Principles Of Operations Management
11th Edition
ISBN: 9780135173930
Author: RENDER, Barry, HEIZER, Jay, Munson, Chuck
Publisher: Pearson,
expand_more
expand_more
format_list_bulleted
Question
Chapter 7, Problem 7P
Summary Introduction
To determine: The preferred process for TU person of UM Company.
Expert Solution & Answer
Trending nowThis is a popular solution!
Students have asked these similar questions
Tim Urban, owner/manager of Urban's Motor Court in Key West, is considering outsourcing the daily room cleanup for his motel to Duffy's Maid Service. Tim rents an average of 50 rooms for each of 365 nights (365 x 50
equals the total rooms rented for the year). Tim's cost to clean a room is $12.50 The Duffy's Maid Service quote is $18.50 per room plus a fixed cost of $26,000 for sundry items such as uniforms with the motel's
name. Tim's annual fixed cost for space, equipment, and supplies is $60,000.
Based on the given information related to costs for each of the options, the crossover point for Tim =
room nights (round your response to the nearest whole number)
4
Tim Urban, owner/manager of Urban's
Motor Court in Key West, is
considering outsourcing the daily
room cleanup for his motel to Duffy's
Maid Service. Tim rents an average of
50 rooms for each of 365 nights (365 x
50 equals the total rooms rented for
the year). Tim's cost to clean a room is
$13.50. The Duffy's Maid Service quote
is $19.00 per room plus a fixed cost of
$26,000 for sundry items such as
uniforms with the motel's name. Tim's
annual fixed cost for space,
equipment, and supplies is $65,000.
Based on the given information related
to costs for each of the options the
crossover point for Tim = room nights (
round your answer to the nearest
whole number). If the number of room
nights is less than the crossover point
the (not outsourcing, outsourcing) is
the best option available to Tim. Based
on the given room nights that Tim
expects to rent (18,250) the best option
is (outsourcing, not outsourcing).
Tim Urban, owner/manager of Urban's Motor Court in Key West, is considering outsourcing the daily room cleanup for his motel to Duffy's Maid Service. Tim rents an average of 50 rooms for each of 365 nights (365 × 50 equals the total rooms rented for the year). Tim's cost to clean a room is $12.50.The Duffy's Maid Service quote is $18.00 per room plus a fixed cost of $26,000for sundry items such as uniforms with the motel's name. Tim's annual fixed cost for space, equipment, and supplies is $65,000.
Part 2
Based on the given information related to costs for each of the options, the crossover point for Tim =
room nights (round your response to the nearest whole
number).
Part 3
If the number of room nights is less than the crossover point, then
is the best option available to Tim.
Chapter 7 Solutions
Principles Of Operations Management
Ch. 7.S - Prob. 1DQCh. 7.S - Prob. 2DQCh. 7.S - Prob. 3DQCh. 7.S - Prob. 4DQCh. 7.S - Prob. 5DQCh. 7.S - Distinguish between bottleneck time and throughput...Ch. 7.S - Prob. 7DQCh. 7.S - Prob. 8DQCh. 7.S - Prob. 9DQCh. 7.S - Prob. 10DQ
Ch. 7.S - Prob. 11DQCh. 7.S - Prob. 12DQCh. 7.S - What are the techniques available to operations...Ch. 7.S - Amy Xias plant was designed to produce 7,000...Ch. 7.S - For the post month, the plant in Problem S7.1,...Ch. 7.S - Prob. 3PCh. 7.S - Prob. 4PCh. 7.S - Prob. 5PCh. 7.S - The effective capacity and efficiency for the next...Ch. 7.S - Southeastern Oklahoma State Universitys business...Ch. 7.S - Prob. 8PCh. 7.S - Prob. 9PCh. 7.S - Prob. 10PCh. 7.S - The three-station work cell illustrated in Figure...Ch. 7.S - The three-station work cell at Pullman Mfg., Inc....Ch. 7.S - The Pullman Mfg., Inc., three-station work cell...Ch. 7.S - Prob. 14PCh. 7.S - 10 minutes per unit. Part 2 is simultaneously...Ch. 7.S - Prob. 16PCh. 7.S - Prob. 17PCh. 7.S - Using the data in Problem S7.17: a) What is the...Ch. 7.S - Prob. 19PCh. 7.S - Prob. 20PCh. 7.S - Prob. 21PCh. 7.S - Prob. 22PCh. 7.S - Prob. 23PCh. 7.S - Prob. 24PCh. 7.S - Prob. 25PCh. 7.S - Prob. 26PCh. 7.S - Prob. 27PCh. 7.S - Prob. 28PCh. 7.S - Prob. 29PCh. 7.S - Prob. 30PCh. 7.S - Prob. 31PCh. 7.S - Prob. 32PCh. 7.S - Prob. 33PCh. 7.S - Prob. 34PCh. 7.S - Prob. 35PCh. 7.S - Prob. 36PCh. 7.S - Prob. 37PCh. 7.S - Prob. 38PCh. 7.S - Prob. 39PCh. 7.S - Prob. 40PCh. 7.S - Prob. 41PCh. 7.S - Prob. 42PCh. 7.S - Prob. 43PCh. 7.S - Prob. 44PCh. 7.S - Prob. 45PCh. 7.S - Prob. 1VCCh. 7.S - a capacity expansion plan and a new 11-story...Ch. 7.S - a capacity expansion plan and a new 11-story...Ch. 7 - Ethical Dilemma For the sake of efficiency and...Ch. 7 - Prob. 1DQCh. 7 - Prob. 2DQCh. 7 - Prob. 3DQCh. 7 - Prob. 4DQCh. 7 - Prob. 5DQCh. 7 - Prob. 6DQCh. 7 - Prob. 7DQCh. 7 - Prob. 8DQCh. 7 - Prob. 9DQCh. 7 - Prob. 10DQCh. 7 - Prob. 11DQCh. 7 - Prob. 12DQCh. 7 - Prob. 13DQCh. 7 - Prob. 14DQCh. 7 - Prob. 15DQCh. 7 - Prob. 16DQCh. 7 - Prob. 17DQCh. 7 - Prob. 18DQCh. 7 - Prob. 19DQCh. 7 - Prob. 1PCh. 7 - Usingthedatain Problem 7.1, determinethemost...Ch. 7 - Prob. 3PCh. 7 - Refer to Problem 7.1. If a contract for the second...Ch. 7 - Stan Fawcetts company is considering producing a...Ch. 7 - Prob. 6PCh. 7 - Prob. 7PCh. 7 - Prob. 8PCh. 7 - Metters Cabinets, Inc., needs to choose a...Ch. 7 - Prob. 10PCh. 7 - Nagle Electric. Inc., of Lincoln, Nebraska, must...Ch. 7 - Stapleton Manufacturing intends to increase...Ch. 7 - Prepare a flowchart for one of the following: a)...Ch. 7 - Prepare a process chart for one of the activities...Ch. 7 - Prob. 15PCh. 7 - Prob. 16PCh. 7 - Prob. 17PCh. 7 - Prob. 1CSCh. 7 - Prob. 2CSCh. 7 - Prob. 3CSCh. 7 - Process Strategy at Wheeled Coach Wheeled Coach,...Ch. 7 - Prob. 1.2VCCh. 7 - Prob. 1.3VCCh. 7 - Prob. 1.4VCCh. 7 - Alaska Airlines: 20-Minute Baggage...Ch. 7 - Prob. 2.2VCCh. 7 - Prob. 2.3VCCh. 7 - Prob. 2.4VCCh. 7 - Prob. 2.5VCCh. 7 - Prob. 3.1VCCh. 7 - Prob. 3.2VCCh. 7 - Prob. 3.3VCCh. 7 - Prob. 3.4VC
Knowledge Booster
Similar questions
- K Tim Urban, owner/manager of Urban's Motor Court in Key West, is considering outsourcing the daily room cleanup for his motel to Duffy's Maid Service. Tim rents an average of 50 rooms for each of 365 nights (365 x 50 equals the total rooms rented for the year). Tim's cost to clean a room is $13.00. The Duffy's Maid Service quote is $18.00 per room plus a fixed cost of $25,000 for sundry items such as uniforms with the motel's name. Tim's annual fixed cost for space, equipment, and supplies is $65,000. Based on the given information related to costs for each of the options, the crossover point for Tim = (round your response to the nearest whole number). room nights elparrow_forwardTim Urban, owner/manager of Urban's Motor Courtin Key West, is considering outsourcing the daily room cleanupfor his motel to Duffy 's Maid Service. Tim rents an average of50 rooms for each of 365 nights (365 X 50 equals the total roomsrented for the year). Tim's cost to clean a room is $12.50. TheDuffy's Ma id Service quote is $18.50 per room plus a fixed costof $25,000 for sundry items such as uniforms with the motel'sname. Tim's annual fixed cost for space, equipment, and suppliesis $6 1,000. Which is the preferred process for Tim, and why?arrow_forwardPlease no written by hand solutionsarrow_forward
