Principles Of Operations Management
Principles Of Operations Management
11th Edition
ISBN: 9780135173930
Author: RENDER, Barry, HEIZER, Jay, Munson, Chuck
Publisher: Pearson,
Question
Book Icon
Chapter 9, Problem 20P

a)

Summary Introduction

To draw: The precedence diagram.

a)

Expert Solution
Check Mark

Answer to Problem 20P

Principles Of Operations Management, Chapter 9, Problem 20P , additional homework tip  1

Explanation of Solution

Given information:

Task Time (minutes) Immediate predecessors
A 3 -
B 6 -
C 7 A
D 5 A, B
E 2 B
F 4 C
G 5 F
H 7 D, E
I 1 H
J 6 E
K 4 G, I, J
Total 50  
  • Number of hours / day is 24
  • Output is 96 instruments / day.

Precedence diagram:

Principles Of Operations Management, Chapter 9, Problem 20P , additional homework tip  2

b)

Summary Introduction

To determine: The cycle time.

Introduction:

Cycle time:

Cycle time is the total time taken to complete an unit of work from the beginning of the process to the end of the process.

b)

Expert Solution
Check Mark

Answer to Problem 20P

The  cycle time is 15 minutes / unit.

Explanation of Solution

Formula to calculate cycle time:

Cycle time=Number of hours per dayDaily production× Number of minutes / hour

Calculation of cycle time:

Cycle time=2496×60=1,44096=15 minutes / unit

The  cycle time is 15 minutes / unit.

c)

Summary Introduction

To determine: The production rate.

c)

Expert Solution
Check Mark

Answer to Problem 20P

The  production rate is 144 units / day.

Explanation of Solution

Given information:

Cycle time = 10 minutes

Formula to calculate production rate:

Cycle time=Number of hours per dayCycle time× Number of minutes / hour

Calculation of cycle time:

Cycle time=2410×60=1,44010=144 units / day

The  production rate is 144 units / day.

d)

Summary Introduction

To determine: The theoretical minimum number of workstations.

d)

Expert Solution
Check Mark

Answer to Problem 20P

The theoretical minimum number of workstations is 5 workstations.

Explanation of Solution

Given information:

Cycle time = 10 minutes

Formula to calculate theoretical minimum number of workstations:

Workstations=Total task timeCycle time

Calculation of theoretical minimum number of workstations:

Workstations=5010=5 workstations

The theoretical minimum number of workstations is 5 workstations.

e)

Summary Introduction

To determine: The efficiency.

Introduction:

Efficiency:

Efficiency is the measure of  what is actually produced as opposed to what can be theoretically produced with the same amount of resources.

e)

Expert Solution
Check Mark

Answer to Problem 20P

The efficiency is 83.3%.

Explanation of Solution

Given information:

Cycle time = 10 minutes

Number of workstations = 6

Formula to calculate efficiency:

Efficiency=Total task timeNumber of workstations×Cycle time×100

Calculation of efficiency:

Efficiency=506×10×100=50060=83.3%

The efficiency is 83.3%.

f)

Summary Introduction

To determine: The total idle time per cycle.

f)

Expert Solution
Check Mark

Answer to Problem 20P

The  idle time is 10 minutes / cycle.

Explanation of Solution

Given information:

Number of workstations = 6

Cycle time = 10

Calculation of total idle time per cycle:

Total idle time=(Number of workstations×Cycle time)-Total task time=(6×10)-50=60-50=10 minutes / cycle

The  total idle time is 10 minutes / cycle.

g)

Summary Introduction

To assign: The different tasks to different workstations and identify the efficiency.

g)

Expert Solution
Check Mark

Explanation of Solution

Assignment of different tasks to different workstations:

Workstation Elligible tasks Selected tasks Task time (minutes) Available cycle time (minutes)
1 10
A, B A 3 7
B B 6 1
1 (Idle time)
2 10
C, D, E C 7 3
3 (Idle time)
3 10
D, E, F D 5 5
E, F E 2 3
3 (Idle time)
4 10
F, G, H, I F 4 6
G, H, I G 5 1
1 (Idle time)
5 10
J, H, I, K H 7 3
H, I, K I 1 2
2 (Idle time)
6 10
K, J J 6 4
K K 4 0
Workstation Task assigned Idle time
1 A, B 1
2 C, D 3
3 D, E 3
4 F, G 1
5 H, I 2
6 J, K 0
Total 10

Efficiency:

Formula to calculate efficiency:

Efficiency=Total task timeNumber of workstations×Cycle time×100

Calculation of efficiency:

Efficiency=506×10×100=50060=83.3%

The efficiency is 83.3%.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
3. [25 pts.] Four projects are available for investment. The projects require the cash flows and yield the net present values (NPV) (in millions) shown in the following table. Project id. 1 2 Cash outflow at time 0 (million Lira) 8 8 NPV (million Lira) 12 11 3 4 6 5 8 6 If 20 million Lira is available for investment at time 0, find the investment plan that maximizes NPV. All investments are required to be 0 or 1 (fractional investment values are not permitted). a. Formulate the mathematical model. (Write the decision variables, objective function and the constraints.) [10 pts.] b. Find the optimal solution by using Branch and Bound method (Draw the branch and bound tree clearly, write also lower bounds(LB)) (Left branches x=0, right branches x =1) [15 pts.].
examine the production concept and operations management, what are the key steps required to achieve success?  Be specific in your response.
Produce a 3000 report with references on one international organization of your choice and Address the following: Provide a brief introduction of the organisation and sector it operates in, including its mission and vision statements, its core values, a summary of its financial performance and a general overview of the business’s operational activities. From the relevant literature explain the Total Quality Management (TQM) processes the chosen organization follows and identify one quality challenge/issue that the organization faced or is currently facing. Explain how the organization managed/or still managing the particular quality challenge/issue. Critically analyze whether the organization failed or succeeded in achieving and maintaining quality performance. Provide a few critical recommendations for business managers in order to highlight the importance of Total Quality Management (TQM) within an organization.
Knowledge Booster
Background pattern image
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
  • Text book image
    Practical Management Science
    Operations Management
    ISBN:9781337406659
    Author:WINSTON, Wayne L.
    Publisher:Cengage,
    Text book image
    MARKETING 2018
    Marketing
    ISBN:9780357033753
    Author:Pride
    Publisher:CENGAGE L
    Text book image
    Marketing
    Marketing
    ISBN:9780357033791
    Author:Pride, William M
    Publisher:South Western Educational Publishing
  • Text book image
    Purchasing and Supply Chain Management
    Operations Management
    ISBN:9781285869681
    Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
    Publisher:Cengage Learning
    Text book image
    Principles of Management
    Management
    ISBN:9780998625768
    Author:OpenStax
    Publisher:OpenStax College
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Text book image
MARKETING 2018
Marketing
ISBN:9780357033753
Author:Pride
Publisher:CENGAGE L
Text book image
Marketing
Marketing
ISBN:9780357033791
Author:Pride, William M
Publisher:South Western Educational Publishing
Text book image
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Text book image
Principles of Management
Management
ISBN:9780998625768
Author:OpenStax
Publisher:OpenStax College