Question
Book Icon
Chapter 7.S, Problem 39P

a)

Summary Introduction

To determine: The present value profit or loss of the deal.

Introduction:

Present value (PV):

It is the value that is in present form of money in contrast to some future amount. This is achieved when it is invested in compound interest.

Net present value (NPV):

The NPV is the measurement of profit that is calculated by subtracting the present values of cash outflows and cash inflows. The NPV is used as a tool to measure the profitability of investing in a project.

a)

Expert Solution
Check Mark

Answer to Problem 39P

The present value profit or loss of the deal is $77,750.

Explanation of Solution

Given information:

Initial cost = $1,000,000

Salvage cost= $50,000

Interest rate = 10%

Yearly maintenance= $75,000

Yearly dues = $300,000

Number of members = 500

Annual dues per member=Yearly duesNumber of members=$300,000500=$600

From the present value of $1 table,

PV annuity factor @ 10% for 0 year= 1.000

PV annuity factor @ 10% for 1 year= 0.909

PV annuity factor @ 10% for 2 year= 0.826

PV annuity factor @ 10% for 3 year= 0.751

PV annuity factor @ 10% for 4 year= 0.683

PV annuity factor @ 10% for 5 year= 0.621

Calculation of cost at year 0:

The cost at year 0 is calculated summing the initial investment and yearly maintenance and expenses.

Cost=Initial investment+Yearly maintenance=$1,000,000+$75,000=$1,075,000

Calculation revenue for year 5:

The revenue of year 5 is calculated by adding the yearly dues and the salvage cost.

Revenue=Yearly dues+Salvage cost=$300,000+$50,000=$350,000

The cost for year 1 to year 4 is $75,000. The revenue for year 1 to year 4 is $300,000.

Formula to calculate profit for each year:

Profit=Revenues-Cost

Formula to calculate net present value (NPV) for each year:

Net Present value=Annuity factor×Profit

Formula to calculate total profit:

Total profit=Individual profits of all the years

Formula to calculate total net present value (NPV):

Total NPV=Individual NPV of all the years

Calculation of profit for each year:

The profit is calculated by subtracting the yearly revenues with yearly cost.

Year 0 Profit:

Profit=$300,000-$1,075,000=-$775,000

Year 1 Profit:

Profit=$300,000-$75,000=$225,000

Year 2 Profit:

Profit=$300,000-$75,000=$225,000

Year 3 Profit:

Profit=$300,000-$75,000=$225,000

Year 4 Profit:

Profit=$300,000-$75,000=$225,000

Year 5 Profit:

Profit=$350,000-$75,000=$275,000

Calculation of total profit:

The total profit is calculated by summing all the individual year profits.

Total profit=-$775,000+$225,000+$225,000+$225,000+$225,000+$275,000=$400,000

Calculation of net present value (NPV):

The net present value for each year is calculated by multiplying the annuity factor with the respective profit.

Year 0 NPV:

Net Present value=1.000×(-$775,000)=-$775,000

Year 1 NPV:

Net Present value=0.909×$225,000=$204,525

Year 2 NPV:

Net Present value=0.826×$225,000=$185,850

Year 3 NPV:

Net Present value=0.751×$225,000=$168,975

Year 4 NPV:

Net Present value=0.683×$225,000=$153,675

Year 5 NPV:

Net Present value=0.621×$275,000=$139,725

Calculation of total net present value (NPV):

The total net present value (NPV) is calculated by summing all the individual NPV values.

Total NPV=-$775,000+$204,525+$185,850+$168,975+$153,675+$139,725=$77,750

Hence, the present value profit of the deal is $77,750.

b)

Summary Introduction

To determine: The special deal should be made or not made.

Introduction:

Present value (PV):

It is the value that is in present form of money in contrast to some future amount. This is achieved when it is invested in compound interest.

Net present value (NPV):

The NPV is the measurement of profit that is calculated by subtracting the present values of cash outflows and cash inflows. The NPV is used as a tool to measure the profitability of investing in a project.

b)

Expert Solution
Check Mark

Answer to Problem 39P

The special deal should be made.

Explanation of Solution

Given information:

Initial cost = $0

Salvage cost= $0

Interest rate = 10%

Yearly maintenance= $0

Yearly dues = $600

From the present value of $1 table,

PV annuity factor @ 10% for 0 year= 1.000

PV annuity factor @ 10% for 1 year= 0.909

PV annuity factor @ 10% for 2 year= 0.826

PV annuity factor @ 10% for 3 year= 0.751

PV annuity factor @ 10% for 4 year= 0.683

PV annuity factor @ 10% for 5 year= 0.621

The cost for year 0 to year 5 is $0. The revenue for year 0 to year 5 is $600.

Formula to calculate profit for each year:

Profit=Revenues-Cost

Formula to calculate net present value (NPV) for each year:

Net Present value=Annuity factor×Profit

Formula to calculate total profit:

Total profit=Individual profits of all the years

Formula to calculate total net present value (NPV):

Total NPV=Individual NPV of all the years

Calculation of profit for each year:

The profit is calculated by subtracting the yearly revenues with yearly cost.

Year 0 Profit:

Profit=$600-$0=$600

Year 1 Profit:

Profit=$600-$0=$600

Year 2 Profit:

Profit=$600-$0=$600

Year 3 Profit:

Profit=$600-$0=$600

Year 4 Profit:

Profit=$600-$0=$600

Year 5 Profit:

Profit=$600-$0=$600

Calculation of total profit:

The total profit is calculated by summing all the individual year profits.

Total profit=$600+$600+$600+$600+$600+$600=$3,600

Calculation of net present value (NPV):

The net present value for each year is calculated by multiplying the annuity factor with the respective profit.

Year 0 NPV:

Net Present value=1.000×$600=$600

Year 1 NPV:

Net Present value=0.909×$600=$545

Year 2 NPV:

Net Present value=0.826×$600=$496

Year 3 NPV:

Net Present value=0.751×$600=$451

Year 4 NPV:

Net Present value=0.683×$600=$410

Year 5 NPV:

Net Present value=0.621×$600=$373

Calculation of total net present value (NPV):

The total net present value (NPV) is calculated by summing all the individual NPV values.

Total NPV=$600+$545+$496+$451+$410+$373=$2,274

The present value profit of the deal is $2,274. The PV profit is less than $3,000. This deal is more worth than the health club deal.

Hence, the special must be made.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
Can you guys help me with this? Thank you! Here's the question: Compared to the CONSTRAINT model, how has the network changed? How do you plan to add contingency to your network? Please answer this thoroughly Here's the what-if scenario: Assume that the LA warehouse becomes temporarily or even indefinitely disabled since facing a large-scale labor disruption. Re-optimize the network considering this new constraint. Here's the scenario comparison analysis:  Scenario Constraint Scenario vs What-if Scenario Summary The Constraint Scenario exhibits a higher total cost of $7,424,575.45 compared to the What-if Scenario's total cost of $6,611,905.60, signifying a difference of approximately $812,669.85, which indicates a more expensive operation in the Constraint Scenario. The average service time is slightly higher in the Constraint Scenario (0.72 days vs. 0.70 days), suggesting that the What-if Scenario provides a marginally quicker service. Moreover, the average end-to-end service time…
Can you guys help me with this? Thank you! Here's the question: Compared to the CONSTRAINT model, how has the network changed? How do you plan to add contingency to your network? Please answer this throughly Here's the what-if scenario: Assume that Dallas plant has lost power. It cannot serve the DCs anymore and has to remain locked indefinitely. Re-optimize the network considering this new constraint. Here's the scenario comparison analysis:  Scenario Constraint Scenario vs What-if Scenario Summary In comparing the Constraint Scenario to the What-if Scenario, a few key differences highlight the efficiencies evident in the supply chain. Firstly, the total cost in the Constraint Scenario is lower at $7,424,575.45, while the What-if Scenario incurs a total cost of $7,486,369.12, resulting in a cost delta of $61,793.67. Additionally, although both scenarios exhibit the same average service time of 0.72 days, the What-if Scenario has a more favorable average end-to-end service time of 2.41…
Employee In-Service Training ASSIGNMENT: In-Service Training. The intern is required to plan and implement two in-service training sessions for employees. Each in-service should last at least 10 but not more than 30 minutes and should be given to all employees affected. The preceptor or supervisor/unit manager must approve all in-service topics. 1) One presentation should be related to a policy or procedure of any kind (e.g. proper use of equipment); 2) The second presentation must be related to sanitation or safety. For each in-service presentation, the intern must develop a written class plan and a visual aid (may be a handout, poster, PowerPoint slide presentation, etc.) appropriate to the life experiences, cultural diversity and educational background of the target audience. The intern must also measure behavior change. Note, this cannot be measured by a written pre- and post- test. That would be measuring knowledge. The intern mustactually observe and document that the learners…

Chapter 7 Solutions

Principles Of Operations Management

Ch. 7.S - Prob. 11DQCh. 7.S - Prob. 12DQCh. 7.S - What are the techniques available to operations...Ch. 7.S - Amy Xias plant was designed to produce 7,000...Ch. 7.S - For the post month, the plant in Problem S7.1,...Ch. 7.S - Prob. 3PCh. 7.S - Prob. 4PCh. 7.S - Prob. 5PCh. 7.S - The effective capacity and efficiency for the next...Ch. 7.S - Southeastern Oklahoma State Universitys business...Ch. 7.S - Prob. 8PCh. 7.S - Prob. 9PCh. 7.S - Prob. 10PCh. 7.S - The three-station work cell illustrated in Figure...Ch. 7.S - The three-station work cell at Pullman Mfg., Inc....Ch. 7.S - The Pullman Mfg., Inc., three-station work cell...Ch. 7.S - Prob. 14PCh. 7.S - 10 minutes per unit. Part 2 is simultaneously...Ch. 7.S - Prob. 16PCh. 7.S - Prob. 17PCh. 7.S - Using the data in Problem S7.17: a) What is the...Ch. 7.S - Prob. 19PCh. 7.S - Prob. 20PCh. 7.S - Prob. 21PCh. 7.S - Prob. 22PCh. 7.S - Prob. 23PCh. 7.S - Prob. 24PCh. 7.S - Prob. 25PCh. 7.S - Prob. 26PCh. 7.S - Prob. 27PCh. 7.S - Prob. 28PCh. 7.S - Prob. 29PCh. 7.S - Prob. 30PCh. 7.S - Prob. 31PCh. 7.S - Prob. 32PCh. 7.S - Prob. 33PCh. 7.S - Prob. 34PCh. 7.S - Prob. 35PCh. 7.S - Prob. 36PCh. 7.S - Prob. 37PCh. 7.S - Prob. 38PCh. 7.S - Prob. 39PCh. 7.S - Prob. 40PCh. 7.S - Prob. 41PCh. 7.S - Prob. 42PCh. 7.S - Prob. 43PCh. 7.S - Prob. 44PCh. 7.S - Prob. 45PCh. 7.S - Prob. 1VCCh. 7.S - a capacity expansion plan and a new 11-story...Ch. 7.S - a capacity expansion plan and a new 11-story...Ch. 7 - Ethical Dilemma For the sake of efficiency and...Ch. 7 - Prob. 1DQCh. 7 - Prob. 2DQCh. 7 - Prob. 3DQCh. 7 - Prob. 4DQCh. 7 - Prob. 5DQCh. 7 - Prob. 6DQCh. 7 - Prob. 7DQCh. 7 - Prob. 8DQCh. 7 - Prob. 9DQCh. 7 - Prob. 10DQCh. 7 - Prob. 11DQCh. 7 - Prob. 12DQCh. 7 - Prob. 13DQCh. 7 - Prob. 14DQCh. 7 - Prob. 15DQCh. 7 - Prob. 16DQCh. 7 - Prob. 17DQCh. 7 - Prob. 18DQCh. 7 - Prob. 19DQCh. 7 - Prob. 1PCh. 7 - Usingthedatain Problem 7.1, determinethemost...Ch. 7 - Prob. 3PCh. 7 - Refer to Problem 7.1. If a contract for the second...Ch. 7 - Stan Fawcetts company is considering producing a...Ch. 7 - Prob. 6PCh. 7 - Prob. 7PCh. 7 - Prob. 8PCh. 7 - Metters Cabinets, Inc., needs to choose a...Ch. 7 - Prob. 10PCh. 7 - Nagle Electric. Inc., of Lincoln, Nebraska, must...Ch. 7 - Stapleton Manufacturing intends to increase...Ch. 7 - Prepare a flowchart for one of the following: a)...Ch. 7 - Prepare a process chart for one of the activities...Ch. 7 - Prob. 15PCh. 7 - Prob. 16PCh. 7 - Prob. 17PCh. 7 - Prob. 1CSCh. 7 - Prob. 2CSCh. 7 - Prob. 3CSCh. 7 - Process Strategy at Wheeled Coach Wheeled Coach,...Ch. 7 - Prob. 1.2VCCh. 7 - Prob. 1.3VCCh. 7 - Prob. 1.4VCCh. 7 - Alaska Airlines: 20-Minute Baggage...Ch. 7 - Prob. 2.2VCCh. 7 - Prob. 2.3VCCh. 7 - Prob. 2.4VCCh. 7 - Prob. 2.5VCCh. 7 - Prob. 3.1VCCh. 7 - Prob. 3.2VCCh. 7 - Prob. 3.3VCCh. 7 - Prob. 3.4VC
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
  • Text book image
    Practical Management Science
    Operations Management
    ISBN:9781337406659
    Author:WINSTON, Wayne L.
    Publisher:Cengage,
    Text book image
    Marketing
    Marketing
    ISBN:9780357033791
    Author:Pride, William M
    Publisher:South Western Educational Publishing
    Text book image
    Purchasing and Supply Chain Management
    Operations Management
    ISBN:9781285869681
    Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
    Publisher:Cengage Learning
  • Text book image
    MARKETING 2018
    Marketing
    ISBN:9780357033753
    Author:Pride
    Publisher:CENGAGE L
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Text book image
Marketing
Marketing
ISBN:9780357033791
Author:Pride, William M
Publisher:South Western Educational Publishing
Text book image
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Text book image
MARKETING 2018
Marketing
ISBN:9780357033753
Author:Pride
Publisher:CENGAGE L
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY