a)
To draw: The precedence diagram.
a)

Answer to Problem 20P
Explanation of Solution
Given information:
Task | Time (minutes) | Immediate predecessors |
A | 3 | - |
B | 6 | - |
C | 7 | A |
D | 5 | A, B |
E | 2 | B |
F | 4 | C |
G | 5 | F |
H | 7 | D, E |
I | 1 | H |
J | 6 | E |
K | 4 | G, I, J |
Total | 50 |
- Number of hours / day is 24
- Output is 96 instruments / day.
Precedence diagram:
b)
To determine: The cycle time.
Introduction:
Cycle time:
Cycle time is the total time taken to complete an unit of work from the beginning of the process to the end of the process.
b)

Answer to Problem 20P
The cycle time is 15 minutes / unit.
Explanation of Solution
Formula to calculate cycle time:
Calculation of cycle time:
The cycle time is 15 minutes / unit.
c)
To determine: The production rate.
c)

Answer to Problem 20P
The production rate is 144 units / day.
Explanation of Solution
Given information:
Cycle time = 10 minutes
Formula to calculate production rate:
Calculation of cycle time:
The production rate is 144 units / day.
d)
To determine: The theoretical minimum number of workstations.
d)

Answer to Problem 20P
The theoretical minimum number of workstations is 5 workstations.
Explanation of Solution
Given information:
Cycle time = 10 minutes
Formula to calculate theoretical minimum number of workstations:
Calculation of theoretical minimum number of workstations:
The theoretical minimum number of workstations is 5 workstations.
e)
To determine: The efficiency.
Introduction:
Efficiency:
Efficiency is the measure of what is actually produced as opposed to what can be theoretically produced with the same amount of resources.
e)

Answer to Problem 20P
The efficiency is 83.3%.
Explanation of Solution
Given information:
Cycle time = 10 minutes
Number of workstations = 6
Formula to calculate efficiency:
Calculation of efficiency:
The efficiency is 83.3%.
f)
To determine: The total idle time per cycle.
f)

Answer to Problem 20P
The idle time is 10 minutes / cycle.
Explanation of Solution
Given information:
Number of workstations = 6
Cycle time = 10
Calculation of total idle time per cycle:
The total idle time is 10 minutes / cycle.
g)
To assign: The different tasks to different workstations and identify the efficiency.
g)

