ACTIVITY PREDECESSORS DURATION (DAYS) A 3 B A 4 A D B 5 1 F D,E F,G 4 3 You are required to a) Draw the network diagram b) Calculate ES, EF, LS, LT c) Calculate slack time d) Identify critical path and activities
ACTIVITY PREDECESSORS DURATION (DAYS) A 3 B A 4 A D B 5 1 F D,E F,G 4 3 You are required to a) Draw the network diagram b) Calculate ES, EF, LS, LT c) Calculate slack time d) Identify critical path and activities
Related questions
Question
Pert And CPM Analaysis

Transcribed Image Text:Question 1
ACTIVITY
PREDECESSORS
DURATION (DAYS)
A
3
B
A
4
A
2
D
B
5
E
1.
2.
G
D,E
4
H
F,G
3
You are required to
a) Draw the network diagram
b) Calculate ES, EF, LS, LT
c) Calculate slack time
d) Identify critical path and activities
Expert Solution

This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
Step by step
Solved in 3 steps with 1 images