The expected times and variances for the project activities are given below, critical path is A-D-F-H. What is the probability of the completing the project in 31 periods? ID Description A B C D E F G H Test market Patent Full production Ad promotion Release 55% 77% Pilot production Select channels of distribution Develop program 88% O 66% Predecessor None None None AA D C B,E,F,G Jy te 6 7 4 4 10 16 32 Variance [(b-a)/6]2 3 4 225 10 21
The expected times and variances for the project activities are given below, critical path is A-D-F-H. What is the probability of the completing the project in 31 periods? ID Description A B C D E F G H Test market Patent Full production Ad promotion Release 55% 77% Pilot production Select channels of distribution Develop program 88% O 66% Predecessor None None None AA D C B,E,F,G Jy te 6 7 4 4 10 16 32 Variance [(b-a)/6]2 3 4 225 10 21
Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
Related questions
Question
100%
![The expected times and variances for the project activities are given below, critical
path is A-D-F-H. What is the probability of the completing the project in 31 periods?
ID
A
B
C
D
E
F
G
H
Description
Pilot production
Select channels of
distribution
Develop program
Test market
Patent
Full production
Ad promotion
Release
55%
77%
88%
66%
Predecessor
None
None
None
A
A
D
C
B,E,F,G
6
7
4
4
10
16
3
2
Variance
[(b-a)/6]2
3
4
2
2
5
10
2
1](/v2/_next/image?url=https%3A%2F%2Fcontent.bartleby.com%2Fqna-images%2Fquestion%2F1259445e-f0d4-4952-862b-183d8fdc76ac%2Fc415f0ff-ca74-44d8-96a4-2e1d9121035f%2F06xcfye_processed.jpeg&w=3840&q=75)
Transcribed Image Text:The expected times and variances for the project activities are given below, critical
path is A-D-F-H. What is the probability of the completing the project in 31 periods?
ID
A
B
C
D
E
F
G
H
Description
Pilot production
Select channels of
distribution
Develop program
Test market
Patent
Full production
Ad promotion
Release
55%
77%
88%
66%
Predecessor
None
None
None
A
A
D
C
B,E,F,G
6
7
4
4
10
16
3
2
Variance
[(b-a)/6]2
3
4
2
2
5
10
2
1
Expert Solution

This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
Step by step
Solved in 3 steps with 3 images

Recommended textbooks for you

Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,

Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education

Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education

Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,

Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education

Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education


Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning

Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.