Principles Of Operations Management
11th Edition
ISBN: 9780135173930
Author: RENDER, Barry, HEIZER, Jay, Munson, Chuck
Publisher: Pearson,
expand_more
expand_more
format_list_bulleted
Concept explainers
Question
Chapter 9, Problem 18P
a)
Summary Introduction
To draw: The precedence diagram and assign tasks to 5 workstations.
b)
Summary Introduction
To determine: The efficiency.
Introduction:
Efficiency:
Efficiency is the measure of what is actually produced as opposed to what can be theoretically produced with the same amount of resources.
c)
Summary Introduction
To determine: The theoretical minimum number of workstations.
d)
Summary Introduction
To determine: The idle time per boat.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
How do mixed-model assembly lines differ from traditional assembly lines? What additional decisions arerequired?
A manufacturing plant has the process displayed below. The drilling operation occurs separately from and simultaneously with the sawing and sanding operations. The product only needs to go through one of the three one of the three assembly operations (the assembly operations are ‘parallel’). Use diagram titled "q3" attached as an image
a) What is the bottleneck operation?
b) What is the throughput time for the overall system?
c) If the firm operates 10 hours a day, 21 days a month, what is the monthly and yearly capacity of the manufacturing process?
d) Supposed that a second drilling machine is added, and it takes the same time as the original drilling machine. What is the new bottleneck time of the system?
e) What is the new throughput time if the second drilling machine is added?
f) What is the new hourly capacity if the second drilling machine is added?
A firm that produces electric golf carts has just received an order for 200 carts, which must be ready for delivery at the start of week 8. Information concerning the product structure, lead times, and quantities on hand is shown in the following table. Use this information to do each of the following:
a. Construct an assembly time chart in Excel.
Chapter 9 Solutions
Principles Of Operations Management
Ch. 9 - Prob. 1EDCh. 9 - Prob. 1DQCh. 9 - Prob. 2DQCh. 9 - Prob. 3DQCh. 9 - Prob. 4DQCh. 9 - Prob. 5DQCh. 9 - Prob. 6DQCh. 9 - Prob. 7DQCh. 9 - Prob. 8DQCh. 9 - Prob. 9DQ
Ch. 9 - Prob. 10DQCh. 9 - Prob. 11DQCh. 9 - Prob. 12DQCh. 9 - Prob. 13DQCh. 9 - Prob. 14DQCh. 9 - Prob. 15DQCh. 9 - Prob. 16DQCh. 9 - Prob. 17DQCh. 9 - Prob. 18DQCh. 9 - Prob. 1PCh. 9 - Prob. 2PCh. 9 - Prob. 3PCh. 9 - Roy Creasey Enterprises, a machine shop, is...Ch. 9 - Adam Munson Manufacturing, in Gainesville,...Ch. 9 - Prob. 6PCh. 9 - Prob. 7PCh. 9 - Prob. 8PCh. 9 - Prob. 9PCh. 9 - Six processes are to be laid out in six areas...Ch. 9 - Stanford Rosenberg Computing wants to establish an...Ch. 9 - Illinois Furniture, Inc., produces all types of...Ch. 9 - Prob. 14PCh. 9 - The Action Toy Company has decided to manufacture...Ch. 9 - Prob. 16PCh. 9 - Prob. 17PCh. 9 - Prob. 18PCh. 9 - Prob. 19PCh. 9 - Prob. 20PCh. 9 - Prob. 21PCh. 9 - Prob. 22PCh. 9 - Prob. 23PCh. 9 - Prob. 25PCh. 9 - Prob. 26PCh. 9 - Prob. 27PCh. 9 - Prob. 1CSCh. 9 - Prob. 2CSCh. 9 - Henry Coupe, the manager of a metropolitan branch...Ch. 9 - Prob. 4CSCh. 9 - Prob. 1.1VCCh. 9 - Prob. 1.2VCCh. 9 - Prob. 1.3VCCh. 9 - Prob. 1.4VCCh. 9 - Prob. 1.5VCCh. 9 - Prob. 1.6VCCh. 9 - Prob. 2.1VCCh. 9 - Prob. 2.2VCCh. 9 - Prob. 2.3VC
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- What are advantages and disadvantages of work cells? What is a heuristic? Name several that can be used in assembly-line balancing.arrow_forwardThe Mach 10 is a one-person sailboat manufactured by Creative Leisure. The final assembly plant is in Cupertino, California. The assembly area is available for production of theMach 10 for 200 minutes per day. (The rest of the time it is busy making other products.) The daily demand is 60 boats. Given the information in the table on the next page,a) Draw the precedence diagram and assign tasks using five workstations .b) What is the efficiency of the assembly line, using your answer to (a)?c) What is the theoretical minimum number of workstations?d) What is the idle time per boat produced?arrow_forwardcan answer thisarrow_forward
- The following tasks are to be performed on an assembly line: TASK ABCDEFGH SECONDS 30 Cycle time 16 21 15 17 14 20 9 Number of workstations. TASKS THAT MUST PRECEDE The workday is 8 hours long. Demand for completed product is 900 per day. a. Find the cycle time required to meet the desired output rate. (Round your answer to 1 decimal place.) 51.0 seconds per unit Work Station A B b. What is the theoretical number of workstations required to meet the desired output rate? (Round up yo number.) Task C D E, F d. Balance the line using sequential restrictions and the longest-operating-time rule. (Leave no cells blar wherever required. Round your answers to 1 decimal place.) Idle Timearrow_forwardSITUATION: A company is about to begin production of a new product. The manager of the department that will produce one of the components for the product wants to know how often the machine used to produce the item will be available for other work. The machine will produce the item at a rate of 200 units a day. Eighty units will be used daily in assembling the final product. Assembly will take place five days a week, 50 weeks a year. The manager estimates that it will take almost a full day to get the machine ready for a production run, at the cost of $300. Inventory holding costs will be $10 a year. QUESTION: Suppose the manager decides to increase the run size of the new product. How many additional units would be needed just to accommodate the other job? How much will that increase the total annual cost?arrow_forwardA paced assembly line has been devised to manufacture calculators, as the following data show: LOADING... Station Work Element Assigned Work Element Time (min) S1 A 4.0 S2 D, E 0.9, 1.5 S3 C 5.0 S4 B, F, G 1.1, 1.0, 1.3 S5 H, I, J 1.1, 0.5, 1.8 S6 K 4.0 a. What is the maximum hourly output rate from this line? (Hint: The line can only go as fast as its slowest workstation.) The maximum hourly output rate is nothing calculators per hour. (Enter your response as an integer.) B. What cycle time corresponds to this maximum output rate? C. If a worker is at each station and the line operates at this maximum output rate, how much idle time is lost during each? 10-hour shift? D. What is the line's efficiency?arrow_forward
- . Kiko Teddy Bear is a manufacturer of stuff ed teddy bears.Kiko would like to be able to produce 40 teddy bears per hour onits assembly line. Use the information provided in Table 10-20 toanswer the questions that follow (a) Draw a precedence diagram.(b) What is the cycle time?(c) What is the theoretical minimum number of stations?(d) Assign tasks to specifi c workstations using the cycle timeyou computed in part (b).(e) What are the effi ciency and balance delay of the line?(f) Which task is the bottleneck?(g) Compute the maximum outputarrow_forwardA company is setting its assembly line for producing bicycles. Information corresponding to the steps is below: Work Element Label A B Check C D E Align Frame on Workstation Answer: 4.82 Assemble Handle Bar Assemble Gears and Pedals Assemble Wheels Tune the bicycle Precedence Time (Min) A A с B, D 4.2 2.2 2.4 1.5 Assume that the assembly line runs 40 hours per week. What is the desired cycle time (a.k.a. takt time) in MINUTES if the company decides that it wants to be able to produce 498 bicycles per week on this assembly line? 1.9 Round your answer to 2 decimal places and do not list the units. For example, answer like 2.34 and NOT 2.34 minutes.arrow_forwardT. Smunt Manufacturing Corp. has the process displayed below. The drilling operation occurs separately from and simultaneously with the sawing and sanding operations. The product only needs to go through one of the three assembly operations (the assembly operations are “parallel”). See attached image with outline a. Which operation is the bottleneck? b. What is the throughput time (time from start to finish for one unit) of for the overall system? c. If the firm operates 8 hours per day, 22 days per month, what is the monthly capacity of the manufacturing process? d. Suppose that a second drilling machine is added, and it takes the same time as the original drilling machine. What are the new bottleneck operation and the bottleneck time? e. Suppose that a second drilling machine is added, and it takes the same time as the original drilling machine. What is the new throughput time? f. Suppose that a second drilling machine is added, and it takes the same time as the…arrow_forward
- Please answer all sub-parts questionarrow_forwardA paced assembly line has been devised to manufacture calculators, as the following data show: Station Work ElementAssigned Work ElementTime (min) S1 S2 S3 S4 S5 S6 A D,E C B,F,G H,I,J K 2.7 0.6, 0.9 3.0 0.7, 0.7, 0.9 0.7, 0.3, 1.2 2.4 a. What is the maximum hourly output rate from this line? (Hint: The line can go only as fast as its slowest workstation.)b. What cycle time corresponds to this maximum output rate?c. If a worker is at each station and the line operates at this maximum output rate, how much idle time is lost during each 10-hour shift?d. What is the line’s efficiency?arrow_forwardYou've just been assigned the job of setting up an electric fan assembly line with the following tasks and precedence relationships The assemtly line wil be nunning 8 hours per day and 5 days per week, The demand forast is 600 Items per week. Your goal is to minimie the numbor of workstations necesary to complete enough units to satisfy the demand forecast. What is the takt time (in minutes) needed to produce the required number of units? (Integer Answer, do not put anything other than numbers.) What is the theoretical minimum number of workstations that you will need (apply the round-up rule)? (Integer Answer, do not put anything other than numbers.)arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY