What is the duration of the critical path for the project? A. 14 weeks B. 7 Weeks C. 5 Weeks D. 8 weeks

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question

subject: Quantitative Analysis For Business

Please answer both of them. 

30. A journalism professor requires his students to conduct interviews with local TV personalities.
The PERT chart below shows the activities for this project, as well as the assumed duration
Schedule
recording
equipment
(Activity A)
Duration: 1
week
Form teams
(Activity B)
Duration:
1 week
Contact list of
interviewees
(Activity C)
Duration: 3
weeks
A. 14 weeks
B. 7 Weeks
C. 5 Weeks
Book
locations
(Activity D)
Duration:
2 weeks
D. 8 weeks
Develop draft
interview
questions
(Activity E)
Duration: 1
week
Finalize final
5
interviewees
(Activity F)
Duration: 1
week
Prepare
packets
(Activity G)
Duration:
1 week
What is the duration of the critical path for the project?
Finalize
interview
questions
(Activity H)
Duration: 1
week
Prep
interviewees
(Activity)
Duration:
1 week
Schedule
inten (Activit
Duration: 1
week
Conduct
interviews
(Activity K)
Duration:
1 week
Transcribed Image Text:30. A journalism professor requires his students to conduct interviews with local TV personalities. The PERT chart below shows the activities for this project, as well as the assumed duration Schedule recording equipment (Activity A) Duration: 1 week Form teams (Activity B) Duration: 1 week Contact list of interviewees (Activity C) Duration: 3 weeks A. 14 weeks B. 7 Weeks C. 5 Weeks Book locations (Activity D) Duration: 2 weeks D. 8 weeks Develop draft interview questions (Activity E) Duration: 1 week Finalize final 5 interviewees (Activity F) Duration: 1 week Prepare packets (Activity G) Duration: 1 week What is the duration of the critical path for the project? Finalize interview questions (Activity H) Duration: 1 week Prep interviewees (Activity) Duration: 1 week Schedule inten (Activit Duration: 1 week Conduct interviews (Activity K) Duration: 1 week
31 A construction company is working on a project to build a new industrial office park. A local television station has asked to film the construction project and conduct interviews with key stakeholders to create a documentary. The PERT chart
for the construction project, including filming the documentary, is shown below:
Hire workers
(Activity A
Duration:
11 days
Design building
(Activity
Duration
18 DAYS
Zoning permits
(Activity C
Duration:
12 dan
Train workers
(Activity D
Duration:
4 days
Rent earthmoving
equipment
(Activity)
Duration 4 days
What is the critical path for this project?
B. B-E-F-I
Clearland
(Activity G
Duration
6 days
A. B-E-G-H-I
D. A-D-I
C. C-G-H-I
The project manager has just learned that activity C will take 45 days instead of 12 days.
What is the critical path for this project if activity C takes 45 days?
Fin documentary
(Activity F
Duration:
29 days
Pour foundation
(Activity)
Duration:
4 days
Complete construction
(Activity
Duration:
7 days
Transcribed Image Text:31 A construction company is working on a project to build a new industrial office park. A local television station has asked to film the construction project and conduct interviews with key stakeholders to create a documentary. The PERT chart for the construction project, including filming the documentary, is shown below: Hire workers (Activity A Duration: 11 days Design building (Activity Duration 18 DAYS Zoning permits (Activity C Duration: 12 dan Train workers (Activity D Duration: 4 days Rent earthmoving equipment (Activity) Duration 4 days What is the critical path for this project? B. B-E-F-I Clearland (Activity G Duration 6 days A. B-E-G-H-I D. A-D-I C. C-G-H-I The project manager has just learned that activity C will take 45 days instead of 12 days. What is the critical path for this project if activity C takes 45 days? Fin documentary (Activity F Duration: 29 days Pour foundation (Activity) Duration: 4 days Complete construction (Activity Duration: 7 days
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 3 steps

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.