Principles Of Operations Management
11th Edition
ISBN: 9780135173930
Author: RENDER, Barry, HEIZER, Jay, Munson, Chuck
Publisher: Pearson,
expand_more
expand_more
format_list_bulleted
Concept explainers
Question
Chapter 7.S, Problem 10P
Summary Introduction
To determine: The throughput time of the work cell in CEC Laundry.
Introduction:
Throughput time:
Throughput time is time taken for a product to move through the manufacturing process from the raw materials stage until it is converted into finished goods.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
A work cell at Chris Ellis Commercial Laundryhas a workstation with two machines, and each unit producedat the station needs to be processed by both of the machines.(The same unit cannot be worked on by both machines simultaneously.) Each machine has a production capacity of 4units per hour. What is the throughput time of the work cell?
The Pullman Mfg., Inc. three-station work cell illustrated in the figure below has two machines at station 1 in parallel. (The product needs to go through only one of the two machines before proceeding to station 2.)
SEE PICTURE
Answer C
A work cell at Chris Ellis Commercial Laundry hasa workstation with two machines, and each unit produced at thestation needs to be processed by both of the machines. (The sameunit cannot be worked on by both machines simultaneously.)Each machine has a production capacity of 4 un its per hour.What is the throughput time of the work cell?
Chapter 7 Solutions
Principles Of Operations Management
Ch. 7.S - Prob. 1DQCh. 7.S - Prob. 2DQCh. 7.S - Prob. 3DQCh. 7.S - Prob. 4DQCh. 7.S - Prob. 5DQCh. 7.S - Distinguish between bottleneck time and throughput...Ch. 7.S - Prob. 7DQCh. 7.S - Prob. 8DQCh. 7.S - Prob. 9DQCh. 7.S - Prob. 10DQ
Ch. 7.S - Prob. 11DQCh. 7.S - Prob. 12DQCh. 7.S - What are the techniques available to operations...Ch. 7.S - Amy Xias plant was designed to produce 7,000...Ch. 7.S - For the post month, the plant in Problem S7.1,...Ch. 7.S - Prob. 3PCh. 7.S - Prob. 4PCh. 7.S - Prob. 5PCh. 7.S - The effective capacity and efficiency for the next...Ch. 7.S - Southeastern Oklahoma State Universitys business...Ch. 7.S - Prob. 8PCh. 7.S - Prob. 9PCh. 7.S - Prob. 10PCh. 7.S - The three-station work cell illustrated in Figure...Ch. 7.S - The three-station work cell at Pullman Mfg., Inc....Ch. 7.S - The Pullman Mfg., Inc., three-station work cell...Ch. 7.S - Prob. 14PCh. 7.S - 10 minutes per unit. Part 2 is simultaneously...Ch. 7.S - Prob. 16PCh. 7.S - Prob. 17PCh. 7.S - Using the data in Problem S7.17: a) What is the...Ch. 7.S - Prob. 19PCh. 7.S - Prob. 20PCh. 7.S - Prob. 21PCh. 7.S - Prob. 22PCh. 7.S - Prob. 23PCh. 7.S - Prob. 24PCh. 7.S - Prob. 25PCh. 7.S - Prob. 26PCh. 7.S - Prob. 27PCh. 7.S - Prob. 28PCh. 7.S - Prob. 29PCh. 7.S - Prob. 30PCh. 7.S - Prob. 31PCh. 7.S - Prob. 32PCh. 7.S - Prob. 33PCh. 7.S - Prob. 34PCh. 7.S - Prob. 35PCh. 7.S - Prob. 36PCh. 7.S - Prob. 37PCh. 7.S - Prob. 38PCh. 7.S - Prob. 39PCh. 7.S - Prob. 40PCh. 7.S - Prob. 41PCh. 7.S - Prob. 42PCh. 7.S - Prob. 43PCh. 7.S - Prob. 44PCh. 7.S - Prob. 45PCh. 7.S - Prob. 1VCCh. 7.S - a capacity expansion plan and a new 11-story...Ch. 7.S - a capacity expansion plan and a new 11-story...Ch. 7 - Ethical Dilemma For the sake of efficiency and...Ch. 7 - Prob. 1DQCh. 7 - Prob. 2DQCh. 7 - Prob. 3DQCh. 7 - Prob. 4DQCh. 7 - Prob. 5DQCh. 7 - Prob. 6DQCh. 7 - Prob. 7DQCh. 7 - Prob. 8DQCh. 7 - Prob. 9DQCh. 7 - Prob. 10DQCh. 7 - Prob. 11DQCh. 7 - Prob. 12DQCh. 7 - Prob. 13DQCh. 7 - Prob. 14DQCh. 7 - Prob. 15DQCh. 7 - Prob. 16DQCh. 7 - Prob. 17DQCh. 7 - Prob. 18DQCh. 7 - Prob. 19DQCh. 7 - Prob. 1PCh. 7 - Usingthedatain Problem 7.1, determinethemost...Ch. 7 - Prob. 3PCh. 7 - Refer to Problem 7.1. If a contract for the second...Ch. 7 - Stan Fawcetts company is considering producing a...Ch. 7 - Prob. 6PCh. 7 - Prob. 7PCh. 7 - Prob. 8PCh. 7 - Metters Cabinets, Inc., needs to choose a...Ch. 7 - Prob. 10PCh. 7 - Nagle Electric. Inc., of Lincoln, Nebraska, must...Ch. 7 - Stapleton Manufacturing intends to increase...Ch. 7 - Prepare a flowchart for one of the following: a)...Ch. 7 - Prepare a process chart for one of the activities...Ch. 7 - Prob. 15PCh. 7 - Prob. 16PCh. 7 - Prob. 17PCh. 7 - Prob. 1CSCh. 7 - Prob. 2CSCh. 7 - Prob. 3CSCh. 7 - Process Strategy at Wheeled Coach Wheeled Coach,...Ch. 7 - Prob. 1.2VCCh. 7 - Prob. 1.3VCCh. 7 - Prob. 1.4VCCh. 7 - Alaska Airlines: 20-Minute Baggage...Ch. 7 - Prob. 2.2VCCh. 7 - Prob. 2.3VCCh. 7 - Prob. 2.4VCCh. 7 - Prob. 2.5VCCh. 7 - Prob. 3.1VCCh. 7 - Prob. 3.2VCCh. 7 - Prob. 3.3VCCh. 7 - Prob. 3.4VC
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- The Pullman Mfg., Inc. three-station work cell illustrated in the figure below has two machines at station 1 in parallel. (The product needs to go through only one of the two machines before proceeding to station 2.) 12 min/unit Station 1 Machine A Station 1 Machine B 12 min/unit Station 2 12 min/unit Station 3 2 min/unit The manager, Ms. Hartley, has asked you to evaluate the system if she adds a parallel machine at station 2. a) The throughput time of the new work cell is 26 minutes (enter your response as a whole number). b) The bottleneck time of the new work cell is 6 minutes per unit (enter your response as a whole number). c) If the firm operates 10 hours per day, 6 days per week, the weekly capacity of the work cell with the second machine at workstation 2 is whole number). units (enter your response as aarrow_forwardThe Pullman Mig, Inc. three-station work cell illustrated in the figure below has two machines at station 1 in parallel. (The product needs to go through only one of the two machines before proceeding to station 2.) 20 minunit Station 1 Machine A Station 1 Machine B 20 min/unit Station 2 6 min/unit Station 3 12 minunit The manager, Seimone Hartley, has asked you to evaluate the system if she adds a parallel machine at station 3. a) The throughput time of the new work cell is 38 minutes (enter your response as a whole number). b) The bottleneck time of the new work cell is 10 minutes per unit (enter your response as a whole number). c) If the firm operates 10 hours per day, 6 days per week, the weekly capacity of the work cell with the second machine at workstation 3 is 360 units (enter your response as a whole number). d) If the firm operates 10 hours per day, 6 days per week, the weekly capacity of the work cell without the second machine at workstation 3 is units (enter your response…arrow_forwardAn output of 720 units per shift (7.40 hours) is desired for a new processing system. The system requires product to pass through four stations where the work content at each station is 26 seconds. What is the required cycle time for such a system? How efficient is your system with the cycle time calculated? Station 3 changes and now requires 50 seconds to complete. What will need to be done to meet demand (assume only 7.40 hours are available)? What is the efficiency of the new system?arrow_forward
