Principles Of Operations Management
Principles Of Operations Management
11th Edition
ISBN: 9780135173930
Author: RENDER, Barry, HEIZER, Jay, Munson, Chuck
Publisher: Pearson,
bartleby

Concept explainers

bartleby

Videos

Textbook Question
Book Icon
Chapter 7.S, Problem 15P

10 minutes per unit. Part 2 is simultaneously processed at work-station C for 20 minutes per unit. Work stations B and C feed the parts to an assembler at workstation D. w here the two parts are assembled. The time at workstation D is 15 minutes.

a) What is the bottleneck of this process?

b) What is the hourly capacity of the process?

•• S7.15 A production process at Kenneth Day Manufacturing is shown in Figure S7.9. The drilling operation occurs separately from, and simultaneously with, sawing and sanding, which are independent and sequential operations. A product needs to go through only one of the three assembly operations (the operations are in parallel).

a) Which operation is the bottleneck?

b) What is the bottleneck time?

c) What is the throughput time of the overall system?

d) If the firm operates 8 hours per day. 20 days per month, what is the monthly capacity of the manufacturing process?

Chapter 7.S, Problem 15P, 10 minutes per unit. Part 2 is simultaneously processed at work-station C for 20 minutes per unit.

a)

Expert Solution
Check Mark
Summary Introduction

To determine: The bottleneck operation.

Introduction:

Bottleneck time:

The bottleneck time of the system is the process in the system which takes the most amount of time to complete its activity. The bottleneck time will reduce the overall efficiency of the system.

Answer to Problem 15P

The bottleneck operation is Welding.

Explanation of Solution

Given information:

Principles Of Operations Management, Chapter 7.S, Problem 15P , additional homework tip  1

Formula to convert capacity into process time:

Process time of each operation=Number of minutes per hourCapacity

Formula to calculate overall assembly operation process time:

Process time of overall assembly=Process time at one assembly operationNumber of assembly operations

Calculation of process time for each operation:

The process time of each station is calculated by dividing the number of minutes with the production capacity of the station.

Sawing:

Process time =606=10 minutes / unit

Sanding:

Process time =606=10 minutes / unit

Drilling:

Process time =602.4=25 minutes / unit

Sawing:

Process time =606=10 minutes / unit

Welding:

Process time =602=30 minutes / unit

Assembly at one operation:

Process time =600.7=85.71 minutes / unit

Calculation of overall assembly operation process time:

The overall assembly operation process time is calculated by dividing the process time at one assembly operation by the Number of assembly operations.

Process time of overall assembly=85.713=28.57

Identification of the bottleneck time of the system:

The bottleneck time of the system is the operation which has the highest process time. Welding has the highest process time when compared to the other operations (30>10, 10, 25, 10, 28.57). Hence, the bottleneck time of the system is 30 minutes per unit.

Therefore, the bottleneck operation is Welding.

b)

Expert Solution
Check Mark
Summary Introduction

To determine: The bottleneck time of the bottleneck operation.

Introduction:

Bottleneck time:

The bottleneck time of the system is the process in the system which takes the most amount of time to complete its activity. The bottleneck time will reduce the overall efficiency of the system.

Answer to Problem 15P

The bottleneck time of the bottleneck operation is 30.

Explanation of Solution

Given information:

Principles Of Operations Management, Chapter 7.S, Problem 15P , additional homework tip  2

Formula to convert capacity into process time:

Process time of each operation=Number of minutes per hourCapacity

Formula to calculate overall assembly operation process time:

Process time of overall assembly=Process time at one assembly operationNumber of assembly operations

Calculation of process time for each operation:

The process time of each station is calculated by dividing the number of minutes with the production capacity of the station.

Sawing:

Process time =606=10 minutes / unit

Sanding:

Process time =606=10 minutes / unit

Drilling:

Process time =602.4=25 minutes / unit

Sawing:

Process time =606=10 minutes / unit

Welding:

Process time =602=30 minutes / unit

Assembly at one operation:

Process time =600.7=85.71 minutes / unit

Calculation of overall assembly operation process time:

The overall assembly operation process time is calculated by dividing the process time at one assembly operation by the number of assembly operations.

Process time of overall assembly=85.713=28.57

Identification of the bottleneck time of the system:

The bottleneck time of the system is the operation which has the highest process time. Welding has the highest process time when compared to the other operations (30 > 10, 10, 25, 10, 28.57).  The bottleneck operation is Welding.

Hence, the bottleneck time of the bottleneck operation is 30 minutes per unit.

c)

Expert Solution
Check Mark
Summary Introduction

To determine: The throughput time of the time of the overall system.

Introduction:

Throughput time:

The throughput time of a system is the time taken for a product to pass from the raw materials stage to the finished goods stage. The higher the throughput time the more efficient the system will be.

Answer to Problem 15P

The throughput time of the overall system is 140.71 minutes.

Explanation of Solution

Given information:

Principles Of Operations Management, Chapter 7.S, Problem 15P , additional homework tip  3

Formula to convert capacity into process time:

Process time of each operation=Number of minutes per hourCapacity

Formula to calculate throughput time:

Throughput time=Maximum ((Sum of process times of Sawing, Sanding, Welding, Assembly),(Sum of process times of Drilling, Welding, Assembly))

Calculation of process time for each operation:

The process time of each station is calculated by dividing the number of minutes with the production capacity of the station.

Sawing:

Process time =606=10 minutes / unit

Sanding:

Process time =606=10 minutes / unit

Drilling:

Process time =602.4=25 minutes / unit

Sawing:

Process time =606=10 minutes / unit

Welding:

Process time =602=30 minutes / unit

Assembly at one operation:

Process time =600.7=85.71 minutes / unit

Calculation of throughput time:

The throughput time is calculated by identifying the maximum value of the summation of process times of Sanding, Sawing, Welding, assembly and the summation of process times of Drilling, Welding, and Assembly.

Throughput time=Maximum((10+10+30+85.71),(25+30+85.71))=Maximum(135.71,140.71)=140.71

Hence, the throughput time of the overall system is 140.71 minutes.

d)

Expert Solution
Check Mark
Summary Introduction

To determine: The monthly capacity of the manufacturing process.

Introduction:

Bottleneck time:

The bottleneck time of the system is the process in the system which takes the most amount of time to complete its activity. The bottleneck time will reduce the overall efficiency of the system.

Monthly capacity:

The monthly capacity is the number of units the firm is able to produce in a month’s time. It will be calculated taking into consideration of the resources and constraints present in the manufacturing process.

Answer to Problem 15P

The monthly capacity of the manufacturing process is 320 units per month.

Explanation of Solution

Given information:

Principles Of Operations Management, Chapter 7.S, Problem 15P , additional homework tip  4

Operating time = 60 minutes / 8 hour / day

Number of days = 20 / month

Formula to convert capacity into process time:

Process time of each operation=Number of minutes per hourCapacity

Formula to calculate overall assembly operation process time:

Process time of overall assembly=Process time at one assembly operationNumber of assembly operations

Formula to calculate monthly capacity:

Monthly capacity=Operating time×Number of days per monthBottleneck time

Calculation of process time for each operation:

The process time of each station is calculated by dividing the number of minutes with the production capacity of the station.

Sawing:

Process time =606=10 minutes / unit

Sanding:

Process time =606=10 minutes / unit

Drilling:

Process time =602.4=25 minutes / unit

Sawing:

Process time =606=10 minutes / unit

Welding:

Process time =602=30 minutes / unit

Assembly at one operation:

Process time =600.7=85.71 minutes / unit

Calculation of overall assembly operation process time:

The overall assembly operation process time is calculated by dividing the process time at one assembly operation by the Number of assembly operations.

Process time of overall assembly=85.713=28.57

Identification of the bottleneck time of the system:

The bottleneck time of the system is the operation which has the highest process time. Welding has the highest process time when compared to the other operations (30 > 10, 10, 25, 10, 28.57). Hence, the bottleneck time of the system is 30 minutes per unit.

Calculation of monthly capacity:

The monthly capacity is calculated by multiplying the operating time per day with the number of days per month and dividing the resultant value with the bottleneck time of the system.

Monthly capacity=Operating time×Number of days per monthBottleneck time=8×60×2030=9,60030=320units

Hence, the monthly capacity of the manufacturing process is 320 units per month.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
Help with question?
What are some good examples of bullet points on a resume for a Christian Elementary School?
What is an example of a cover letter for a Christian School Long-Term Substitute Teaching position?

Chapter 7 Solutions

Principles Of Operations Management

Ch. 7.S - Prob. 11DQCh. 7.S - Prob. 12DQCh. 7.S - What are the techniques available to operations...Ch. 7.S - Amy Xias plant was designed to produce 7,000...Ch. 7.S - For the post month, the plant in Problem S7.1,...Ch. 7.S - Prob. 3PCh. 7.S - Prob. 4PCh. 7.S - Prob. 5PCh. 7.S - The effective capacity and efficiency for the next...Ch. 7.S - Southeastern Oklahoma State Universitys business...Ch. 7.S - Prob. 8PCh. 7.S - Prob. 9PCh. 7.S - Prob. 10PCh. 7.S - The three-station work cell illustrated in Figure...Ch. 7.S - The three-station work cell at Pullman Mfg., Inc....Ch. 7.S - The Pullman Mfg., Inc., three-station work cell...Ch. 7.S - Prob. 14PCh. 7.S - 10 minutes per unit. Part 2 is simultaneously...Ch. 7.S - Prob. 16PCh. 7.S - Prob. 17PCh. 7.S - Using the data in Problem S7.17: a) What is the...Ch. 7.S - Prob. 19PCh. 7.S - Prob. 20PCh. 7.S - Prob. 21PCh. 7.S - Prob. 22PCh. 7.S - Prob. 23PCh. 7.S - Prob. 24PCh. 7.S - Prob. 25PCh. 7.S - Prob. 26PCh. 7.S - Prob. 27PCh. 7.S - Prob. 28PCh. 7.S - Prob. 29PCh. 7.S - Prob. 30PCh. 7.S - Prob. 31PCh. 7.S - Prob. 32PCh. 7.S - Prob. 33PCh. 7.S - Prob. 34PCh. 7.S - Prob. 35PCh. 7.S - Prob. 36PCh. 7.S - Prob. 37PCh. 7.S - Prob. 38PCh. 7.S - Prob. 39PCh. 7.S - Prob. 40PCh. 7.S - Prob. 41PCh. 7.S - Prob. 42PCh. 7.S - Prob. 43PCh. 7.S - Prob. 44PCh. 7.S - Prob. 45PCh. 7.S - Prob. 1VCCh. 7.S - a capacity expansion plan and a new 11-story...Ch. 7.S - a capacity expansion plan and a new 11-story...Ch. 7 - Ethical Dilemma For the sake of efficiency and...Ch. 7 - Prob. 1DQCh. 7 - Prob. 2DQCh. 7 - Prob. 3DQCh. 7 - Prob. 4DQCh. 7 - Prob. 5DQCh. 7 - Prob. 6DQCh. 7 - Prob. 7DQCh. 7 - Prob. 8DQCh. 7 - Prob. 9DQCh. 7 - Prob. 10DQCh. 7 - Prob. 11DQCh. 7 - Prob. 12DQCh. 7 - Prob. 13DQCh. 7 - Prob. 14DQCh. 7 - Prob. 15DQCh. 7 - Prob. 16DQCh. 7 - Prob. 17DQCh. 7 - Prob. 18DQCh. 7 - Prob. 19DQCh. 7 - Prob. 1PCh. 7 - Usingthedatain Problem 7.1, determinethemost...Ch. 7 - Prob. 3PCh. 7 - Refer to Problem 7.1. If a contract for the second...Ch. 7 - Stan Fawcetts company is considering producing a...Ch. 7 - Prob. 6PCh. 7 - Prob. 7PCh. 7 - Prob. 8PCh. 7 - Metters Cabinets, Inc., needs to choose a...Ch. 7 - Prob. 10PCh. 7 - Nagle Electric. Inc., of Lincoln, Nebraska, must...Ch. 7 - Stapleton Manufacturing intends to increase...Ch. 7 - Prepare a flowchart for one of the following: a)...Ch. 7 - Prepare a process chart for one of the activities...Ch. 7 - Prob. 15PCh. 7 - Prob. 16PCh. 7 - Prob. 17PCh. 7 - Prob. 1CSCh. 7 - Prob. 2CSCh. 7 - Prob. 3CSCh. 7 - Process Strategy at Wheeled Coach Wheeled Coach,...Ch. 7 - Prob. 1.2VCCh. 7 - Prob. 1.3VCCh. 7 - Prob. 1.4VCCh. 7 - Alaska Airlines: 20-Minute Baggage...Ch. 7 - Prob. 2.2VCCh. 7 - Prob. 2.3VCCh. 7 - Prob. 2.4VCCh. 7 - Prob. 2.5VCCh. 7 - Prob. 3.1VCCh. 7 - Prob. 3.2VCCh. 7 - Prob. 3.3VCCh. 7 - Prob. 3.4VC
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Text book image
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Text book image
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Text book image
Business in Action
Operations Management
ISBN:9780135198100
Author:BOVEE
Publisher:PEARSON CO
Text book image
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Text book image
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY