The following information has been gathered for a project to install a new machine lathe at Diamond Manufacturing, Inc: Activity Activity Time (weeks) Immediate Predecessor(s) A B 7 A B D 3 B E 14 D 10 C, D G 11 F.E a. Choose the correct network diagram for this project. O A. OB. Start Start 10 Finish Finish 11 C. O D. Start Start Finish Finish b. Calculate the slack for each activity and determine the critical path. How long will the project take? The critical path is path A-B-C-F-G and the project duration is 41 weeks. (Enter your response as an integer.) Determine the slack for each activity. (Enter your responses as integers.) Slack Activity (weeks) A B D E F

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
icon
Concept explainers
Topic Video
Question
### Project Network Diagram and Critical Path Analysis for Diamond Manufacturing, Inc.

**Project Overview:**
The following information has been gathered for a project to install a new machine lathe at Diamond Manufacturing, Inc.

| **Activity** | **Activity Time (weeks)** | **Immediate Predecessor(s)** |
|--------------|---------------------------|-----------------------------|
| A            | 4                         | -                           |
| B            | 7                         | A                           |
| C            | 9                         | -                           |
| D            | 3                         | B                           |
| E            | 14                        | D                           |
| F            | 10                        | C, D                        |
| G            | 11                        | F, E                        |

**Tasks:**
1. **Choose the correct network diagram for this project.**

    Correct diagram: **C**
    ![Network Diagram C](path/to/image)

    Explanation:
    The network diagram illustrates the flow of tasks and their dependencies. The start point leads to activities A and C. Activity A then leads to B, which further leads to D. Activity D has two subsequent activities, E and F. The final activity, G, is dependent on the completion of both E and F.

2. **Calculate the slack for each activity and determine the critical path. How long will the project take?**

    The critical path is **A-B-C-F-G** and the project duration is **41 weeks**.

    | **Activity** | **Slack (weeks)** |
    |--------------|-------------------|
    | A            |                   |
    | B            |                   |
    | C            |                   |
    | D            |                   |
    | E            |                   |
    | F            |                   |
    | G            |                   |

    Explanation:
    To determine the slack for each activity, perform forward pass and backward pass calculations on the network diagram. The slack is the difference between the latest start time and the earliest start time or the latest finish time and the earliest finish time for each activity.

### Detailed Explanation of the Network Diagram:

1. **Start** - The project initiation.
2. **A (4 weeks)** - An initial activity with no predecessor.
3. **B (7 weeks)** - Immediately follows A.
4. **C (9 weeks)** - Another initial activity with no predecessor.
5. **D (3 weeks)** - Follows B.
6. **E (
Transcribed Image Text:### Project Network Diagram and Critical Path Analysis for Diamond Manufacturing, Inc. **Project Overview:** The following information has been gathered for a project to install a new machine lathe at Diamond Manufacturing, Inc. | **Activity** | **Activity Time (weeks)** | **Immediate Predecessor(s)** | |--------------|---------------------------|-----------------------------| | A | 4 | - | | B | 7 | A | | C | 9 | - | | D | 3 | B | | E | 14 | D | | F | 10 | C, D | | G | 11 | F, E | **Tasks:** 1. **Choose the correct network diagram for this project.** Correct diagram: **C** ![Network Diagram C](path/to/image) Explanation: The network diagram illustrates the flow of tasks and their dependencies. The start point leads to activities A and C. Activity A then leads to B, which further leads to D. Activity D has two subsequent activities, E and F. The final activity, G, is dependent on the completion of both E and F. 2. **Calculate the slack for each activity and determine the critical path. How long will the project take?** The critical path is **A-B-C-F-G** and the project duration is **41 weeks**. | **Activity** | **Slack (weeks)** | |--------------|-------------------| | A | | | B | | | C | | | D | | | E | | | F | | | G | | Explanation: To determine the slack for each activity, perform forward pass and backward pass calculations on the network diagram. The slack is the difference between the latest start time and the earliest start time or the latest finish time and the earliest finish time for each activity. ### Detailed Explanation of the Network Diagram: 1. **Start** - The project initiation. 2. **A (4 weeks)** - An initial activity with no predecessor. 3. **B (7 weeks)** - Immediately follows A. 4. **C (9 weeks)** - Another initial activity with no predecessor. 5. **D (3 weeks)** - Follows B. 6. **E (
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps with 3 images

Blurred answer
Knowledge Booster
Inventory management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.