Part 1: For the activities, duration, and sequence shown in the table below, prepare a Gantt chart with details. Activity Activity Description Depends Level Duration Code (Day) on 100 Inspect the machine after installation 300 1 200 Hire the operator None 1 25 300 Install the new machine 500,400 3 2 Insect and store the machine after delivery 400 700 1 500 Hire labor to install the new machine None 1 20 600 Train the operator 200,300 4 3
Q: You are alone at home and have to prepare a bread sandwich for yourself. The following preparation…
A: Find the Given details below: Given Details Task Descriptions Predecessor Time(Mins) A…
Q: The City Commission of Nashville has decided to build a botanical garden and picnic area in the…
A: Gantt chart is a visual representation of a network diagram which helps to identify the starting and…
Q: Define each of these terms, and indicate how each is determined.a. Expected activity time
A: Expected Activity time is calculated for anticipating the approximate time in which any activity…
Q: Slack time for each of the activities is?
A: A network diagram is the set sequence of the task that is done to complete a project. It usually…
Q: a-b) One of the possible assignment of tasks to workstations is shown correctly in Fig. 2 The…
A: Project schedule helps in calculating different values all related to the production cycle like the…
Q: Dave's latest start (LS) and latest finish (LF) are: Activity H LS 13 LF
A: Steps to find LS and LF: Start from the end and take LF same as EF of the ending activity, that is,…
Q: Given the following information, answer the following: Task Description Immediate predecessors…
A: 1. The total cost required for completing this project on normal time will be the total sum of costs…
Q: Managed by Q case wage analysis: Cleaning operators and handymen are two of the most important jobs…
A: A job description is a written statement of the obligations, specifications, and criteria of a…
Q: 1.The chief engineer of firm XYZ is responsible for supervising the construction work of a road. He…
A: Network diagramEdge and its preceded and succeeded node Edge Node1 → Node2 B 1→2 A 1→3 C…
Q: what is the diagram for the below table? task performance
A:
Q: Task Task Description Predecessors Time estimate (in minutes) te σ2 to tm tp A Slice the…
A: Drawing a network diagram can help in identifying the critical path and the critical activities…
Q: You and several friends are about to prepare a lasagna dinner. The tasks to be performed, their…
A: Note: - Since we can answer only up to three subparts we will answer the first three subparts(1, 2,…
Q: What is The Critical Path and Time (day)
A:
Q: Ising the line drawing tool, draw a Gart chart for activities E through I of the roiect
A: THE ANSWER IS AS BELOW:
Q: Normal Time Problem 1 You are the manager of a project to improve a billing process at your firm.…
A: Finding the Optimum Project Duration with Crashing and Penalty Costs: A Step-by-Step GuideIn project…
Q: Managed by Q case wage analysis: Cleaning operators and handymen are two of the most important jobs…
A: Wage analysis is the process of evaluating and comparing pay rates for various jobs or roles within…
Q: Activity Predecessor Activities Normal Crashed Duration (Days) Cost ($) Duration…
A: ES indicating Early Starting time for an activity and LS indicating the latest starting time.…
Q: 9. A work operation consisting of three (3) elements has been subjected to a time study. The…
A: Note: - Since the exact question that has to be answered is not specified we will answer the first…
Q: Stage 2 General Mathematics - Summative Discrete Models Test 1. Nine activities are needed to…
A: The relationships and dependencies between the tasks or activities of a project are graphically…
Q: b) The critical activities for the leadership training program development project are c) The…
A: Project duration is the total time taken to complete the project successfully measurable in days or…
Q: a. Find the critical path.
A: A network diagram is a visual representation of a project which identifying the activity…
Q: a-b) One of the possible assignment of tasks to workstations is shown correctly in Fig. 2 . The…
A: A project schedule network diagram shows the sequential and analytical connection between tasks in a…
Q: Roger Ginde is developing a program in supply chain management certification for managers. Ginde has…
A: Note: - Since we can answer only up to 3 subparts, we will answer only the first three subparts(a,…
Q: a. Construct a network for this problem. b. Determine the expected time and variance for each…
A: D(duration)=given in the question as normal time ES (Early start)= The first activity from where the…
Q: An assembly task was broken down into four elements, and timed using the continuous timing method.…
A: The Standard Time is the result of three variables: Observed time: The time estimated to do the job.…
Q: • 3.8 management certification for managers. Ginde has listed a num- ber of activities that must be…
A: "Since you have posted a question with multiple sub-parts, we will solve first three sub-parts for…
Q: Which activity has the highest slack time
A: When it comes to managing projects with precision, understanding the mechanics of "slack…
Q: Power Builders Inc. is planning for an upcoming job with a large client. They have listed the…
A: Given data is
Q: What can be adjusted to reduce the overall scheduled duration of an activity? 1. Manpower 2.…
A: Scheduling is an important aspect of project management, and it involves creating a plan that…
Q: Draw Gantt Chart
A: THE ANSWER IS AS BELOW:
Q: What is the total project completion time? Round your answer to the nearest whole number. ___…
A:
Q: 1. For an activity (A, determine the slope. Activity A Normal Time 8 Cost 6000 Time 4 Crash Cost…
A: Slope of the line which passes through (x1,y1) & (x2,y2) is given as m=(y2-y1)/(x2-x1)
Trending now
This is a popular solution!
Step by step
Solved in 2 steps with 3 images
- 11. Draw an arrow diagram that depicts the logic for finishing work on a house project, as described below: Activity ABCDEFGHLIKIN M Activity Description Mobilize Paint walls and ceiling Vinyl floor in kitchen and laundry room Ceramic floor in bathroom Wallpaper in bathroom and kitchen Set kitchen appliances Install wall-hung mirror Hang prefab kitchen cabinets Set bath fixtures Install base trim Lay carpet in living room, etc. Touch up paint Demobilize Dependent on Activity | ARRACH B AUT C, E H, I F, J G, K L4.What is the probability that it would be in more than 14 days? Show ALL of your work.5) We offered 50% of our drivers monetary bonuses to increase their activity. Compare the results with the control group and explain if the campaign was successful and should we do it again or not. Condition: Stay online 30 hours and accept 75% of rides. Get 70€ bonus. Control Group Online hours Offline hours Bookings received Bookings successfully completed Bonus Group Online hours Offline hours Bookings received Bookings successfully completed Write here your answer about the results of the campaign Driver 1 15 35 15 13 Driver 55 33 19 29 25 Driver 2 29 21 30 Driver 56 5 55 6 6 Driver 3 17 23 12 10 Driver 57 32 8 19 16 Driver 4 31 19 31 26 Driver 58 32 18 29 26 Driver 5 36 24 44 24 Driver 59 38 22 20 17 Driver 6 14 26 10 12 Driver 60 17 23 10 9 Driver 7 5 40 5 4 Driver 61 4 46 3 3 Driver…
- Information for the Time-Cost Model Exercise Crash Normal Immediate Normal Time Crash Crash cost Task Time Cost Predecessors (weeks) Cost per week (weeks) NONE 3 $5,000 $13,000 $8,000 4 $10,000 $20,000 $5.000 A 17 $6,000 $6,000 D. 6 $4,000 $8,000 $2,000 B&C 9. $4,000 $9,000 $2,500 D&E 4 $5,000 $9,000 $4,000 G. F 3. $3,000 $6.000 $3,000 Your firm needs to find a new supplier for a key raw material. The table below lists the steps that need to be complete. Due to unforeseen issues, you need to expedite the project in order to continue to supply your customers with the finished product you are producing with this key raw material. What is the duration of the project after all crashing is complete? 25 23 24 O 22TOYS AND JOB DESIGN AT THE HOVEY AND BEARD COMPANY The following is a situation that occurred in the Hovey and Beard Company, as reported by J. V. Clark. This company manufactured a line of wooden toys. One part of the process involved spray painting partially assembled toys, after which the toys were hung on moving hooks that carried them through a drying oven. The operation, staffed entirely by women, was plagued with absenteeism, high turnover, and low morale. Each woman at her paint booth would take a toy from the tray beside her, position it in a fixture, and spray on the color according to the required pattern. She then would release the toy and hang it on the conveyor hook. The rate at which the hooks moved had been calculated so that each woman, once fully trained, would be able to hang a painted toy on each hook before it passed beyond her reach. The women who worked in the paint room were on a group incentive plan that tied their earnings to the…2. CH 10: The table below includes the time (in minutes) that it took a worker to complete a single task that an analyst collected while performing a stopwatch time study. Use the information provided in this table to answer the following questions. You must show your work for credit, and please round all answers to two (2) decimal places. Observation Time 1 2 2 2.5 3 2 4 3 5 3.5 If the worker observed was 10% faster than average, what is the normal time? If an allowance factor of 15% of the workday is used, what is the standard time? 6 2
- A time study was conducted on a job that contains four elements. The observed times and performance ratings for six cycles are shown in the following table. Element 1 2 3 4 Performance Rating 95% 90 125 110 1 0.46 1.46 0.81 1.06 Element 1 2 3 4 Click here for the Excel Data File Element 1 2 OBSERVATIONS (minutes per cycle) Average cycle 2 0.51 1.46 0.81 1.11 a. Determine the average cycle time for each element. (Round your answers to 3 decimal places.) Normal time 3 0.41 1.41 0.71 1.06 4 5 6 0.41 0.41 0.41 1.41 1.41 1.46 0.76 0.81 0.76 1.11 1.11 1.16 b. Find the normal time for each element. (Round your answers to 3 decimal places.)please answer within 30 minutes.help please
- State and describe some of the limitations of time study method ?List - BUS-2353-05W (Sprin X D21 Quizzes - BUS-2353-05W (Spring X + frame_auto.d21?ou=23288&isprv=&drc=0&qi=79747&cfql=0&dnb=0&fromQB=0&in Progress=0 353 Program Assessment G502 Joshua Miller: Attempt 1 Time Taken:0:25:25 Question 1 (1 point) ✓ Saved E Listen XYZ Company determined that it needed to improve upon productX, and do a better job of getting the word out. The marketing staff decided to create a new and improved packaging, place the product in various outlets, use the mediums of radio, TV and social media and make sure their pricing was competitive. Consumers that were specifically chosen were women 30 years of age who were of Hispanic descent and worked outside of the home. These women had also used the product before however the product has been redesigned. Often these women purchased in bulk for their families. Prior to determining who they would work with and how they would redesign the product, XYZ Company created surveys, held in-store demonstrations and took various…Latisha Simmons, a loan processor at Wentworth Bank, has been timed performing four work elements, with the results shown in the following table. Task Element 1 2 3 4 Performance Rating 110% 85% 90% 85% 1 0.6 0.6 0.5 1.4 Observation (minutes per cycle) 2 3 4 0.3 0.8 0.5 1.9 0.6 0.7 0.6 1.9 0.4 0.6 0.5 1.7 The allowances for tasks such as this are personal, 8%; fatigue, 12%; and delay, 3%. minutes (round your response to two a) The normal time for the complete operation : = decimal places). b) The standard time for this process = minutes (round your response to two decimal places). 0.5 0.8 0.5 1.4