Principles Of Operations Management
11th Edition
ISBN: 9780135173930
Author: RENDER, Barry, HEIZER, Jay, Munson, Chuck
Publisher: Pearson,
expand_more
expand_more
format_list_bulleted
Question
Chapter 9, Problem 22P
a)
Summary Introduction
To develop: A layout and balance the line.
b)
Summary Introduction
To determine: The number of people that can be processed in an hour.
c)
Summary Introduction
To determine: The activity that accounts for the current bottleneck.
d)
Summary Introduction
To determine: The total idle time per cycle.
e)
Summary Introduction
To identify: The new layout and throughout when an additional doctor and paramedic is added.
Expert Solution & Answer
Trending nowThis is a popular solution!
Students have asked these similar questions
The City Commission of Nashville has decided to build a botanical garden and picnic area in the
heart of the city for the recreation of its citizens. The precedence table for all the activities
required to construct this area successfully is as follows:
Code Description
A
BCDEFGH
Find location; determine resource
requirements
Requisition of lumber and sand
Dig and grade
Saw lumber into appropriate sizes
Position lumber in correct locations
Nail lumber together
Put sand in and under the equipment
Put dirt around the equipment
Put grass all over the garden, landscape,
paint
Legend
Code
T
Time
(hrs)
15
55
105
30
20
15
25
15
25
ABCDEFGH
Activity
Planning
Purchasing
Excavation
Sawing
Placement
Assembly
Infill
Outfill
Decoration
Immediate Predecessor(s)
None
A
A
B
Refer to the legend for the activity that corresponds to each code.
Using the line drawing tool, draw a Gantt chart for activities E through I of the project.
D, C
E F
F
G, H
X
C
A+
B-
C-
D-
E-
F-
Q
H-
1-
O.
0
20 40 60 80 100 120…
The preinduction physical examination given by the i U.S. Army involves the following seven activities: These activities can be performed in any order, with two exceptions:Medical history must be taken first, and Exit medical evaluation is last. At present, there are three paramedics and two physicians on duty during each shift. Only physicians can performexit evaluations and conduct psychological in terviews. Other activities can be carried out by either physicians or paramedics.a) Develop a layout and balance the line.b) How many people can be processed per hour?c) Which activity accounts for the current bottleneck?d) What is the total idle time per cycle?e) If one more physician and one more paramedic can be placed on duty, how would you redraw the layout? What is the new throughput?
The CEO of Carol O'Lights Manufacturing, produces custom-built relay devices for auto makers. The most recent project undertaken by Ms. O'Lights requires 11 different activities. The activities necessary to build an experimental relay model and related data are given in the following table.
What is the Late Finish on Activity D?
Chapter 9 Solutions
Principles Of Operations Management
Ch. 9 - Prob. 1EDCh. 9 - Prob. 1DQCh. 9 - Prob. 2DQCh. 9 - Prob. 3DQCh. 9 - Prob. 4DQCh. 9 - Prob. 5DQCh. 9 - Prob. 6DQCh. 9 - Prob. 7DQCh. 9 - Prob. 8DQCh. 9 - Prob. 9DQ
Ch. 9 - Prob. 10DQCh. 9 - Prob. 11DQCh. 9 - Prob. 12DQCh. 9 - Prob. 13DQCh. 9 - Prob. 14DQCh. 9 - Prob. 15DQCh. 9 - Prob. 16DQCh. 9 - Prob. 17DQCh. 9 - Prob. 18DQCh. 9 - Prob. 1PCh. 9 - Prob. 2PCh. 9 - Prob. 3PCh. 9 - Roy Creasey Enterprises, a machine shop, is...Ch. 9 - Adam Munson Manufacturing, in Gainesville,...Ch. 9 - Prob. 6PCh. 9 - Prob. 7PCh. 9 - Prob. 8PCh. 9 - Prob. 9PCh. 9 - Six processes are to be laid out in six areas...Ch. 9 - Stanford Rosenberg Computing wants to establish an...Ch. 9 - Illinois Furniture, Inc., produces all types of...Ch. 9 - Prob. 14PCh. 9 - The Action Toy Company has decided to manufacture...Ch. 9 - Prob. 16PCh. 9 - Prob. 17PCh. 9 - Prob. 18PCh. 9 - Prob. 19PCh. 9 - Prob. 20PCh. 9 - Prob. 21PCh. 9 - Prob. 22PCh. 9 - Prob. 23PCh. 9 - Prob. 25PCh. 9 - Prob. 26PCh. 9 - Prob. 27PCh. 9 - Prob. 1CSCh. 9 - Prob. 2CSCh. 9 - Henry Coupe, the manager of a metropolitan branch...Ch. 9 - Prob. 4CSCh. 9 - Prob. 1.1VCCh. 9 - Prob. 1.2VCCh. 9 - Prob. 1.3VCCh. 9 - Prob. 1.4VCCh. 9 - Prob. 1.5VCCh. 9 - Prob. 1.6VCCh. 9 - Prob. 2.1VCCh. 9 - Prob. 2.2VCCh. 9 - Prob. 2.3VC
Knowledge Booster
Similar questions
- A company needs to rebalance a product layout for producing new plastic license plates. They plan to use the assembly line six hours in order to meet projected demand of 2,160 license plates each day. The following table describes the tasks involved in the production of this product: Without regard to projected demand, what is the maximum possible cycle time for this assembly line? Task Time (secs) Immediate Predecessor a 3 none b 4 none c 5 a,b d 7 none e 9 c,darrow_forwardLine balancing As the Operations Manager of Shane Manufacturing Ltd., you are given the task to balance the assembly line that is used to produce a special type of toy. a. Develop your own scenario (quantitative example) of this line balancing problem. Include all relevant information. b. Draw the precedence diagram for the problem that you set up in part “a" above. c. Use the example that you set up to demonstrate how you will balance the line. d. Calculate the efficiency of the line.arrow_forwardThe City Commission of Nashville has decided to build a botanical garden and picnic area in the heart of the city for the recreation of its citizens. The precedence table for all the activities required to construct this area successfully is as follows: Code A B с D E F G H I Description Find location; determine resource requirements Requisition of lumber and sand Dig and grade Saw lumber into appropriate sizes Position lumber in correct locations Time (hrs) 20 60 100 30 20 10 20 10 30 Nail lumber together Put sand in and under the equipment Put dirt around the equipment Put grass all over the garden, landscape, paint Refer to the legend for the activity that corresponds to each code. Using the line drawing tool, draw a Gantt chart for activites E through I of the project. Immediate Predecessor(s) None A A B D, C E F F G, H A B C- D- E F G H- H 0 20 40 60 80 100 120 140 160 180 200 Q ✔arrow_forward
- MGT-314 (Operations Management) MCQ: 1. Tesla is launching a new model of their cars. It is known as the Tesla-model X. Their production facility in Chicago cannot fit the assembly line needed for making the new model. They bought robots, tools, and materials to expand the manufacturing facility. This assembly line is only going to make model-X's and no other models. Their layout is: a) Services Layout b) Product Layout c) Fixed Position Layout d) Process Layout 2. A country is only as strong as its citizens. Due to Bangladesh being a third world country, the crisis is everywhere. With a massive number of people believing in hard work for a minimum wage, these blue-collar employees are having the harshest time surviving this countrywide condition. They simply don't have the means to withstand this situation and that is where the government comes in to aid these people with essentials such as food and equipment (Tran) which will help them to stay afloat from this pandemic. While…arrow_forwardFor an enterprise resource planning (ERP) system design project for a dairy company to incorporate the following steps: Analysis and conceptual design: Perform an analysis of existing processes and collect the organization's requirements.Define the necessary modules, design the database and establish workflows.Development and implementation: Develops and implements the modules of the ERP system, integrating them with each other.Design a friendly and intuitive user interface for employees.Testing, training and deployment: Performs extensive system functionality and security testing.Provides training to employees on how to use the ERP system.Deploys the system throughout the organization and provides technical support and ongoing maintenance.arrow_forwardThe City Commission of Nashville has decided to build a botanical garden and picnic area in the heart of the city for the recreation of its citizens. The precedence table for all the activities required to construct this area successfully is as follows: A- Time B- Code Description (hrs) Immediate Predecessor(s) C- A Find location; determine resource requirements 25 None Requisition of lumber and sand Dig and grade Saw lumber into appropriate sizes 55 A D- C 100 A E- 30 В E Position lumber in correct locations 20 D, C F- F Nail lumber together 10 E G- Put sand in and under the equipment Put dirt around the equipment G 25 F H F H- Put grass all over the garden, landscape, paint 35 G, H Refer to the legend for the activity that corresponds to each code. Using the line drawing tool, draw a Gantt chart for activities E through I of the project. 20 40 60 80 100 120 140 160 180 200 220arrow_forward
- Statement of the ProblemKuala Lumpur Hospital, as we all know, is one of Malaysia's busiest hospitals. This is due to the fact that it admits a diverse range of patients suffering from a diverse range of disorders. These patients have arrived as a result of the health sector that operates in this facility. In other words, the departments within it are quite diverse. As a result, the hospital must deal with a high volume of both existing and new patients. Employees are required to gather patient personal information such as name, address, and so on for all of these admissions. It intends to capture and save their data for further use. Employee admissions, such as physicians and nurses, should also be recorded by the hospital. Furthermore, the hospital must manually record the many departments, rooms, and physicians in hospitals. It is also required to keep frequent records of patients, patients admitted to the hospital, doctor exams on patients, patients who have had surgery, and…arrow_forwardManagement wants to design an assembly line that will turn out 800 videotapes per day. There will be eight working hours in each day. The industrial engineering staff has assembled the information below: A) Determine the maximum and minimum cycle times.B) Determine the optimum cycle time.C) What is the minimum number of stations needed?D) Draw the precedence diagram.E) Assign tasks to stations in order of most following tasks first. Submit an Excel file based on Chapter 6 Excel Template to indicate your computation.arrow_forwardSue Helms Appliances wants to establish an assembly line to manufacture its new product, the Micro Popcorn Popper. The goal is to produce five poppers per hour. The tasks, task times, and immediate predecessors for producing one Micro Popcorn Popper are as follows: Task Performance Time (mins) Task Must Follow Task Listed Below A 8 − B 11 A C 10 A, B D 9 B, C E 8 C F 4 D, E A C F B E D In the diagram, there are 6 circles labeled using the letters from A to F. There are 8 of arrows, and each arrow connects one circle to another circle. The arrows are situated in the following manner: A to B, A to C, B to C, C to D, B to D, C to E, D to F, and E to F. Part 2 a) The theoretical minimum number of workstations=55 (round your response up to the…arrow_forward
- Professor Garcia has assigned 15 cases in his OM Seminarclass to be completed in a 15-week semester. The students, of course, are moaning and groaning that the caseload can-not possibly be completed in the time allotted. Professor Garcia sympathetically suggests that the students work in groups and learn to organize their work efficiently. Know-ing when a situation is hopeless, the students make a list of the tasks that have to be completed in preparing a case. These tasks are listed here, along with precedence require-ments and estimated time in days. Assuming students will work five days a week on this assignment, how many stu-dents should be assigned to each group, and what is the most efficient allocation of tasks? Can 15 cases be com-pleted in a semester? Explain your answer.arrow_forwardA life cycle model specifies the criteria for entering and exiting each phase. When may a phase begin?arrow_forwardRoger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before a training program of this nature could be conducted. The activities, immediate predecessors, and times appear in the accompanying table: Activity Immediate Predecessor(s) Time (days) A − 4 B − 6 C − 1 D B 10 E A, D 5 F C 5 G E, F 8 This exercise contains only parts b, c, and d. Part 2 b) The critical activities for the leadership training program development project are ▼ B - D - E - G C - F - G A - E - G . Part 3 c) The project length for the leadership training program development project = enter your response here days. Part 4 d) Slack time for each of the activities is: Part 5 Part 6 Part 7…arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.