prepar precedence are presented in the table below. Three time estimates (in weeks) are given for each activity: optimistic time, most likely time, and pessimistic time. (a) Draw the PERT network diagram for the project, labeling all activities and times. (b) Perform a forward pass and backward pass through the network to determine the critical path, the expected duration of the project, and the slack time for each activity. (c) What is the probability that the project will be completed in 17 days? (d) Allowing for lost days due to snow emergencies, what is the probability that the project will be completed in 15 days?
prepar precedence are presented in the table below. Three time estimates (in weeks) are given for each activity: optimistic time, most likely time, and pessimistic time. (a) Draw the PERT network diagram for the project, labeling all activities and times. (b) Perform a forward pass and backward pass through the network to determine the critical path, the expected duration of the project, and the slack time for each activity. (c) What is the probability that the project will be completed in 17 days? (d) Allowing for lost days due to snow emergencies, what is the probability that the project will be completed in 15 days?
Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
Related questions
Question
Please help to solve

Transcribed Image Text:7.9 The Industrial Engineering Department at Ivy University is moving from its old building to a
new building. The move must be completed within the 17-day period between semesters.
A list of tasks (activities) has been prepared. The activities and precedence requirements
are presented in the table below. Three time estimates (in weeks) are given for each activity:
optimistic time, most likely time, and pessimistic time. (a) Draw the PERT network diagram
for the project, labeling all activities and times. (b) Perform a forward pass and backward
pass through the network to determine the critical path, the expected duration of the project,
and the slack time for each activity. (c) What is the probability that the project will be
completed in 17 days? (d) Allowing for lost days due to snow emergencies, what is the
probability that the project will be completed in 15 days?
Activity Activity description
Immediate
predecessor
Optimistic
time (days)
Most likely
time (days)
Pessimistic
time (days)
1
Initiate move
Prepare new building space
Pack faculty files and books
Disconnect computers
Disconnect lab equipment
Movers move files and books
2
3
6.
3
3
4
4
1
1
2
3
6
6.
2,3
2
3
6.
Movers move furniture
4, 6
2
Riggers move lab equipment
Movers move computers
Install computers, telephones
Install lab equipment
Faculty set up new offices
Department ready
2
4
6.
9.
2
10
9
2
8.
11
8
3
4
7, 10
11, 12
12
3
9
13
Expert Solution

This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
This is a popular solution!
Trending now
This is a popular solution!
Step by step
Solved in 5 steps with 5 images

Recommended textbooks for you

Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,

Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education

Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education

Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,

Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education

Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education


Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning

Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.