- J 1 ue K Beth Zion Hospital has received initial certification from the state of California to become a center for liver transplants. The hospital, however, must complete its first 10 transplants under great scrutiny and at no cost to the patients with the hospital picking the expenses. The cost per hour of surgery is estimated to be $5,000. The very first transplant, just completed, required 27 hours. On the basis of research at the hospital, Beth Zion estimates that it will have an 75% learning curve. Using Table E.3, estimate the time it will take to complete: a) the 10th transplant hours (round your response to two decimal places). Learning Curve Coefficients Unit Number (N) 10 Unit Time .385 75% Total Time 5.589 Unit Time .477 80% Total Time 6.315 Unit Time .583 85% Total Time 7.116 Xarrow_forwardA manager is trying to decide whether to purchase a certain part or to have it produced internally.Internal production could use either of two processes. One would entail a variable cost of $17 perunit and an annual fixed cost of $200,000; the other would entail a variable cost of $14 per unitand an annual fixed cost of $240,000. Three vendors are willing to provide the part. Vendor A hasa price of $20 per unit for any volume up to 30,000 units. Vendor B has a price of $22 per unit for demand of 1,000 units or less, and $18 per unit for larger quantities. Vendor C offers a price of$21 per unit for the first 1,000 units, and $19 per unit for additional units.a. If the manager anticipates an annual volume of 10,000 units, which alternative would be bestfrom a cost standpoint? For 20,000 units, which alternative would be best?arrow_forwardHandy-Maid Cleaning Service is considering off ering anadditional line of services to include professional offi ce cleaning.Annual fi xed costs for this additional service are estimated tobe $9000. Variable costs are estimated at $50 per unit of service.If the price of the new service is set at $80 per unit of service,how many units of service are needed for Handy-Maid to breakeven?10. Easy-Tech Soft ware Corporation is evaluating theproduction of a new soft ware product to compete with thepopular word processing soft ware currently available. Annualfi xed costs of producing the item are estimated at $150,000, andthe variable cost is $10 per unit. Th e current selling price of theitem is $35 per unit, and the annual sales volume is estimated at50,000 units.(a) Easy-Tech is considering adding new equipment thatwould improve soft ware quality. Th e negative aspect ofthis new equipment would be an increase in both fi xedand variable costs. Annual fi xed costs would increase by$50,000 and…arrow_forward
- Borges Machine Shop, Inc. has a 1-year contract for the production of 200,000 gear housings for a new off-road vehicle Owner Luis Borges hopes the contract will be extended and the volume increased next year Borges has developed costs for three alternatives. They are general-purpose equipment (GPE), flexible manufacturing system (FMS), and expensive, but efficient, dedicated machine (DM) The cost data follow Annual contracted units Annual fixed cost General Purpose Equipment (GPE) 200.000 $150.000 $15.00 Per unit variable cost The option GEE is best when the contracted volume is below units (enter your response as a whole number) Flexible Manufacturing System (FMS) 200,000 $250.000 $14.00 Dedicated Machine (DM) 200.000 $525,000 $13.00arrow_forward“How many dozen should I put in the proofer?” asked Elizabeth, the new baker at the Sands Cafeteria. Rami El‐Hussieny was the day shift operations manager, and, unfortunately, he did not know how to answer Elizabeth's question. What she wanted to know was simple enough: How many dozen rolls should be placed in the proofer in anticipation of the night's dinner business? The problem was that the frozen dinner roll dough used at the Sands Cafeteria needed to be proof for at least 2 hours prior to being baked for 15 minutes. If too many rolls were proofed, they would never be needed, but they would still have to be baked and made into bread dressing or even tossed out. If too few dozen were proofed and the night was busier than anticipated, they would run out of “Fresh Baked Rolls” (one of the restaurant's signature items), and Rami knew that the night manager would be really upset. It was a daily guess, and sometimes Rami missed the guess! He wondered if a prebaked roll with a shelf life…arrow_forwardA biotech firm is considering abandoning its old plant, built 23 years ago, andconstructing a new facility that has 50% more square footage. The original cost of the old facility was $300,000, and its capacity in terms of standardizedproduction units is 250,000 units per year. The capacity of the new laboratoryis to be 400,000 units per year. During the past 23 years, costs of laboratoryconstruction have risen by an average of 5% per year. If the cost-capacity factor, based on square footage, is 0.80, what is the estimated cost of the newlaboratory?arrow_forward
- Q3) Case study below: Checkers plans to open its first “dark store” later this year to support growing demand for its Sixty60 on-demand grocery app. A dark store is a retail outlet that exists exclusively to support on-demand deliveries. It does not have a store front or retail customers, but purely assists with order fulfilment.It will be in Bree Street in Cape Town’s central business district, and comes as the group considers the capacity of its store base to meet the growing demand from SA’s leading grocery app.The Checkers Sixty60 one-hour delivery service was launched in November 2019 and order volumes continue to grow exponentially. It is already available in 300 locations across the country - up from 233 locations last year. About 23 000 products are on offer at in-store prices and it has created almost 6 300 jobs, according to Checkers. The need for such a store format is due to Checkers limiting the number of Sixty60 deliveries it can support from each retail store, which is…arrow_forwardBorges Machine Shop, Inc., has a 1-year contract for the production of 75,000 gear housings for a new off-road vehicle, Owner Luis Borges hopes the contract will be extended and the volume increased next year. Borges has developed costs for three alternatives. They are general-purpose equipment (GPE), flexible manufacturing system (FMS), and expensive, but efficient, dedicated machine (DM). The cost data follow Annual contracted units Annual fixed cost Per unit variable cost General-Purpose Equipment (GPE) 75,000 $100,000 $16.00 Flexible Manufacturing System (FMS) 75,000 $225,000 $14.00 Dedicated Machine (DM) 75,000 $450,000 $13.75 Based on the total cost, the process that is best suited for the current contracted volume is Suppose the contracted volume changes to 275,000 gear housings. Based on the total cost, the process that is best suited for the new volume is Suppose the contracted volume changes to 375,000 gear housings. Based on the total cost, the process that is best suited…arrow_forwardPlease do not give solution in image format thanku Bob's candle factory is considering three different manufacturing options. Option A uses hand labor with fixed costs of $10,000 and variable costs of $2.75/candle. Option B uses a combination of hand and automation with fixed costs of $15,000 and variable costs of $1.10/candle. Option C is highly automated with fixed costs of $20,000 and variable costs of $0.75/candle. a. If demand for Bob's candles is 2500, which option should he pick, and what is the cost? b. If demand for Bob's candles is 4500 which option should he pick, and what is the cost?arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,MarketingMarketingISBN:9780357033791Author:Pride, William MPublisher:South Western Educational Publishing
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Marketing
Marketing
ISBN:9780357033791
Author:Pride, William M
Publisher:South Western Educational Publishing