Dave Fletcher was able to determine the activity times for constructing h ser scanning machine. Fletcher would like to determine ES, EF, LS, LF, and slack for each activity. The total project completion time and the critical path should also be determined. Here are the activity times: Activity A B C D Time (weeks) 5622 Immediate Predecessor(s) A A Dave's earliest start (ES) and earliest finish (EF) are: Activity A B А C Dave's latest start (LS) and latest finish (LF) are: D EFC G H Activity EFGH ES 0 0 5 5 66 11 12 Time (weeks) 5 6 9 7 EF 1567 7 11 12 4 20 19 Immediate Predecessor(s) B B C, E D, F
Dave Fletcher was able to determine the activity times for constructing h ser scanning machine. Fletcher would like to determine ES, EF, LS, LF, and slack for each activity. The total project completion time and the critical path should also be determined. Here are the activity times: Activity A B C D Time (weeks) 5622 Immediate Predecessor(s) A A Dave's earliest start (ES) and earliest finish (EF) are: Activity A B А C Dave's latest start (LS) and latest finish (LF) are: D EFC G H Activity EFGH ES 0 0 5 5 66 11 12 Time (weeks) 5 6 9 7 EF 1567 7 11 12 4 20 19 Immediate Predecessor(s) B B C, E D, F
Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
Related questions
Question

Transcribed Image Text:DEFG
The slack times are:
Dave's latest start (LS) and latest finish (LF) are:
Activity
H
G
F
E
H
D
C
B
A
Activity
A
5
6
6
11
12
LS
13
11
7
6
11
9
0
4
Slack
11
12
20
19
LF
20
20
13
11
13
11
6
9

Transcribed Image Text:Dave Fletcher was able to determine the activity times for constructing hi ser scanning machine. Fletcher would like
to determine ES, EF, LS, LF, and slack for each activity. The total project completion time and the critical path should
also be determined. Here are the activity times:
Activity
A
B
C
D
Time
(weeks)
5622
Immediate
Predecessor(s)
A
A
Dave's earliest start (ES) and earliest finish (EF) are:
Activity
A
B
O
ס ח ד 0 I
Dave's latest start (LS) and latest finish (LF) are:
F
G
H
Activity
Activity
ES
0
0
5
5
EFGH
6
6
11
12
LS
Time
(weeks)
5
6
9
7
EF
156
7
7
11
12
20
19
LF
Immediate
Predecessor(s)
B
B
C, E
D, F
Expert Solution

Step 1
1. During forward pass in case of more than two preceding activities the early start will be equal to the maximum early finish (early ending) of the preceding activities. |
2. During backward pass in case of more than two preceding activities the late finish will be equal to the minimum late start (late ending) of the preceding activities. |
Step by step
Solved in 2 steps with 3 images

Recommended textbooks for you

Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,

Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education

Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education

Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,

Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education

Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education


Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning

Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.