Illinois Furniture, Inc., produces all types of office furniture. The “Executive Secretary” is a chair that has been designed using ergonomics to provide comfort during long work hours. The chair sells for $130. There are 480 minutes available during the day, and the average daily demand has been 50 chairs. There are eight tasks:
a) Draw a precedence diagram of this operation.
b) What is the cycle time for this operation?
c) What is the theoretical minimum number of workstations?
d) Assign tasks to workstations.
e) What is the idle time per cycle?
f) How much total idle time is present in an 8-hour shift?
g) What is the efficiency of the assembly line, given your answer in (d)?
a)

To draw: The precedence diagram.
Answer to Problem 13P
Explanation of Solution
Given information:
Task | Time (minutes) | Immediate predecessors |
A | 4 | - |
B | 7 | - |
C | 6 | A, B |
D | 5 | C |
E | 6 | D |
F | 7 | E |
G | 8 | E |
H | 6 | F, G |
Total | 49 |
- The chair is sold for $130.
- Number of minutes available = 480 / day.
- Average daily demand is 50 chairs.
Precedence diagram:
b)

To determine: The cycle time.
Introduction:
Cycle time:
Cycle time is the total time taken to complete an unit of work from the beginning of the process to the end of the process.
Answer to Problem 13P
The cycle time is 9.6 minutes / unit.
Explanation of Solution
Given information:
Task | Time (minutes) | Immediate predecessors |
A | 4 | - |
B | 7 | - |
C | 6 | A, B |
D | 5 | C |
E | 6 | D |
F | 7 | E |
G | 8 | E |
H | 6 | F, G |
Total | 49 |
- The chair is sold for $130.
- Number of minutes available = 480 / day.
- Average daily demand is 50 chairs.
Formula to calculate cycle time:
Calculation of cycle time:
The cycle time is 9.6 minutes / unit.
c)

To determine: The theoretical minimum number of workstations.
Answer to Problem 13P
The theoretical minimum number of workstations is 6 workstations.
Explanation of Solution
Given information:
Task | Time (minutes) | Immediate predecessors |
A | 4 | - |
B | 7 | - |
C | 6 | A, B |
D | 5 | C |
E | 6 | D |
F | 7 | E |
G | 8 | E |
H | 6 | F, G |
Total | 49 |
- The chair is sold for $130.
- Number of minutes available = 480 / day.
- Average daily demand is 50 chairs.
Formula to calculate theoretical minimum number of workstations:
Calculation of theoretical minimum number of workstations:
The theoretical minimum number of workstations is 6 workstations.
d)

To assign: The different tasks to different workstations.
Explanation of Solution
Assignment of different tasks to different workstations:
Task A is assigned to station 1. Task B is assigned to station 2. Task C is assigned to station 3. Task D is assigned to station 4. Task E is assigned to station 5. Task G is assigned to station 6. Task F is assigned to station 7. Task H is assigned to station 8.
e)

To determine: The idle time per cycle.
Answer to Problem 13P
The idle time is 15 minutes / cycle.
Explanation of Solution
Given information:
Task | Time (minutes) | Immediate predecessors |
A | 4 | - |
B | 7 | - |
C | 6 | A, B |
D | 5 | C |
E | 6 | D |
F | 7 | E |
G | 8 | E |
H | 6 | F, G |
Total | 49 |
- The chair is sold for $130.
- Number of minutes available = 480 / day.
- Average daily demand is 50 chairs.
Calculation of idle time per cycle:
The idle time is 15 minutes / cycle.
f)

To determine: The total idle time present in an 8 hour shift.
Answer to Problem 13P
The total idle time present in an 8 hour shift is 15 hours.
Explanation of Solution
Given information:
Task | Time (minutes) | Immediate predecessors |
A | 4 | - |
B | 7 | - |
C | 6 | A, B |
D | 5 | C |
E | 6 | D |
F | 7 | E |
G | 8 | E |
H | 6 | F, G |
Total | 49 |
- The chair is sold for $130.
- Number of minutes available = 480 / day.
- Average daily demand is 50 chairs.
Calculation of total idle time present in an 8 hour shift:
There are 480 minutes available in a day. The longest operation time is 8 minutes. Therefore the number of cycles in a day is given by:
The total idle time is calculated by multiplying the number of cycles with the total idle time per cycle.
The total idle time present in an 8 hour shift is 15 hours.
g)

To determine: The efficiency.
Introduction:
Efficiency:
Efficiency is the measure of what is actually produced as opposed to what can be theoretically produced with the same amount of resources.
Answer to Problem 13P
The efficiency is 76.6%.
Explanation of Solution
Given information:
Task | Time (minutes) | Immediate predecessors |
A | 4 | - |
B | 7 | - |
C | 6 | A, B |
D | 5 | C |
E | 6 | D |
F | 7 | E |
G | 8 | E |
H | 6 | F, G |
Total | 49 |
- The chair is sold for $130.
- Number of minutes available = 480 / day.
- Average daily demand is 50 chairs.
Formula to calculate efficiency:
Calculation of efficiency:
The efficiency is 76.6%
Want to see more full solutions like this?
Chapter 9 Solutions
Principles Of Operations Management
- what is an other difination for principle?arrow_forwardNeed help or ideas to design out two slides as my script and writing quite long to squeese into two slides. But can just point form in slides with correct title and a good script for me to present two slides in only 2.5 mins. Following is my draft, pls guide me step by step on powerpoint creation and good script to present findings. My draft: Slide 1: Foreign Labor Exploitation in Dyson's Supply Chain Introduction Dyson's former Malaysian supplier, ATA IMS Bhd, became embroiled in serious labor exploitation allegations in 2021. These concerns surfaced when whistleblowers exposed unethical labor practices affecting migrant workers, primarily from Nepal and Bangladesh. Key Forms of Exploitation Debt Bondage Due to Recruitment Fees Workers were forced to pay exorbitant recruitment fees before securing employment, often taking loans at high interest rates. This financial burden trapped them in debt bondage, leaving them with little choice but to accept exploitative working…arrow_forwardNot use ai pleasearrow_forward
- The Business Development Bank of Canada. (2023). Canadian economic outlook for 2024: Shifting into neutral. https://www.bdc.ca/en/articles-tools/blog/canadian-economic-outlook-for-2024-shifting-into-neutral “Despite persistently high inflation and rising interest rates, the news was generally better than expected for the Canadian economy in 2023” (BDC Blog 2024). Discussion Question: In your view, what are the most pressing problems for Canadian companies or consumers in 2024? Explain your answer using current examples of companies or consumer concerns.arrow_forwardhow have idividual objectives led to the current situation at TeraCog? what should Emaa do?arrow_forwardCan you write me an email about addressing an issue to mentor my supervisor the right way of deligating operations dutiesarrow_forward
- Can you right me an email about addressing an issue to mentor the right why of deligating operations dutiesarrow_forwardDefine delegation. Discuss in detail the four reasons why managers do delegation? Also statethe four main types of delegation.arrow_forwardB) Going forward, is Lean/JIT worth the risks? Should it be embraced (why?), abandoned (if so, why & what are the costs), or modified (how?) Do you think Lean works or not? Please write a complete response (about 1-2 paragraphs each part). Each team member should discuss and contribute so that the group agrees on their joint response. Please help each other and build upon and/or challenge others' points (in a respectful way!)arrow_forward
- Discuss the principle reasons that employee benefits have risen over the past 20 years, along with how best an organization can provide employees with a fair wage yet also provide some level of employee benefit coverage.arrow_forwardPlease assist with the Case Study below as attached. Read the case study below and answer the questions that follow. The Importance of the Planning Phase to Project Success. Traditional wisdom is that planning and analysis are very important and the more there is in a project, the more successful the project will be. Time spent on these activities will reduce risk and increase project success. On the other hand, inadequate analysis and planning will lead to a failed project. If poor planning has led to failed projects, then perhaps billions of dollars have been lost. But how much is too much? “Light weight” project management techniques such as agile are gaining popularity. Part of their ethos is that less initial planning is better and an evolutionary process is more efficient. QUESTION 1 The article above states: “Traditional wisdom is that planning and analysis are very important and the more there is in a project, the more successful the project will be”. Describe FIVE (5) ways…arrow_forwardOn a daily basis, the van is dispatched from Maplewood Hospital to pickup blood and platelet donations made at its local donation centers. The distances in miles between all locations may be found in the table below. Click the icon to view mileage data for Vampire Van. a. The van travels from the Hospital (A) to (B) to (C) to (D) to (E) and then returns to the Hospital (A). What is the total number of miles that the van must travel using this route? Route ABCDEA requires a total distance of 20.4 miles. (Enter your response rounded to one decimal place.) b. Using Maplewood Hospital as the beginning location, create a route using the Nearest Neighbor heuristic. What is the total number of miles that the van must travel using this route? The new route is A A and requires a total distance of miles. (Enter your response rounded to one decimal place.) More Info Maplewood City Center Westbrook Hospital (A) Donation Site (B) Donation Site (C) Municipal Park Donation Site (D) Valley Hills…arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,MarketingMarketingISBN:9780357033791Author:Pride, William MPublisher:South Western Educational Publishing
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningManagement, Loose-Leaf VersionManagementISBN:9781305969308Author:Richard L. DaftPublisher:South-Western College Pub