Using the data in the table develop a work breakdown structure.
Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
Related questions
Question
The data below belongs to High Veld Construction. Using the data in the table develop a work
breakdown structure.

Transcribed Image Text:Task Name
Duration
* Construction of a house 32 days?
✓ Design
5 days?
3 days
5 days
3 days
10 days
4 days
4 days
4 days
6 days
2 days
3 days
4 days
5 days
2 days
3 days
8 days
3 days
4 days
1 day
Permits
Drawings
Quantity survaying
✔ Procurement
Electrical
Plumbing
HVAC
✔ Construction
Interior
Exterior
Fencing
✓ Inspections
Masonry Work
Building Finishes
Turnorver
Walk Thru
Closing
Hand Over
Start
Mon 1/1/24
Mon 1/1/24
Mon 1/1/24
Mon 1/1/24
Wed 1/3/24
Mon 1/8/24
Mon 1/8/24
Wed 1/10/24
Tue 1/16/24
Mon 1/22/24
Mon 1/22/24
Thu 1/25/24
Mon 1/22/24
Fri 1/26/24
Fri 1/26/24
Tue 1/30/24
Fri 2/2/24
Fri 2/2/24
Wed 2/7/24
Tue 2/13/24
Finish
Tue 2/13/24
Fri 1/5/24
Wed 1/3/24
Fri 1/5/24
Fri 1/5/24
Fri 1/19/24
Thu 1/11/24
Mon 1/15/24
Fri 1/19/24
Mon 1/29/24
Tue 1/23/24
Mon 1/29/24
Thu 1/25/24
Thu 2/1/24
Mon 1/29/24
Thu 2/1/24
Tue 2/13/24
Tue 2/6/24
Mon 2/12/24
Tue 2/13/24
Expert Solution

This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
Step by step
Solved in 3 steps with 1 images

Recommended textbooks for you

Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,

Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education

Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education

Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,

Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education

Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education


Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning

Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.