Question
### Problem 5: Bookmatch

The following information has been gathered for a project to install a new machine lathe at Diamond Manufacturing, Inc.:

| Activity | Activity Time (weeks) | Immediate Predecessor(s) |
|----------|------------------------|---------------------------| 
| A        | 4                      | -                         |
| B        | 7                      | A                         |
| C        | 9                      | B                         |
| D        | 3                      | B                         |
| E        | 14                     | D                         |
| F        | 10                     | C, D                      |
| G        | 11                     | F, E                      |

#### a. Choose the correct network diagram for this project.

##### Option A:

A network diagram is shown here:

- **Start** → **A (4 weeks)** → **B (7 weeks)** → **C (9 weeks)**
  - **Start** → **A (4 weeks)** → **B (7 weeks)** → **D (3 weeks)** → **E (14 weeks)**
  - **C (9 weeks)** and **D (3 weeks)** connect to **F (10 weeks)**
  - **F (10 weeks)** and **E (14 weeks)** connect to **G (11 weeks)**
  - **G (11 weeks)** connects to **Finish**

##### Option B:

Another network diagram is presented similarly but not the correct option based on the given data.

- **Start** → **A (4 weeks)** → **B (7 weeks)**
  - **B (7 weeks)** connects to **C (9 weeks)** and **D (3 weeks)**
  - **D (3 weeks)** connects to **E (14 weeks)**
  - **C (9 weeks)** and **D (3 weeks)** through node F **(10 weeks)** and finally to **Finish**

Click to select your answer and then click "Check Answer".

### Explanation of Graphs/Diagrams:
- The diagrams illustrate the sequence of activities required to complete the project.
- Each circle represents a task with the corresponding activity time in weeks.
- Arrows show the dependencies between tasks, ensuring that certain tasks must be completed before others can begin.

Remember to analyze the sequence carefully to determine the correct network diagram for successful project planning.
Transcribed Image Text:### Problem 5: Bookmatch The following information has been gathered for a project to install a new machine lathe at Diamond Manufacturing, Inc.: | Activity | Activity Time (weeks) | Immediate Predecessor(s) | |----------|------------------------|---------------------------| | A | 4 | - | | B | 7 | A | | C | 9 | B | | D | 3 | B | | E | 14 | D | | F | 10 | C, D | | G | 11 | F, E | #### a. Choose the correct network diagram for this project. ##### Option A: A network diagram is shown here: - **Start** → **A (4 weeks)** → **B (7 weeks)** → **C (9 weeks)** - **Start** → **A (4 weeks)** → **B (7 weeks)** → **D (3 weeks)** → **E (14 weeks)** - **C (9 weeks)** and **D (3 weeks)** connect to **F (10 weeks)** - **F (10 weeks)** and **E (14 weeks)** connect to **G (11 weeks)** - **G (11 weeks)** connects to **Finish** ##### Option B: Another network diagram is presented similarly but not the correct option based on the given data. - **Start** → **A (4 weeks)** → **B (7 weeks)** - **B (7 weeks)** connects to **C (9 weeks)** and **D (3 weeks)** - **D (3 weeks)** connects to **E (14 weeks)** - **C (9 weeks)** and **D (3 weeks)** through node F **(10 weeks)** and finally to **Finish** Click to select your answer and then click "Check Answer". ### Explanation of Graphs/Diagrams: - The diagrams illustrate the sequence of activities required to complete the project. - Each circle represents a task with the corresponding activity time in weeks. - Arrows show the dependencies between tasks, ensuring that certain tasks must be completed before others can begin. Remember to analyze the sequence carefully to determine the correct network diagram for successful project planning.
### Project Management Exercise: Problem 5 Bookmatch

**Instructions:**
Select the correct diagram by clicking the corresponding option (A, B, C, or D) and then click the "Check Answer" button.

#### Diagram Descriptions for Problem 5 Bookmatch:

**Option A:**
- **Start Node**
  - Leads to Node A (duration: 4)
- **Node A**:
  - Leads to Node B, which takes 7 units of time
- **Node B**:
  - Leads to Node C (duration: 9)
  - Leads to Node D (duration: 3)
  - Leads to Node E (duration: 14)
- **Node C**:
  - Leads to Node G (duration: 9)
- **Node G**:
  - Leads to Node F (duration: 10), T (11), and E (14)
- **Finish Node**

**Option B:**
- **Start Node**
  - Leads to Node A (duration: 4)
- **Node A**:
  - Leads to Nodes B (7), E (14)
  - Leads to Node D (3)
- **Node G**:
  - Leads to Node F (10)
- **Finish Node**

**Option C:**
- **Start Node**
  - Leads to Node D (3)
- **Node D**:
  - Leads to Node A (4)
- **Node A**:
  - Leads to Node B (7)
- **Node G**:
  - Leads to Node F (10), E (14)

**Option D:**
- **Start Node**
  - Leads to Node A (4)
- **Node A**:
  - Leads to Nodes B (7) and E (14)
  - Leads to Node D (3)
- **Node C**:
  - Leads to Nodes F (11) and G (10)
- **Finish Node**

2 parts remaining.

**Action Steps:**
1. Review the diagrams carefully.
2. Select the appropriate diagram by clicking the radio button next to it.
3. Click on "Check Answer" to submit your selection.

---

**Note:** By understanding and correctly identifying the critical path in each network diagram, you will enhance your project management skills.
Transcribed Image Text:### Project Management Exercise: Problem 5 Bookmatch **Instructions:** Select the correct diagram by clicking the corresponding option (A, B, C, or D) and then click the "Check Answer" button. #### Diagram Descriptions for Problem 5 Bookmatch: **Option A:** - **Start Node** - Leads to Node A (duration: 4) - **Node A**: - Leads to Node B, which takes 7 units of time - **Node B**: - Leads to Node C (duration: 9) - Leads to Node D (duration: 3) - Leads to Node E (duration: 14) - **Node C**: - Leads to Node G (duration: 9) - **Node G**: - Leads to Node F (duration: 10), T (11), and E (14) - **Finish Node** **Option B:** - **Start Node** - Leads to Node A (duration: 4) - **Node A**: - Leads to Nodes B (7), E (14) - Leads to Node D (3) - **Node G**: - Leads to Node F (10) - **Finish Node** **Option C:** - **Start Node** - Leads to Node D (3) - **Node D**: - Leads to Node A (4) - **Node A**: - Leads to Node B (7) - **Node G**: - Leads to Node F (10), E (14) **Option D:** - **Start Node** - Leads to Node A (4) - **Node A**: - Leads to Nodes B (7) and E (14) - Leads to Node D (3) - **Node C**: - Leads to Nodes F (11) and G (10) - **Finish Node** 2 parts remaining. **Action Steps:** 1. Review the diagrams carefully. 2. Select the appropriate diagram by clicking the radio button next to it. 3. Click on "Check Answer" to submit your selection. --- **Note:** By understanding and correctly identifying the critical path in each network diagram, you will enhance your project management skills.
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps

Blurred answer
Knowledge Booster
Inventory management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.