Calculate expected time, critical path, variance, standard deviation, slack time
Calculate expected time, critical path, variance, standard deviation, slack time
Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
Related questions
Question
Calculate expected time, critical path, variance, standard deviation, slack time

Transcribed Image Text:Activity
a
b
с
d
e
f
g
h
i
j
k
I
m
Xn
O
Р
q
r
S
t
u
V
W
X
END
Activity Description
Excavation
Lay foundation
Frame and roof
Lay drain tiles
Sewer (floor) drains
Install insulation
Pour basement floor
Rough plumbing, pipes
Install windows
Rough electrical wiring
Install air conditioners
Exterior brickwork
Install plasterboard, mud,
plaster
Roof shingles, flushing
Attach gutter, downspouts
Grading
Lay subflooring
Lay driveway, walks and
landscape
Finish carpentry
Kitchen cabinetry, sink and
appliances
Bathroom cabinetry,
fixtures
2
Painting the walls
Finish wood floors, lay
carpet
Final electrical and light
fixtures
Immediate
Predeces
sor
tu
a
b
b
b
с
e
e
f
f
c.g
i
i.b.k
I
n
do
m
Р р
q
q
q
VAS
V
GWX
Time Estimates
(days)
o-m-p
3-4-6
2-3-5
2-4-5
1-2-4
1-2-3
2-4-5
2-3-5
2-4-7
1-3-4
1-2-4
3-5-8
5-6-10
6-8-12
2-3-6
1-2-5
2-3-7
3-4-6
4-6-10
3-5-12
2-4-8
2-3-6
4-6-10
2-5-8
1-3-4
Expert Solution

This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
Step by step
Solved in 4 steps with 4 images

Recommended textbooks for you

Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,

Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education

Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education

Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,

Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education

Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education


Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning

Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.