The spreadsheet in Microsoft Excel file Ch01Ex01_U10e.xlsx contains records of employee activity on special projects. Open this workbook and examine the data that you find in the three spreadsheets it contains. Assess the accuracy, relevancy, and sufficiency of this data to the following people and problems.
- a. You manage the Denver plant, and you want to know how much time your employees are spending on special projects.
- b. You manage the Reno plant, and you want to know how much time your employees are spending on special projects.
- c. You manage the Quota Computation project in Chicago, and you want to know how much time your employees have spent on that project.
- d. You manage the Quota Computation project for all three plants, and you want to know the total time employees have spent on your project.
- e. You manage the Quota Computation project for all three plants, and you want to know the total labor cost for all employees on your project.
- f. You manage the Quota Computation project for all three plants, and you want to know how the labor-hour total for your project compares to the labor-hour totals for the other special projects.
- g. What conclusions can you make from this exercise?

Explanation of Solution
a.
Time taken by employees for completing the special project in Denver plant:
Special project at Denver involves Market Analysis, Quota computation, Sourcing review and Production planning.
- Time taken by employees for Quota computation is “22+30+17+31=100” hours.
- Time taken by employees for Market analysis is “17+21=38” hours.
- Time taken by employees for sourcing review is “9+22+10+21+5=67” hours.
- Time taken by employees for production planning is “12+15+21+35+20+19=122 hours”
Therefore, time taken by employees for completing the special project in Denver plant is “327”hours.

Explanation of Solution
b.
Time taken by employees for completing the special projects in Reno plant:
Special project at Reno plant involves Quota computation, Sourcing review and Production planning.
- Time taken by employees for Quota computation is “27+42=69” hours.
- Time taken by employees for Sourcing review is “17+23+21+27=88” hours.
- Time taken by employees for Production planning is “19+20+11=50” hours.
Therefore, the time taken by employees for completing the special project in Reno plant is “207” hours.
c.

Explanation of Solution
Time taken by employees for Quota Computation in Chicago plant:
Time taken by employees for special project at Chicago plant for Quota computation is: “27+12+22+29+11+29 = 130” hours.
Therefore, the time taken by employees for computation in Chicago plant is “130” hours.

Explanation of Solution
d.
Total time taken by employees for Quota Computation for all plants:
Time taken by employees for special project at Chicago plant, Denver plant and Reno plant for Quota computation is:
- Time taken by employees for Quota computation in Denver plant is “22+30+17+31=100” hours.
- Time taken by employees for Quota computation in Reno plant is “27+42=69” hours.
- Time taken by employees for special project at Chicago plant for Quota computation is: “27+12+22+29+11+29 = 130”hours.
Therefore, the total time taken by employees is: “100+69+130=299” hours.

Explanation of Solution
e.
Total labor cost for all employees in the Quota computation project:
- Suppose the hourly pay of an employee is “$30”.
- The number of hours worked by the employees on Quota computation project is “299” hours.
Labor cost= hourly wage × number of hours = 30 × 299 = $8970
Therefore, the total labor cost for all employees in the quota computation project is “8970$”.

Explanation of Solution
f.
Comparison of labor hour total for Quota computation with other projects:
- The total time taken by employees for Quota computation is: “100+69+130=299” hours.
- The total time taken by employees for market analysis is “38” hours.
- The total time taken by employees for sourcing review is “67+88+52=207” hours.
- The total time taken by employees for production planning is “122+75+50 =247” hours.
Thus, the ratio of Quota computation with Market analysis = 299/38=7.86 hours, the ratio of Quota computation with sourcing review = 299/207=1.44 hours, and the ratio of Quota computation with production planning = 299/247= 1.21 hours.

