Question
Chapter 8, Problem 9P
Summary Introduction
To draw: The time required for an employee to assemble his or her eightieth Mega-Burger.
Introduction
Human resource is one of the major resource of an organization like any other resource such as capital and raw material. Human resource of an organization includes the individuals who work for the organization. Employees working in the organization are the human resource.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Suad Alwan, the purchasing agent for Dubai Airlines, has determined that the
second
plane took
18,000
hours to produce. Using an
85%
learning curve and a
$35-per-hour
labor charge, he wants to determine the cost of the
six
additional planes.
Part 2
Time required for the
sixth
unit =
13900
hours (round your response to the nearest whole number).
Part 3
Cost of the
sixth
unit =
486500
dollars (round your response to the nearest whole number).
Part 4
Time required for the
seventh
unit =
enter your response here
hours (round your response to the nearest whole number). Part 5. Cost of the seventh unit?
The product superx takes 9949 hours for production of 250 unit, where learning curve rate is 99.7% and what will be the total time taken by 2000 units of product superx using cumulative method ?
The product TRX takes 9.99 hours for production of 1 unit, where learning curve rate is 77% and what will be the total time taken by 8th unit of product TRX using incremental unit time method ?
Chapter 8 Solutions
Operations and Supply Chain Management, 9th Edition WileyPLUS Registration Card + Loose-leaf Print Companion
Ch. 8.S - Compare the use of predetermined motion times for...Ch. 8.S - Prob. 2QCh. 8.S - Prob. 3QCh. 8.S - Prob. 5QCh. 8.S - Prob. 6QCh. 8.S - Prob. 7QCh. 8.S - Prob. 1PCh. 8.S - A sewing operator at the Gameday Sportswear...Ch. 8 - Prob. 1QCh. 8 - Prob. 2Q
Ch. 8 - Prob. 3QCh. 8 - Prob. 4QCh. 8 - Prob. 5QCh. 8 - Prob. 6QCh. 8 - Prob. 7QCh. 8 - What are some of the ways companies achieve...Ch. 8 - Prob. 10QCh. 8 - Prob. 12QCh. 8 - Prob. 13QCh. 8 - Prob. 16QCh. 8 - Prob. 17QCh. 8 - Prob. 18QCh. 8 - Prob. 20QCh. 8 - Prob. 21QCh. 8 - Prob. 22QCh. 8 - Prob. 23QCh. 8 - Prob. 24QCh. 8 - Prob. 25QCh. 8 - Prob. 27QCh. 8 - Prob. 28QCh. 8 - Prob. 33QCh. 8 - Prob. 34QCh. 8 - Discuss some of the uses and limitations of...Ch. 8 - Prob. 1PCh. 8 - Professor Cook teaches operations management at...Ch. 8 - Nite-Site, Inc., manufactures image...Ch. 8 - Prob. 4PCh. 8 - Prob. 5PCh. 8 - Prob. 6PCh. 8 - Prob. 7PCh. 8 - Prob. 8PCh. 8 - Prob. 9PCh. 8 - Prob. 10PCh. 8 - Prob. 11PCh. 8 - Prob. 12P
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- A contractor is preparing a bid to install swimming pools at a new housing addition. The estimated time to build the first pool is 33 hours. The contractor estimates an 80 percent learning rate. Using POM for Windows or OM Explorer, how long do you estimate the time required to install the fifth pool?arrow_forwardA newly established electric car company estimates that the manufacturing time for their 4th car to be 77.0 hours. Given an 85.0 learning percentage and a labor/overhead cost of $650 per hour, what's the total labor/overhead cost for the first set of 10 cars of the runarrow_forwardIf a company is preparing a bid on a government contract for 40 units of a certain product. The operations manager estimates the assembly time required for the first two units to be 10.4 hours and 8.8 hours respectively. What is the appropriate learning curve? Explain and show your answer.arrow_forward
- The company zutsu takes 30.7 hours for production of 1 unit of a chemical box, where learning curve rate is 97% and what will be the total time taken by 2th unit of chemical box using incremental unit time method ?arrow_forwardSusan Sherer, an IRS auditor, took 48 minutes to process her first tax return. The IRS uses an 82% learning curve. The amount of processing time that Susan is going to require for the 2nd return __ minutes 4th return __ minutes and 8th return __ minutesarrow_forwardOnline training could be an example of asynchronous training. True or falsearrow_forward
- Suad Alwan, the purchasing agent for Dubai Airlines, has determined that the third plane took 20,000 hours to produce. Using an 80% learning curve and a $40-per-hour labor charge, he wants to determine the cost of the four additional planes. a) Time required for the fourth unit = 18,231 hours b) Cost of the fourth unit = ? dollars (round to the nearest whole number)arrow_forwardIn yuyox ltd the first 71 units takes 92 hours to be produced where learning curve is 83% , calculate how much time it will take to produce 568 units using the wrights model ? Solve asaparrow_forwardSuad Alwan, the purchasing agent for Dubai Airlines, has determined that the second plane took 18,000 hours to produce. Using an 85% learning curve and a $35-per-hour labor charge, he wants to determine the cost of the six additional planes. Time required for the sixth unit = hours (round your response to the nearest whole number).arrow_forward
- A new product made from recycled bio-plastics needs 20 labor hours to complete the build for the first unit. If production operates at a 85% learning curve rate, calculate the average labor hours required per unit to produce five units.arrow_forwardGiven the following information from an assembly task: First cycle time: 35 seconds Learning rate of 90% a. Determine the predicted performance time of the 200th b. Determine the number of cycles it will take to reach the standard time of 14 secondsarrow_forwardIn yuyox ltd the first 71 units takes 92 hours to be produced where learning curve is 83% , calculate how much time it will take to produce 568 units using the wrights model ?arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.