- The Universal Manufacturing Company produces a par-ticular product in an assembly-line operation. One of the machines on the line is a drill press that has a single as-sembly line feeding into it. A partially completed unit ar-rives at the press to be worked on every 8 minutes, on average, according to an exponential distribution. Themachine operator can process an average of 10 parts perhour (Poisson distributed). Determine the average numberof parts waiting to be worked on, the percentage of timethe operator is working, and the percentage of time themachine is idle.arrow_forwardAdditional Algo 5-8 Flow-Dependent Processing Times Two types of student come to the career-services office for counseling. New students arrive at a rate of 8 students per hour and spend 6 minutes in registration and 13 minutes with an advisor. Returning students students arrive at a rate of 12 students per hour and spend 5 minutes in registration and 10 minutes with an advisor. The staff consists of 1 registration employee and 1 advisor. How many new students will be served each hour? Note: Round your answer to 1 decimal place. Number of new students per hour 1.0arrow_forwardA veterinary office with three processes (examination, greeting, and checkout) has two types of customers (boarding and medical). A veterinary office has a demand of 2 boarding customers per hour and 5 medical customers per hour. Boarding customers visit the greeting and checkout processes while medical customers visit all three processes. What is the total demand at the checkout process each hour? customers per hourarrow_forward
- A three-station line with six operators, where a part needs an operator at stations 1, 2 and 3 for and average of 10, 15 and 5 minutes, respectively. There are plenty of machines at each station, so many that we are confident none of them could be the bottleneck resource, so we don’t need to calculate any of their processing rates.arrow_forwardThe Pullman Mfg., Inc. three-station work cell illustrated in the figure below has two machines at station 1 in parallel. (The product needs to go through only one of the two machines before proceeding to station 2.) Station 1 Machine A Capacity: 3 Units/hr Station 2 Station 3 Capacity: 6 Units/hr Capacity 5 Units/hr Station 1 Machine B Capacity: 3 Units/hr The manager, Mr. Heisler, has asked you to evaluate the system if she adds a parallel machine at station 2. What is the bottleneck time of the new work cell? (enter your response as a whole number). 12 minutes 6 minutes 10 minutes 20 minutesarrow_forwardLaVilla is a village in the Italian Alps. Given its enormous popularity among Swiss,German, Austrian, and Italian skiers, all of its beds are always booked in the winterseason and there are, on average, 1200 skiers in the village. On average, skiers stayin LaVilla for 10 days. How many new skiers are arriving, on average, in LaVillaevery day?arrow_forward
- During the early morning hours, customers arrive at a branch post office at an average rate of 45 per hour (Poisson), while clerks can handle transactions in an average time (exponential) of 4 minutes each. If clerk cost is $30 per hour and customer waiting time represents a "cost" of $20 per hour, how many clerks can be justified on a cost basis? Select one: O a. 3 O b. 6 O c. 4 O d. 5arrow_forwardA work cell in a local manufacturer has a workstation with 4 machines that form a line (Machine 1-Machine 2-Machine 3-Machine 4). Each unit needs to pass through each machine in order to be completed. Each machine has a production capacity of four units per hour. What is the process time of the work cell in minutes per unit? 15 4 8 16arrow_forwardyou have a store with a blue counter that on average 45 clients per hour come in, when the stores medium capacity is of 60 clients per hour. If a client stays a medium of 3 minutes in line, determine: 1. Average time of clients in the blue counter 2. Medium number of clients in line 3. Medium number of clients in the store in any given momentarrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY