b. What is the critical path? O A-C-F-H OB-E-G-H O A-D-G-H O A-D-F-H c. What is the expected project completion time? Note: Do not round intermediate calculations. Round your answer to 3 decimal places. Project completion time days
b. What is the critical path? O A-C-F-H OB-E-G-H O A-D-G-H O A-D-F-H c. What is the expected project completion time? Note: Do not round intermediate calculations. Round your answer to 3 decimal places. Project completion time days
Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
Related questions
Question

Transcribed Image Text:The following represents a project that should be scheduled using CPM:
IMMEDIATE
PREDECESSORS
ACTIVITY
A
B
с
D
E
F
G
H
A
A
B
O A-C-F-H
OB-E-G-H
O A-D-G-H
ⒸA-D-F-H
C,D
D,E
F,G
b. What is the critical path?
a
1
1
2
Project completion time
1
TIMES (DAYS)
m
3
2
3
2
2
3
7
5
b
289723533
days
12
3.
13
c. What is the expected project completion time?
Note: Do not round intermediate calculations. Round your answer to 3 decimal places.
13
Expert Solution

Step 1: Introduce the question:
Here, I will determine the expected activity time for each activity, I am given the immediate predecessor data, and I will construct the network diagram using the CPM method, From the REF of this network diagram, I can answer all the questions.
Step by step
Solved in 3 steps with 5 images

Recommended textbooks for you

Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,

Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education

Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education

Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,

Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education

Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education


Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning

Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.