) Based on the given information regarding the activities for the project, the project length = ) The total cost required for completing this project on normal time = $ ) For reducing the duration of the project by one week, the activity that should be crashed first is activity The cost of the project based on the first activity selected for crashing will increase by $ weeks.

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
Development of Version 2.0 of a particular accounting software product is being considered by Jose​ Noguera's technology firm in Baton Rouge. The activities necessary for the completion of this project are listed in the following​ table:
                                                                                                                                
Activity
Normal Time​ (weeks)
Crash Time​ (weeks)
Normal Cost
Total Cost with Crashing
Immediate​ Predecessor(s)
A
4
3
$2,100
$2,750
B
2
1
$2,300
$3,100
C
3
3
$600
$600
D
8
4
$2,400
$2,720
A
E
6
3
$1,000
$1,450
B
F
3
2
$3,000
$4,400
C
G
4
2
$1,500
$2,000
​D, E
 
​a) Based on the given information regarding the activities for the​ project, the project length​ =
enter your response here
weeks.
 
​b) The total cost required for completing this project on normal time​ =
​$enter your response here.
 
​c) For reducing the duration of the project by one​ week, the activity that should be crashed first is activity
 
A
B
C
D
E
F
G
.
 
The cost of the project based on the first activity selected for crashing will increase by
​$enter your response here.

 

Development of Version 2.0 of a particular accounting software product is being considered by Jose
Noguera's technology firm in Baton Rouge. The activities necessary for the completion of this project are
listed in the following table:
Activity
ABCDEFG
Normal Time Crash Time Normal
Cost
(weeks)
4
A W ∞ W N
3
8
6
3
4
(weeks)
3
1
3
Total Cost
with
Immediate
Crashing Predecessor(s)
$2,100
$2,750
$2,300
$3,100
$600
$600
$2,400
$2,720
$1,000
$1,450
$3,000
$4,400
$1,500 $2,000
4
3
2
2
A
B
C
D, E
a) Based on the given information regarding the activities for the project, the project length =
b) The total cost required for completing this project on normal time = $
c) For reducing the duration of the project by one week, the activity that should be crashed first is activity
weeks.
The cost of the project based on the first activity selected for crashing will increase by $
Transcribed Image Text:Development of Version 2.0 of a particular accounting software product is being considered by Jose Noguera's technology firm in Baton Rouge. The activities necessary for the completion of this project are listed in the following table: Activity ABCDEFG Normal Time Crash Time Normal Cost (weeks) 4 A W ∞ W N 3 8 6 3 4 (weeks) 3 1 3 Total Cost with Immediate Crashing Predecessor(s) $2,100 $2,750 $2,300 $3,100 $600 $600 $2,400 $2,720 $1,000 $1,450 $3,000 $4,400 $1,500 $2,000 4 3 2 2 A B C D, E a) Based on the given information regarding the activities for the project, the project length = b) The total cost required for completing this project on normal time = $ c) For reducing the duration of the project by one week, the activity that should be crashed first is activity weeks. The cost of the project based on the first activity selected for crashing will increase by $
A
B
C
D
E
TI
F
G
e project bas
Transcribed Image Text:A B C D E TI F G e project bas
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 5 steps with 3 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.