Question
Book Icon
Chapter 8, Problem 10P
Summary Introduction

To draw: The number of rooms that newly hired housekeepers have to clean before it can be done in 32 minutes. Also to determine the number of work days required before the housekeeper is fully proficient

Introduction

Human resource is one of the major resource of an organization like any other resource such as capital and raw material. Human resource of an organization includes the individuals who work for the organization. Employees working in the organization are the human resource.

Blurred answer
Students have asked these similar questions
The Hand-To-Mouth Company (HTM) has $200,000 in cash, no inventory, and a 90 percent learning curve. To reduce the complexity of this problem, ignore the hiring and training costs associated with dramatically increased production. Employees are paid $20 per hour every Friday for that week’s work. HTM has received an order to build 1,000 oak desks over the next 15 weeks. Materials cost $400 per desk. Suppliers make deliveries each Monday and insist on cash upon delivery. The first desk takes 100 hours of direct labor to build. HTM will be paid $1,500 per desk 2 weeks after the desks are delivered. Should HTM take this order? Week Units Week Units Week Units 1 2 3 4 5   2 4 8 12 4   6 7 8 9 10   24 64 128 128 128   11 12 13 14 15 Total 88 100 100 100 100 1000
local market research fim has just won a contract for several thousand small projects involving   data gathering and statistical analysis. In the past, the firm has assigned each project to a single member of its highly trained professional staff. This person would both gather and analyze the data Using this approach, an experienced person can complete an average of 10 such projects in an eight-hour day. The firm's management is thinking of assigning two people to each project in order to allow them to specialize and become more efficient The process would require the data gatherer to fill out a matrix on the computer, check it and transmit it to the statistical analysis program for the analyst   to complete. Data can be gathered on one project while the analysis is being completed on   another, but the analysis must be complete before the statistical analysis program can accept the   new data. After some practice, the new process can be completed with a standard time of 20   minutes…
Suppose a manufacturer of copiers has concluded that an 82% learning curve applies to the time a beginning service technician takes to diagnose a faulty copying machine. The estimated time the technician takes to install the first copier is 3.2 hrs. Estimate how long will the technician take to diagnose the 10th copier.  Plot the learning curve (include time estimates of 50 units in your plot).  If another technician has an estimated learning curve of 80%, which technician is expected to learn faster? PLOT the learning curve, please.
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Understanding Management (MindTap Course List)
Management
ISBN:9781305502215
Author:Richard L. Daft, Dorothy Marcic
Publisher:Cengage Learning