Concept explainers
A
Interpretation:The network diagram is to be drawn.
Concept Introduction:Network diagram is a graphical representation of tasks in symbols and lines for easy understanding. The networking technique is a method for planning, programming and controlling of work in progress. It is helpful for effective management. It helps the management for decisions.
B
Interpretation:The critical path and duration of the project are to be determined.
Concept Introduction:Critical path is a technique which has various stages. It is used to calculate the optimum time is requiredto complete a task. It is the longest length of time for completion of the project.
C
Interpretation:The slack for each activity is to be determined.
Concept Introduction:Slack is the time evaluatedwhich causes the delay during any activity. For calculation, the earliest and the latest time of activity are required.
Want to see the full answer?
Check out a sample textbook solutionChapter 7 Solutions
Operations Management: Processes and Supply Chains (12th Edition) (What's New in Operations Management)
- Paul Silver, owner of Sculptures International, just initiateda new art project. The following data are available for theproject:Activity Activity Time (days) Immediate Predecessor(s)A 4 —B 1 —C 3 AD 2 BE 3 C, Da. Draw the network diagram for the project.b. Determine the project’s critical path and duration.c. What is the slack for each activity?arrow_forwardPlease I want to solve the point 1&2 in 10 minutesarrow_forwardNeed help with problem 2arrow_forward
- A project manager has compiled a list of major activities that will be required to install a new CCTV system in the office. The list includes estimated completion time for activities and precedence relationship. Determine the Critical Path Activities Compute for Total Project Duration Note: Use MS Excel QM Activity Immediate Predecessor Estimated Times (weeks) 2-4-6 A D A 6-8-10 E D 7-9-12 E 2-3-5 IF A 3-4-8 F 5-7-9 2-2-3 2-3-6 J 3-4-5 K 4-5-8 5-8-12 M 1-1-1 IN M 6-7-11 8-9-13 End |Н, G, К, Оarrow_forwardEarned value analysis is the project management tool that is used to measure project progress. You are a project manager in company XYZ that responsible to handling the packaging machine project with the total cost budgeting is RM100,000. There are including RM24,000 (Design), RM60,000 (build) and RM16,000 (install & test). The information regarding on the project progress development in weeks 8 as shown in Table 2 below: No Type Cumulative Budgeted Cost (CBC) 2 Cumulative Actual Cost (CAC) Cumulative Earned Value (CEV) 1 3 TOTAL RM i. ii. iii. iv. 64,000 68,000 54,000 100,000 Percentage 64.0 Cost performance Index (CPI) [hint: CEV/CAC] Cost variance (VC) [hint: CEV-CAC] 68.0 54.0 a) Based on question 2(a), calculate and elaborate the various of indicators of cost performance for this project based on the respective below: 100.0 Forecasted cost of completion (FCAC) with action taken [hint: TBC/CPI] Forecasted cost of completion (FCAC) without any action taken [hint: CAC + [TBC-CEV]arrow_forwardPlease do not give solution in image format thankuarrow_forward
- Reliable Garage is completing production of the J2000 kit car. The following data are available for the project:a. Draw the network diagram for the project.b. Determine the project’s critical path and duration.c. What is the slack for each activity?arrow_forwardThe following information is known about a project toupgrade a point-of-sale system at Kids and Tots Apparel.Activity Activity Time (days) Immediate Predecessor(s)A 7 —B 2 A C 4 AD 4 B, CE 4 DF 3 EG 5 Ea. Draw the network diagram for this project.b. Determine the critical path and project duration.c. Calculate the slack for each activity.arrow_forwardDraw the network diagram, and find out the critical path and project duration?arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.