Explanation of Solution
g.
Conclusion:
From the above questions, it can be observed that Quota computation almost takes “37%” of the total time taken to complete all projects as compared to the projects – market analysis, sourcing review and production planning.
Therefore, it can be said that the labor employed in Quota computation project is less efficient as compared to the other three projects.
Want to see more full solutions like this?
Chapter AE Solutions
Using MIS (10th Edition)
Additional Engineering Textbook Solutions
Java: An Introduction to Problem Solving and Programming (8th Edition)
SURVEY OF OPERATING SYSTEMS
Starting Out with Python (4th Edition)
Starting Out with C++ from Control Structures to Objects (9th Edition)
Computer Science: An Overview (13th Edition) (What's New in Computer Science)
Introduction To Programming Using Visual Basic (11th Edition)
- # Find the error# Why will the following code not print out a list of contact namesphoneBook = {'Doe, Jane' : '843-000-0000' ,'Doe, John' : '843-111-1111' ,'Smith, Adam' : '843-222-2222' ,'Jobs, Steve' : '999-333-3333' ,}for contact in phoneBook.values():print(contact)arrow_forward# Find the error:# The following code creates an empty dictionary and attempts to add a record# Why will the following code not create a new dictionary entry as intended?phoneBook = {}phoneBook{'Jobs, Steve'} = '999-111-1111'arrow_forwardSelect all the possible polar representations of the vector that is obtained from rotating where by Zrot Ź x = 3e² T= 3п 8 Hint: Consider the negative angle that is equivalent to the positive angle of the rotated vector. 0arrow_forward
- Character Analysis If you have downloaded the source code you will find a file named text.txt on the Chapter 08 folder. Write a program that reads the file's contents and determines the following: The number of uppercase letters in the file The number of lowercase letter in the file The number of digits in the file The number of whitespace characters in the filearrow_forwardWrite a program that reads the text file's contents and calculates and outputs the following in this order: • The number of words in the file • The number of lines in the file • The number of uppercase letters in the file • The number of lowercase letters in the file • The number of digits in the file • The number of letter H's in the file • The number of whitespace characters in the file NOTE: Your program should include at least one try-except error handling statement block. Your program should also validate any input that could cause your program to crash. I'm Henery The Eighth, I Am! Henery The Eighth, I Am, I am!I got married to the widow next door,She's been married seven times before.And ev'ryone was a Henery,She wouldn't have Willie or a Sam.I'm her eighth old man named Henery,Henery the Eighth, I Am!Second verse same as the first!I'm Henery The Eighth, I Am! Henery The Eighth, I Am, I am!I got married to the widow next door,She's been married seven times before.And…arrow_forwardFigure 4-40 Modern Database Management, 13th edition, question 4-53arrow_forward
- Which of the following needs improvement in the dashboard shown? A. Instructional clarity missing for the views B. Filter placed at the top of the dashboard C. Inconsistent use of colors to represent missed goals D. Dashboard title too largearrow_forwardIf we click Show dashboard title in this dashboard, what will the title be?arrow_forwardPlease draw the diagram where it is asked to be drawn. Don't just describe how to do it.arrow_forward
- C. Homework Assignment Task: Write a one-page CV using the provided template. Steps: 1. Use the CV guide to structure your CV. 2. Fill in each section with real information about yourself. 3. Format your CV neatly and use professional language. 4. Submit to the instructor before the next classarrow_forwardSimulate on a vertical time axis (with events labeled with the senders names A-D) the contention period of FOUR equally distanced Ethernet stations that all attempt to transmit at T=0 a minimally sized frame, in the style of the binary Exponential Backoff Algorithm. Assume that time is measured in slot times, and that exactly one slot time is needed to detect a collision (so that if two stations transmit at T=1 and collide, and one of them chooses a backoff time k=0, then that station will transmit again at T=2). Use as coin flip (source of randomness) an ID written in binary. use the bits in order from the least significant to the most significant. If for a given coin throw you need k bits, use the least significant ID bit extracted in the corresponding group of bits, as the least significant bit of the coin thrown. Start be writing the ID, which is 904012207 As example of the expected answer format, with the random sequence R: 100101010101001011001010 01 01011 10010 1010 1010 010…arrow_forwardBig State University The Big State University course catalog reads as follows: "To enroll in MIS 260, which is an advanced course, a student must complete two prerequisites: MIS 120 and MIS 222. A student who completes either one of these prerequisites and obtains the instructor's permission, however, will be allowed to take MIS 260." Tasks 1. Create a decision table that describes the Big State University course catalog regarding eligibility for MIS 260. Show all possible rules. 2. Simplify the table you just created. Describe the results. 3. Draw a simplified decision tree to represent the Big State University catalog. Describe the results. 4. Why might you use a decision tree rather than a decision table?arrow_forward
- Np Ms Office 365/Excel 2016 I NtermedComputer ScienceISBN:9781337508841Author:CareyPublisher:CengageDatabase Systems: Design, Implementation, & Manag...Computer ScienceISBN:9781305627482Author:Carlos Coronel, Steven MorrisPublisher:Cengage Learning
- Database Systems: Design, Implementation, & Manag...Computer ScienceISBN:9781285196145Author:Steven, Steven Morris, Carlos Coronel, Carlos, Coronel, Carlos; Morris, Carlos Coronel and Steven Morris, Carlos Coronel; Steven Morris, Steven Morris; Carlos CoronelPublisher:Cengage LearningA Guide to SQLComputer ScienceISBN:9781111527273Author:Philip J. PrattPublisher:Course Technology Ptr