A renovation of the gift shop at Orlando Amway Center has six activities (in hours). In the following table, the estimates of a, m, and b times for each of the activities are listed: Activity A B C D E F a 12 27 18 7 Activity A 16 16 m 16 32 18 14 17 18 Based on the activity time estimates, the expected times for each of the activities are (round your responses to two decimal places): b 20 41 18 20 21 21 Expected Time

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
## Project Time Estimation for Gift Shop Renovation

The gift shop at Orlando Amway Center is undergoing renovations, which involve six distinct activities. Each activity's estimated time (in hours) is categorized into three values: optimistic (a), most likely (m), and pessimistic (b).

### Activity Time Estimates

| Activity | a  | m  | b  |
|----------|----|----|----|
| A        | 12 | 16 | 20 |
| B        | 27 | 32 | 41 |
| C        | 18 | 18 | 18 |
| D        | 7  | 14 | 20 |
| E        | 16 | 17 | 21 |
| F        | 16 | 18 | 21 |

### Expected Time Calculation

For each activity, the expected time can be calculated using the formula:

\[ \text{Expected Time} = \frac{a + 4m + b}{6} \]

This formula provides a weighted average, where the most likely time is given more weight.

### Example Calculation for Activity A

Based on the given time estimates:

\[
\text{Expected Time for A} = \frac{12 + 4(16) + 20}{6}
\]

### Filling the Expected Time

For activity A, calculate the expected time using the given formula and round your response to two decimal places.

*Note: This method helps in better project planning and risk assessment by considering variability in time estimates.*
Transcribed Image Text:## Project Time Estimation for Gift Shop Renovation The gift shop at Orlando Amway Center is undergoing renovations, which involve six distinct activities. Each activity's estimated time (in hours) is categorized into three values: optimistic (a), most likely (m), and pessimistic (b). ### Activity Time Estimates | Activity | a | m | b | |----------|----|----|----| | A | 12 | 16 | 20 | | B | 27 | 32 | 41 | | C | 18 | 18 | 18 | | D | 7 | 14 | 20 | | E | 16 | 17 | 21 | | F | 16 | 18 | 21 | ### Expected Time Calculation For each activity, the expected time can be calculated using the formula: \[ \text{Expected Time} = \frac{a + 4m + b}{6} \] This formula provides a weighted average, where the most likely time is given more weight. ### Example Calculation for Activity A Based on the given time estimates: \[ \text{Expected Time for A} = \frac{12 + 4(16) + 20}{6} \] ### Filling the Expected Time For activity A, calculate the expected time using the given formula and round your response to two decimal places. *Note: This method helps in better project planning and risk assessment by considering variability in time estimates.*
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps with 3 images

Blurred answer
Follow-up Questions
Read through expert solutions to related follow-up questions below.
Follow-up Question
A renovation of the gift shop at Orlando Amway Center has six activities (in hours). In the following table, the estimates of a, m, and b times for each of the activities are listed:
Activity
A
B
C
D
E
F
Activity
A
B
C
D
E
F
a
12
27
18
7
16
16
Activity
A
m
16
32
18
14
17
18
Based on the activity time estimates, the expected times for each of the activities are (round your responses to two decimal places):
Expected Time
16
32.67
18
13.83
17.5
18.17
b
20
41
18
20
21
21
Based on the activity time estimates, standard deviation for each of the activities is (enter your responses rounded to two decimal places):
Standard Deviation
Transcribed Image Text:A renovation of the gift shop at Orlando Amway Center has six activities (in hours). In the following table, the estimates of a, m, and b times for each of the activities are listed: Activity A B C D E F Activity A B C D E F a 12 27 18 7 16 16 Activity A m 16 32 18 14 17 18 Based on the activity time estimates, the expected times for each of the activities are (round your responses to two decimal places): Expected Time 16 32.67 18 13.83 17.5 18.17 b 20 41 18 20 21 21 Based on the activity time estimates, standard deviation for each of the activities is (enter your responses rounded to two decimal places): Standard Deviation
Solution
Bartleby Expert
SEE SOLUTION
Similar questions
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.