Explanation of Solution
Assignment of different tasks to different workstations:
Workstation | Elligible tasks | Selected tasks | Task time (minutes) | Available cycle time (minutes) |
1 | 10 | |||
A, B | A | 3 | 7 | |
B | B | 6 | 1 | |
1 (Idle time) | ||||
2 | 10 | |||
C, D, E | C | 7 | 3 | |
3 (Idle time) | ||||
3 | 10 | |||
D, E, F | D | 5 | 5 | |
E, F | E | 2 | 3 | |
3 (Idle time) | ||||
4 | 10 | |||
F, G, H, I | F | 4 | 6 | |
G, H, I | G | 5 | 1 | |
1 (Idle time) | ||||
5 | 10 | |||
J, H, I, K | H | 7 | 3 | |
H, I, K | I | 1 | 2 | |
2 (Idle time) | ||||
6 | 10 | |||
K, J | J | 6 | 4 | |
K | K | 4 | 0 |
Workstation | Task assigned | Idle time |
1 | A, B | 1 |
2 | C, D | 3 |
3 | D, E | 3 |
4 | F, G | 1 |
5 | H, I | 2 |
6 | J, K | 0 |
Total | 10 |
Efficiency:
Formula to calculate efficiency:
Calculation of efficiency:
The efficiency is 83.3%.
Want to see more full solutions like this?
Chapter 9 Solutions
Principles Of Operations Management
- Can you write me an email about addressing an issue to mentor my supervisor the right way of deligating operations dutiesarrow_forwardCan you right me an email about addressing an issue to mentor the right why of deligating operations dutiesarrow_forwardDefine delegation. Discuss in detail the four reasons why managers do delegation? Also statethe four main types of delegation.arrow_forward
- B) Going forward, is Lean/JIT worth the risks? Should it be embraced (why?), abandoned (if so, why & what are the costs), or modified (how?) Do you think Lean works or not? Please write a complete response (about 1-2 paragraphs each part). Each team member should discuss and contribute so that the group agrees on their joint response. Please help each other and build upon and/or challenge others' points (in a respectful way!)arrow_forwardDiscuss the principle reasons that employee benefits have risen over the past 20 years, along with how best an organization can provide employees with a fair wage yet also provide some level of employee benefit coverage.arrow_forwardPlease assist with the Case Study below as attached. Read the case study below and answer the questions that follow. The Importance of the Planning Phase to Project Success. Traditional wisdom is that planning and analysis are very important and the more there is in a project, the more successful the project will be. Time spent on these activities will reduce risk and increase project success. On the other hand, inadequate analysis and planning will lead to a failed project. If poor planning has led to failed projects, then perhaps billions of dollars have been lost. But how much is too much? “Light weight” project management techniques such as agile are gaining popularity. Part of their ethos is that less initial planning is better and an evolutionary process is more efficient. QUESTION 1 The article above states: “Traditional wisdom is that planning and analysis are very important and the more there is in a project, the more successful the project will be”. Describe FIVE (5) ways…arrow_forward
- On a daily basis, the van is dispatched from Maplewood Hospital to pickup blood and platelet donations made at its local donation centers. The distances in miles between all locations may be found in the table below. Click the icon to view mileage data for Vampire Van. a. The van travels from the Hospital (A) to (B) to (C) to (D) to (E) and then returns to the Hospital (A). What is the total number of miles that the van must travel using this route? Route ABCDEA requires a total distance of 20.4 miles. (Enter your response rounded to one decimal place.) b. Using Maplewood Hospital as the beginning location, create a route using the Nearest Neighbor heuristic. What is the total number of miles that the van must travel using this route? The new route is A A and requires a total distance of miles. (Enter your response rounded to one decimal place.) More Info Maplewood City Center Westbrook Hospital (A) Donation Site (B) Donation Site (C) Municipal Park Donation Site (D) Valley Hills…arrow_forwardView the video Noodles & Company (8.28minutes, Ctrl + Click on the link); what are your key takeaways (tie to one or more of the topics discussed in Chapters 7 & 7S – service process design, type of job design, methods analysis, work methods, job design, learning curve effect, etc.) after watching this video. https://media.gaspar.mheducation.com/GASPARPlayer/play.html?id=E5i8OKgpqhwywhgFmpp1bmM Note: As a rough guideline, please try to keep the written submission to one or two paragraphs. 2) Leland, the job analyst at Zevo Toys, wanted to perform a time study on the assembling of toys. He observed one of the workers, Magorium, for five hours. During that time, Magorium assembled 250 toys. Leland rated Magorium as performing at 110 percent. The allowance for rest, personal time, etc. at Zevo Toys is 12 percent. a) Compute the normal time for the job. b) Compute the standard time for the job. Note: You could work out the problem by hand or use excel; in chapter 7,…arrow_forward1) Noodles & Company View the video Noodles & Company (8.28minutes, Ctrl + Click on the link); what are your key takeaways (tie to one or more of the topics discussed in Chapters 7 & 7S – service process design, type of job design, methods analysis, work methods, job design, learning curve effect, etc.) after watching this video. https://media.gaspar.mheducation.com/GASPARPlayer/play.html?id=E5i8OKgpqhwywhgFmpp1bmM Note: As a rough guideline, please try to keep the written submission to one or two paragraphs. 2) Leland, the job analyst at Zevo Toys, wanted to perform a time study on the assembling of toys. He observed one of the workers, Magorium, for five hours. During that time, Magorium assembled 250 toys. Leland rated Magorium as performing at 110 percent. The allowance for rest, personal time, etc. at Zevo Toys is 12 percent. a) Compute the normal time for the job. b) Compute the standard time for the job. Note: You could work out the problem by hand or use…arrow_forward
- An investigation of career development opportunities and job satisfaction atarrow_forwardThe Donald Fertilizer Company produces industrial chemical fertilizers. The projected manufacturing requirements (in gallons) for the next four quarters are 90,000, 90,000, 60,000, and 140,000 respectively. A level workforce is desired, relying only on anticipation inventory as a supply option. Stockouts and backorders are to be avoided, as are overtime and undertime. a. Determine the quarterly production rate required to meet total demand for the year, and minimize the anticipation inventory that would be left over at the end of the year. Beginning inventory is 0. The quarterly production rate is 95000 gallons. (Enter your response as an integer.) b. Specify the anticipation inventory that will be produced. (Enter your responses as an integers.) Quarter Anticipation inventory (gallons) 1 5000 2 10000 3 4 45000 c. Suppose that the requirements (in gallons) for the next four quarters are revised to 140,000, 60,000, 90,000, and 90,000 respectively. If total demand is the same, what level…arrow_forwardPlease help with the attached Capstone proposal Requirements:arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,MarketingMarketingISBN:9780357033791Author:Pride, William MPublisher:South Western Educational Publishing
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage Learning