The expected times and variances for the project activities are given below, critical path is A-D-F-H. What is the probability of the completing the project in 28 periods? Variance
The expected times and variances for the project activities are given below, critical path is A-D-F-H. What is the probability of the completing the project in 28 periods? Variance
Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
Related questions
Question
Ib
![The expected times and variances for the project activities are given below, critical
path is A-D-F-H. What is the probability of the completing the project in 28 periods?
ID Description
A
B
C
D
E
F
G
H
Pilot production
Select channels of
distribution
Develop program
Test market
Patent
Full production
Ad promotion
Release
48%
51%
50%
49%
Predecessor
None
None
None
A
A
D
C
B,E,F,G
te
6
7
4 4 10 10
16
3
2
Variance
[(b-a)/6]2
3
4
2
25
10
2
1](/v2/_next/image?url=https%3A%2F%2Fcontent.bartleby.com%2Fqna-images%2Fquestion%2Fae4556bc-f96c-4422-810a-f9be18ed4561%2F4f290e64-a888-4361-9683-da5e2c64967b%2Ffdl3u6e_processed.jpeg&w=3840&q=75)
Transcribed Image Text:The expected times and variances for the project activities are given below, critical
path is A-D-F-H. What is the probability of the completing the project in 28 periods?
ID Description
A
B
C
D
E
F
G
H
Pilot production
Select channels of
distribution
Develop program
Test market
Patent
Full production
Ad promotion
Release
48%
51%
50%
49%
Predecessor
None
None
None
A
A
D
C
B,E,F,G
te
6
7
4 4 10 10
16
3
2
Variance
[(b-a)/6]2
3
4
2
25
10
2
1
Expert Solution

This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
This is a popular solution!
Trending now
This is a popular solution!
Step by step
Solved in 3 steps

Recommended textbooks for you

Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,

Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education

Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education

Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,

Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education

Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education


Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning

Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.