Question
Book Icon
Chapter 9, Problem 2P

a)

Summary Introduction

To determine: The cost of plan A layout.

Introduction: Process layout refers to the plan or graphical representation about the design of the floor of a plant. It helps the firm to improve the efficiency of the design and it would help to improve the location of the departments.

a)

Expert Solution
Check Mark

Answer to Problem 2P

The cost of plan A layout is $23,400.

Explanation of Solution

Given information:

Given the distances in feet from one department to the other as follows

Principles Of Operations Management, Chapter 9, Problem 2P , additional homework tip  1

And the work pieces moved from one department to the other as follows

Principles Of Operations Management, Chapter 9, Problem 2P , additional homework tip  2

Calculation of cost of plan A layout:

Calculate the total weekly material handling cost, MH cost using the formula

MHcost=i=1nj=1nxij×Cij (1)

where   n= total number of departments

i,j = individual departments

xij= number of loads moved from department i to department j

Cij= cost to move an item from department i to department j

Substitute into the equation (1), the various values to obtain

MtoD=20×600×$0.5=$6,000MtoF=12×1,800×$0.5=$10,800MtoP=8×200×$0.5=$800

DtoF=400×6×$0.5=$1,200DtoP=200×10×$0.5=$1,000FtoP=4×1,800×$0.5=$3,600

Add all the costs to obtain the total material handling costs $23,400_ .

Hence, the cost of plan A layout is $23,400.

b)

Summary Introduction

To determine: The cost of the layout.

b)

Expert Solution
Check Mark

Answer to Problem 2P

The cost of the layout is $20,600.

Explanation of Solution

Given information:

Given the distances in feet from one department to the other as follows

Principles Of Operations Management, Chapter 9, Problem 2P , additional homework tip  3

And the work pieces moved from one department to the other as follows

Principles Of Operations Management, Chapter 9, Problem 2P , additional homework tip  4

Calculation of cost of the layout:

After switching departments F and P, calculate the total material handling cost, MH cost using the formula

Calculate the total weekly material handling cost, MH cost using the formula

MHcost=i=1nj=1nxij×Cij (2)

where   n= total number of departments

i,j = individual departments

xij= number of loads moved from department i to department j

Cij= cost to move an item from department i to department j

Substitute in equation (2), the various values to obtain

MtoD=20×600×$0.5=$6,000MtoF=8×1,800×$0.5=$7,200MtoP=12×200×$0.5=$1,200

DtoF=400×10×$0.5=$2,000DtoP=200×6×$0.5=$600FtoP=4×1,800×$0.5=$3,600

Add all the costs to obtain the total material handling costs $20,600_

Hence, the cost of the layout is $20,600.

c)

Summary Introduction

To determine: The cost of the layout.

c)

Expert Solution
Check Mark

Answer to Problem 2P

The cost of the layout is $22,000.

Explanation of Solution

Given information:

Given the distances in feet from one department to the other as follows

Principles Of Operations Management, Chapter 9, Problem 2P , additional homework tip  5

And the work pieces moved from one department to the other as follows

Principles Of Operations Management, Chapter 9, Problem 2P , additional homework tip  6

Calculation of cost of the layout:

After switching departments M and D, calculate the total material handling cost, MH cost using the formula

Calculate the total weekly material handling cost, MH cost using the formula

MHcost=i=1nj=1nxij×Cij (3)

where   n= total number of departments

i,j = individual departments

xij= number of loads moved from department i to department j

Cij= cost to move an item from department i to department j

Substitute in equation (3), the various values to obtain

MtoD=20×600×$0.5=$6,000MtoF=10×1,800×$0.5=$9,000MtoP=6×200×$0.5=$600

DtoF=400×8×$0.5=$1,600DtoP=200×12×$0.5=$1,200FtoP=4×1,800×$0.5=$3,600

Add all the costs to obtain the total material handling costs $22,000_ .

Hence, the cost of the layout is $22,000.

d)

Summary Introduction

To determine: The best layout in terms of cost perspective.

d)

Expert Solution
Check Mark

Explanation of Solution

Best layout in terms of cost perspective:

From above calculations, the cost perspective, Plan B which has the total material handling costs of $20,600 is cost effective than other plans.

Hence, Plan B is the best layout.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
Davison Electronics manufactures three LED television monitors, identified as Model A, Model B, and Model C. Davison Electronics four manufacturing plants. Each model has its lowest possible production cost when produced at Plant 1. However, Plant 1 does not have the capacity to handle the total production of all three models. As a result, at least some of the production must be routed to the other manufacturing plants. The following table shows the minimum production requirements for next month, the plant capacities in units per month, and the production cost per unit at each plant: Model Production Cost per Unit Minimum Production Requirements Plant 1 Plant 2 Plant 3 Plant 4 A $25 $28 $37 $34 48,000 B $26 $35 $36 $41 75,000 C $20 $31 $26 $23 60,000 Production Capacity 65,000 50,000 32,000 43,000   Davison’s objective is to determine the cost-minimizing production plan
Anecdotally, entrepreneurs frequently encounter two critical dilemmas in managing human resources: the timing of hiring and the decision regarding hiring a generalist versus a specialist for their growing venture. Deciding when to expand a team is crucial, as premature hiring (i.e., hiring too soon) can strain resources, while delayed hiring (i.e., hiring too late) might hinder growth opportunities. Moreover, the choice between hiring a generalist or a specialist depends on the specific needs and stage of the venture, with each option presenting distinct advantages and challenges. To address these issues, a management scholar seeks to identify the factors shaping the hiring cycle throughout the entrepreneurial journey and to understand the criteria for choosing between generalists and specialists at various stages of a venture. The scholar has assembled a sample of 20 experienced South African entrepreneurs who have encountered both failure and success in the financial technology…
3. [25 pts.] Four projects are available for investment. The projects require the cash flows and yield the net present values (NPV) (in millions) shown in the following table. Project id. 1 2 Cash outflow at time 0 (million Lira) 8 8 NPV (million Lira) 12 11 3 4 6 5 8 6 If 20 million Lira is available for investment at time 0, find the investment plan that maximizes NPV. All investments are required to be 0 or 1 (fractional investment values are not permitted). a. Formulate the mathematical model. (Write the decision variables, objective function and the constraints.) [10 pts.] b. Find the optimal solution by using Branch and Bound method (Draw the branch and bound tree clearly, write also lower bounds(LB)) (Left branches x=0, right branches x =1) [15 pts.].
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
  • Text book image
    Practical Management Science
    Operations Management
    ISBN:9781337406659
    Author:WINSTON, Wayne L.
    Publisher:Cengage,
    Text book image
    MARKETING 2018
    Marketing
    ISBN:9780357033753
    Author:Pride
    Publisher:CENGAGE L
    Text book image
    Marketing
    Marketing
    ISBN:9780357033791
    Author:Pride, William M
    Publisher:South Western Educational Publishing
  • Text book image
    Purchasing and Supply Chain Management
    Operations Management
    ISBN:9781285869681
    Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
    Publisher:Cengage Learning
    Text book image
    Principles of Management
    Management
    ISBN:9780998625768
    Author:OpenStax
    Publisher:OpenStax College
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Text book image
MARKETING 2018
Marketing
ISBN:9780357033753
Author:Pride
Publisher:CENGAGE L
Text book image
Marketing
Marketing
ISBN:9780357033791
Author:Pride, William M
Publisher:South Western Educational Publishing
Text book image
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Text book image
Principles of Management
Management
ISBN:9780998625768
Author:OpenStax
Publisher:OpenStax College