(ii) Draw the network for the following project: Activity A B CD E F Preceded -- G H I J AABB CCFDG,HE K L I by Time (weeks) 10 9 7 6 126884 11 5 7 Find the critical path, event slacks, total, free and independent floats.
Q: 1. To develop an LP mathematical model for a transportation or transshipment problem, you must…
A: Here, the first three questions are related to transportation problems. The main objective would be…
Q: 15) A project being analyzed by PERT has 60 activities, 13 of which are on the critical path. If the…
A: No. of activities in the project = 60Estimated time in the critical path () = 214Project Variance =…
Q: According to expectancy theory, your ________ is low if you don’t think a bonus or raise is going to…
A: Expectancy theory is a type of motivational theory that helps to understand how individuals make…
Q: A telephone call center uses five customer service representatives (CSRs) during the 8:30 a.m. to…
A: Number of CSRs = 5Standard service rate =5 min per call = 30/5=6 callsUtilization rate = 80% = 0.80
Q: Use simplex method to solve the following problem: Max. Z = 2x1 + 5x2, s.t. x1 + 4x25 24 3x1 + x22…
A: Linear programming (LP) is a mathematical optimization technique that helps solve problems where an…
Q: Large-scale Integrated (LSI) circult chips are made in one department of an electronics firm. These…
A: Given-
Q: Formulate recommendations to manage organizational change processes
A: The organisational transformation has become a continual reality in the fast-paced and intensely…
Q: Pickson Luthiers Corporation makes four models of electric guitars, ScarCT, Dela Mort, Warax, and…
A: Linear optimization is based on the mathematical technique that is used to determine the best…
Q: need to be recognized. ng ethical behavior. ting ethics and g programs ems below. Rewarding ethical…
A: *5Strategy: Screening prospective employeesScenario: Employees at Riverview go through an extensive…
Q: Southern Gas Company (SGC) is preparing to make a bid for oil and gas leasing rights in a newly…
A:
Q: Molly e-mailed her clients offering a free 30-minute massage for referrals. In the following…
A: A confusion matrix is a matrix which shows that depicts the performnace of a machine learning model…
Q: Mohawk Valley Furniture Warehouse has purchased a retail outlet with six departments (A, B, C, D, E,…
A: A load summary chart is a graphical representation that displays the movement of loads between…
Q: Complete the master production schedule (enter your responses as whole numbers). On-hand inventory…
A:
Q: Please do not give solution in image formate thanku. Global Supply Chain Management Select three…
A: Global Supply Chain Management is a critical discipline that includes the design, making plans,…
Q: What is the probability that no cars are in the system? What is the average number of cars waiting…
A: Queueing theory provides valuable insights into the behavior and performance of systems involving…
Q: Discuss how an organisation develops a supplier evaluation and certification program?
A: The procedure that businesses employ to select vendors and suppliers for their goods or materials is…
Q: Discuss the reasons why Mayo Clinic, a well-known company with a reputation for excellence, starts a…
A: The Mayo Clinic is an illustrious example of distinction among healthcare organisations, renowned…
Q: = data on the average number of customers processed by several bank hourly wage rate is $25, the…
A: To compute the labor productivity and multi factor productivity for each unit, we can use the…
Q: The lower and upper specifications for a software upgrade are 77 minutes and 81 minutes. Estimate…
A: Control charts are also known as process behaviour charts. It is a statistical process that helps in…
Q: QUESTION 12 Consider Modern Active MBA, a periodical dedicated to selecting an MBA program and…
A: The Newsvendor Model is based on an inventory management model, that is used in decision-making for…
Q: If a firm has an expected demand of 50 for its product but demand increases to 55 units 10% of the…
A: The cost of stock outs considers the costs sustained by a corporation when its inventory or stock of…
Q: Choose the correct time-phased assembly plan to prepare the gift bags OA А OF OB OD
A: A time-phased assembly plan- is a detailed schedule that outlines the specific tasks and activities…
Q: The SOAR system from Pillsbury is tailored to
A: The SOAR (State, Operator, And Result) system developed by Allen Newell and the Herbert A. Simon at…
Q: what is the multi-factor percent change this year vs last year
A: Last year This YearOutput…
Q: 14.) A part structure, lead time (weeks), and on-hand quantities for product A are shown in Figure…
A: It shows the items required in manufacturing with their1. levels in which they appear and 2. the…
Q: Detail 5 approaches to improving decision making. You can speak from the perspective of an…
A: Following are five ways to deal with further developing decision-making according to alternate…
Q: In the payoff table from the previous question, what is the optimal decision under the maximin…
A: Maximin or Pessimistic decision making model considers the highest payoff indicating decision making…
Q: Consider the following Solver sensitivity report of a profit maximization problem. 5 6 Variable…
A: Admissible development with inside the expulsion utilized limitation is 6 and shadow charge is 3.…
Q: λ= μ= b. Calculate P0 c. How many callers, on average, are waiting to place an order under the…
A:
Q: In an M/M/1 queueing system, the arrival rate is 5 customers per hour and the service rate is 7…
A: Arrival rate of calls λ=5 customers per hourService rate μ=7 customers per hour
Q: a) is the bottleneck.
A: Here, I have been given the network figure for the production process, Each operation has the output…
Q: Amalgamated Products which produces chemical materials has the following demand pattern for one of…
A: Find the Given details below:…
Q: Using the data in the table, what is the naive forecast of monthly income for April? (Round to two…
A: Here, for each month, I have been given the income data, I would apply a naive forecasting technique…
Q: Two products are manufactured on two sequential machines. The following table gives the machining…
A: Given data :machine time in minutesmachine time in minutes machine product 1product 2153262The daily…
Q: Use the following scenario and data for all questions The following is the Bill of Material (BOM) of…
A: Find the given details below: Itemon-handLead timeSchedule ReceiptsInventory(weeks)A02-B03100 in…
Q: Q2 (BREAK-EVEN ANALYSIS). An operations manager is deciding on the level of automation used to…
A: Find the Given details below: Given details:AlternativeFixed CostsVariable costs per unitA $…
Q: Refer to the scenario above. What is the theoretical minimum number of stations? seven five four six
A: Each task is given with the time and predecessor data, TaskTime(sec)PredecessorJ45NoneK50JL40JM55K,…
Q: 10 SIIKILL 1 2 3 # n is W 11 Took Mode 4 Took Name Activity 1 Artivity + Activity 4 62 Activity #…
A: According to issue, Thor is liable for exercises 3, 4, 6, and 7 in light of the fact that Bjorn…
Q: s expanding its product line to include three new products: A, B, and C. These are to be produced on…
A:
Q: irm C’s demand for a product is 60 units per month. Its supplier charges an ordering cost of $40 per…
A:
Q: Which of the following is NOT a typical application of analytics in operations and supply chain…
A: Operation management is the study of the operation function of an organization that helps in…
Q: 6 Which kind of warehouse arrangement is likely to have the highest variable cost for a company? O…
A: Here, I would determine a specific warehousing type where the company would pay the highest variable…
Q: what is the critical path
A: The critical path method (CPM) stands as a cornerstone, serving as a powerful analytical tool for…
Q: The Custom Bike Company has set up a weighted scoring matrix for evaluation of potential projects.…
A: Project management includes those processes that are important for quality planning and control. It…
Q: Please do not give solution in image format thanku Canine Gourmet Super Breath dog treats are sold…
A: Specification limits = 261±15 Upper Specification limit (USL) = 261+15 = 276Lower Specification…
Q: The MediQuick lab has three lab technicians available to process blood samples and three jobs that…
A: Assign Job 432 to Technician C which will cost $6.
Q: a. Find the equation of a simple linear regression line using Excel. (Round your answers to 3…
A: Here, for each quarter, I have been given the quantity(units) data, Here, I would use the actual…
Q: Decorum, Inc., manufactures high-end ceiling fans. Their sales are seasonal with higher demand in…
A: Regular production cost$300Over time production cost$350Selling price$500Holding cost$20Beginning…
Q: UC is catering an event on campus in TUC- that last time they did this they ran out of plastic…
A: The economic order quantity is the concept of inventory management and it helps in determining the…
Q: Ram Roy's firm has developed the following supply, demand, cost, and inventory data. Supply…
A:
Step by step
Solved in 3 steps with 4 images
- ces Mailings Po V ates) EE E AL Review View Tell me $ Text Predictions: On 4 BIU 1. Evergreen Company wants to construct a new office building. The company has contracted a construction management contractor for this project. Given below are the details of a construction project. ✓ ✓ ✓ % Activity A 5 B C D ¶ E F — a) Construct the project network (AON) diagram for Evergreen Company and list all possible activity paths and their duration. b) Determine Evergreen Company's critical path(s). What is the duration of project competition? c) Determine the ES, EF, LS, LF, and floats for each activity. d) Construct a Gantt chart for Evergreen Company's project. AaBbCcDdEe Normal A STR 6 Predecessor(s) Duration (days) 1 2 A A B B, C E AaBbCcDdEe No Spacing !!! 3 2 1 1 & 7 E Do AaBbCcL AaBbCcDd AaBb AaBbCeDdE Heading 1. Heading 2 Title Subtitle * 00 8 I 9 Focus ( ) 0 Comm > St FRoger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before a training program of this nature could be conducted. The activities, immediate predecessors, and times appear in the accompanying table: Immediate Predecessor(s) Activity ABCDEFG This exercise contains only parts b, c, and d. b) The critical activities for the leadership training program development project are B A, D C E, F Time (days) 4 5 3 10 4 6 10ull Tsel-PakaiMasker LTE 1 09.03 O 1 0 70% Assignment c.. Assignment chapter 17: Project Management 1). Based on the below table: (a) Construct a network for this problem. (b) Determine the expected time and variance for each activity. (c) Determine ES, EF, LS, LF, and slack for each activity. (d) Determine the critical path and project completion time. (e) Determine the probability that the project will be finished in 70 days or less. (f) Determine the probability that the project will be finished in 80 days or less. (g) Determine the probability that the project will be finished in 90 days or less. IMMEDIATE PREDECESSORS DAYS ACTIVITY 8 10 12 6 7 9 B 3 3 4 10 20 30 6 7 8 9 10 6 7 10 E 11 R D, E R, D, E H 14 15 16 F 10 11 13 F 6 7 8 G.H K 4 7 L. 2 4 G,H 2). Based on the below table: a. Construct the network. b. How long will it take to finish the project? C.. What is the critical path activities? d. If the project is to be finished in 16 weeks, which activities should be crashed? e.…
- Chuck’s Custom Boats (CCB) builds luxury yachts to customer order. CCB has landed a contract with a wealthy customer. Relevant data are shown in the table below. The complication is that the customer wants delivery in 32 weeks or he will impose a penalty of $375 for each week his yacht is late. Activity Immediate Predecessor Normal Time (NT) Weeks Crashing Cost 1st Week 2nd Week A ― 9 $410 $415 B A 7 125 -- C A 5 45 45 D B 4 300 350 E C 6 50 -- F D, E 5 200 225 G F 8 -- -- H F 7 85 90 I G 6 90 -- Construct a network diagram for the project Indicate the critical path when normal activity times are used. Develop a crashing schedule. Note: No activity can be crashed more than two weeks. Show breakdown of workConsider the following table: ACTIVITY PREC. ACT. TIME ESTIMATES (days) to tml tp te A --- 2 3 4 B --- 4 7 10 C A 1 2 3 D B 2 5 8 E B 4 6 8 F C , D 1 1 1 G E 3 4 5 H G , F 3 6 15 1. Construct a PERT network. [NOTE: This is the most crucial part of the exercise. Make sure you…The manager of the Oak Hills Swimming Club is planning the club's swimming team program. The first team practice is scheduled for May 1. The activities, their immediate predecessors, and the activity time estimates (in weeks) are as follows. Time (Weeks) Immediate Predecessor Activity Description Optimistic Most Probable Pessimistic A Meet with board 1 1 2 B Hire coaches A 4 8 Reserve pool A 4. 