (days) | Immediate Predecessor(s) |
|----------|----------------------|--------------------------|
| A        | 3                    | –                        |
| B        | 5                    | A                        |
| C        | 6                    | A                        |
| D        | 4                    | B                        |
| E        | 1                    | B                        |
| F        | 5                    | B, C                     |
| G        | 3                    | D, E                     |
| H        | 6                    | F                        |
| I        | 5                    | F                        |
| J        | 6                    | G, H, I                  |

#### Task

a. Choose the correct network diagram below:

- **Option A**: Displays a sequence of activities starting from S (start), showing various dependencies such as A leading to B and C, followed by other activities as per their predecessors.

- **Option B**: Has a similar layout but differs in dependency connections and flow from S (start) through the tasks.

Each diagram represents a network flow for project activities, with arrows indicating the sequence and dependencies of tasks based on provided data. Select the diagram that accurately reflects the project dependencies and workflow.
Transcribed Image Text:### Project Data for New Server Installation at Northland Pines High School The following table provides the necessary data for planning the installation of a new server: | Activity | Activity Time (days) | Immediate Predecessor(s) | |----------|----------------------|--------------------------| | A | 3 | – | | B | 5 | A | | C | 6 | A | | D | 4 | B | | E | 1 | B | | F | 5 | B, C | | G | 3 | D, E | | H | 6 | F | | I | 5 | F | | J | 6 | G, H, I | #### Task a. Choose the correct network diagram below: - **Option A**: Displays a sequence of activities starting from S (start), showing various dependencies such as A leading to B and C, followed by other activities as per their predecessors. - **Option B**: Has a similar layout but differs in dependency connections and flow from S (start) through the tasks. Each diagram represents a network flow for project activities, with arrows indicating the sequence and dependencies of tasks based on provided data. Select the diagram that accurately reflects the project dependencies and workflow.
Expert Solution
Step 1: State the given information in the question.

Operations Management homework question answer, step 1, image 1

steps

Step by step

Solved in 5 steps with 9 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.