Normal time 4 2 3 8 6 3 4 the cost for crashing the project by 5 days? ity Crash time Normal cost Crash cost Pre 3 1 3 4 +3~ ~ 2 2 2200 2400 500 2200 600 3600 1100 2600 2800 500 2600 1200 4200 2000

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 21P
Question
Consider the following:
Activity
A B C D E F G
с
Normal
time
4
2
3
8
6
3
4
Crash time Normal cost Crash cost Predecessor
3
1
3
4
+3~ ~
2
2
2200
2400
500
2200
600
3600
1100
What is the cost for crashing the project by 5 days?
2600
2800
500
2600
1200
4200
2000
A
B
с
D,E
Transcribed Image Text:Consider the following: Activity A B C D E F G с Normal time 4 2 3 8 6 3 4 Crash time Normal cost Crash cost Predecessor 3 1 3 4 +3~ ~ 2 2 2200 2400 500 2200 600 3600 1100 What is the cost for crashing the project by 5 days? 2600 2800 500 2600 1200 4200 2000 A B с D,E
Expert Solution
steps

Step by step

Solved in 4 steps with 1 images

Blurred answer
Similar questions
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Marketing
Marketing
Marketing
ISBN:
9780357033791
Author:
Pride, William M
Publisher:
South Western Educational Publishing
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning