Given the information below, what are the estimated expected (mean) times (in weeks) for activities A-H?  What are the estimated standard deviations (in weeks) in the times for activities A-H?

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question

Given the information below, what are the estimated expected (mean) times (in weeks) for activities A-H? 

What are the estimated standard deviations (in weeks) in the times for activities A-H?  

 

 

### Project Management Activity Table

#### Overview:
This table represents a set of activities involved in a project, outlining their respective start and finish nodes, along with duration estimates in terms of optimistic, most likely, and pessimistic days.

| Activity | Start Node | Finish Node | Duration Estimate (Days) |
|----------|------------|-------------|--------------------------|
|          |            |             | Optimistic | Most Likely | Pessimistic |
| A        | 1          | 2           | 9          | 15          | 21          |
| B        | 1          | 3           | 13         | 21          | 33          |
| C        | 2          | 4           | 6          | 9           | 18          |
| D        | 2          | 5           | 23         | 35          | 47          |
| E        | 3          | 5           | 19         | 26          | 27          |
| F        | 4          | 6           | 23         | 29          | 41          |
| G        | 5          | 6           | 14         | 20          | 26          |
| H        | 6          | 7           | 2          | 5           | 8           |

#### Explanation of Columns:

- **Activity**: The label used to identify each activity.
- **Start Node**: The node at which the activity begins.
- **Finish Node**: The node at which the activity ends.
- **Duration Estimate (Days)**:
  - **Optimistic**: The minimum time required to complete the activity under ideal conditions.
  - **Most Likely**: The most realistic time required to complete the activity considering normal constraints and conditions.
  - **Pessimistic**: The maximum time required to complete the activity under adverse conditions.

#### Example Explanation:
- **Activity A** starts at Node 1 and finishes at Node 2. The optimistic duration is 9 days, most likely duration is 15 days, and pessimistic duration is 21 days.
- **Activity B** starts at Node 1 and finishes at Node 3. The optimistic duration is 13 days, most likely duration is 21 days, and pessimistic duration is 33 days.

This table is crucial for project planning and scheduling, allowing for estimation
Transcribed Image Text:### Project Management Activity Table #### Overview: This table represents a set of activities involved in a project, outlining their respective start and finish nodes, along with duration estimates in terms of optimistic, most likely, and pessimistic days. | Activity | Start Node | Finish Node | Duration Estimate (Days) | |----------|------------|-------------|--------------------------| | | | | Optimistic | Most Likely | Pessimistic | | A | 1 | 2 | 9 | 15 | 21 | | B | 1 | 3 | 13 | 21 | 33 | | C | 2 | 4 | 6 | 9 | 18 | | D | 2 | 5 | 23 | 35 | 47 | | E | 3 | 5 | 19 | 26 | 27 | | F | 4 | 6 | 23 | 29 | 41 | | G | 5 | 6 | 14 | 20 | 26 | | H | 6 | 7 | 2 | 5 | 8 | #### Explanation of Columns: - **Activity**: The label used to identify each activity. - **Start Node**: The node at which the activity begins. - **Finish Node**: The node at which the activity ends. - **Duration Estimate (Days)**: - **Optimistic**: The minimum time required to complete the activity under ideal conditions. - **Most Likely**: The most realistic time required to complete the activity considering normal constraints and conditions. - **Pessimistic**: The maximum time required to complete the activity under adverse conditions. #### Example Explanation: - **Activity A** starts at Node 1 and finishes at Node 2. The optimistic duration is 9 days, most likely duration is 15 days, and pessimistic duration is 21 days. - **Activity B** starts at Node 1 and finishes at Node 3. The optimistic duration is 13 days, most likely duration is 21 days, and pessimistic duration is 33 days. This table is crucial for project planning and scheduling, allowing for estimation
Expert Solution
steps

Step by step

Solved in 5 steps with 4 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.