6 D Announce program В, с 3 E Meet with coaches B 4 F Order team suits A 1 2 3 G Register swimmers D 2 3 H Collect fees G 1 I Plan first practice Е, Н, F 1 1 1 (a) Draw a project network. (Submit a file with a maximum size of 1 MB.) Browse. No file selected. (b) Develop an activity schedule. (Round your answers to two decimal places.) Earliest Start Earliest Finish Latest Latest Activity Slack Start Finish A B D E F G H I (c) What are the critical activities? (Enter your answers as a comma-separated list.) What is the expected project completion time (in weeks)? (Round your answer to two decimal…
- By using Bar chart planning method, find the following: - Total duration for the project activities shown below - The project completion date (assume the start date is 1/3/2012 Activity A CDEFGHI J Duration 85 2846 7 45 6 (days) Following Activity C,D EFGHIJJ * If the project shown above had a delay of (4 days after (13working days), what would its new delivery date be? B BThe detail of the direct cost for project XYZ are given in Table 1. Table 1 Details for Project XYZ Normal Direct Cost 100 150 Activity Predecessor Maximum Slope Time (day) crash time A 100 50 A 3 A 4 200 1 200 200 D B 3 1 60 E C 4 2 D.E 70 90 F 3 150 1 The indirect cost is listed in Table 2. i. If the project needs to be crashed from its initial time, T1 to T5, list the step-by-step changes in activity and the direct cost to crash the project in Table 2,. ii. Identify the project's lowest cost possible within T1-T5 duration Table 2 Project Duration Activity crashed Step Total Direct Indirect Total Cost Cost Cost 1 Initial time T1 900 New time T2 800 New time T3 600 4 New time T4 550 New time T5 500blä 8 Q2/ By using PERT Method, Solve the ? following Q2/ For the project described in table below, assume that the activity durations are approximately normally distributed. Determine the probability to complete this project in (15 weeks). Activity Path m b a A (1,2) 1 2 В (2,3) 2 4 C (2,4) 1 3 D (4,5) 2 5 8 E (1,5) 2 4 F (5,6) 1 2 Note that the activity (3,4) is a dummy activity. 3. 3.
- 9:0V Il e P,77K/s l Asiacell 2_5368817288... -> Q1: A project consisting of the following activities: JI H.E G.F D.C D.C D.C 7 2 3 8 6|31 M LK KJ H G в A 5 3 () TE E D A B 4 4 1- Draw the network diagram of the project 2- Calçulate (Es) and (Lc) the project events 3- Select the critical path 4- What is the minimum time required to complete the project?2. The following table lists the activities of a network along with their time estimates: Activity Predecessor Duration (Days) Optimistic (a) Most Likely (m) Pessimistic (b) A None 2 5 8 B None 4 7 16 C A 3 6 9 D A 2 5 8 E C 5 8 11 F D 3 6 15 G B 2 5 14 H E, F 2 5 8 I G 6 9 12 J H, I 0 0 0 (a) Draw the project network. Use activity on node (A-O-N) method. (b) Identify the Critical Path. Calculate the length and variance of the Critical Path. (c) Identify the non-critical activities. Work out the Total Slack (TS) and Free Slack (FS) for all the non-critical activities. (d) State whether the network is sensitive or insensitive! (e) What is the approximate probability that jobs on the critical path will be completed by the due date of (i)24 days, (ii) 29 days?on in OMGT 1013 x (1) Facebook - usl-tuguegarao.neolms.com/student take_quiz_assignment/display/23380965?part=14&r ODE 606 ÖMGT 1013 Item 14 of 78 Refer to the given information below for a particular project. Activity Immediate Predecessors Time (weeks) A None 2 BD 4. 3 E F Compute the slack time for activity D A. LL