The following Table 1 contains a list of activities, with precedence requirements and crash costs. All start and finish times and crash costs are on a per-week basis. Table 1 Activity Predecessor Normal Time Crash Time Normal Cost Crash Cost (Weeks) (Weeks) A 10 7 2000 2600 B A 12 8 1500 2000 A 16 12 2200 3000 D B 8 7 2500 3000 E 13 10 1950 2275 F D 9. 8 800 1000 G E, F 24 29 3650 4000 H G 17 14 1200 1800 a) Determine the project cost and duration without crashing. b) Determine the least expensive project cost if the duration is to be 10% shorter than normal project duration. c) Determine the least expensive project cost if the duration is to be 20% shorter than normal project duration.

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
The following Table 1 contains a list of activities, with precedence requirements and crash
costs. All start and finish times and crash costs are on a per-week basis.
Table 1
Activity Predecessor
Crash Time Normal Cost
(Weeks)
Normal Time
Crash Cost
(Weeks)
$
A
10
7
2000
2600
A
12
1500
2000
C
A
16
12
2200
300
D
8
7
2500
3000
E
C
13
10
1950
2275
F
D
9.
8
800
1000
G
E, F
24
29
3650
4000
H
G
17
14
1200
1800
a) Determine the project cost and duration without crashing.
b) Determine the least expensive project cost if the duration is to be 10% shorter than
normal project duration.
c) Determine the least expensive project cost if the duration is to be 20% shorter than
normal project duration.
Transcribed Image Text:The following Table 1 contains a list of activities, with precedence requirements and crash costs. All start and finish times and crash costs are on a per-week basis. Table 1 Activity Predecessor Crash Time Normal Cost (Weeks) Normal Time Crash Cost (Weeks) $ A 10 7 2000 2600 A 12 1500 2000 C A 16 12 2200 300 D 8 7 2500 3000 E C 13 10 1950 2275 F D 9. 8 800 1000 G E, F 24 29 3650 4000 H G 17 14 1200 1800 a) Determine the project cost and duration without crashing. b) Determine the least expensive project cost if the duration is to be 10% shorter than normal project duration. c) Determine the least expensive project cost if the duration is to be 20% shorter than normal project duration.
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 5 steps with 9 images

Blurred answer
Knowledge Booster
Facility layout
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.