Operations Management: Processes and Supply Chains (12th Edition) (What's New in Operations Management)
12th Edition
ISBN: 9780134741062
Author: Lee J. Krajewski, Manoj K. Malhotra, Larry P. Ritzman
Publisher: PEARSON
expand_more
expand_more
format_list_bulleted
Concept explainers
Question
Chapter 7, Problem 4AME
Summary Introduction
Interpretation:The effect of increasing activity A by 1 week after becoming critical is to be determined.
Concept Introduction: Critical path is a method used to evaluate the project. It is used when the activity times are deterministic. It is the longest path in the network. It defines the minimum time required for completion of the project.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Activity E has an optimistic time of 9 days, a most likely time of 12 days, and a pessimistic time of 15 days. Estimate its expected time and standard deviation.
Crashed Completion
time (week)
Crashed Cost per
Preceding
Activity
Normal Completion
Time (week)
Activity
week
A
7
5
$600
$700
$400
$800
12
10
A
8
2
D
9
7
E
C, D
5
4
$300
F
E
9
8
$500
G
D, F
10
10
Find the minimum possible completion time of the project by considering the crashed
completion times and the minimal total cost of that crashing the project.
Highlight the critical and non-critical activities of the finally completed project by taking into
account the crashed times of activities.
Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before a training program of this nature
could be conducted. The activities, immediate predecessors, and times appear in the accompanying table:
Immediate Predecessor(s)
Activity
A
B
C
D
E
F
G
This exercise contains only parts b, c, and d.
b) The critical activities for the leadership training program development project are A-E-G
c) The project length for the leadership training program development project = 22 days.
d) Slack time for each of the activities is:
B
A, D
C
E, F
Activity
A
B
Slack Time
0
Time (days)
10
6
3
2
4
8
Chapter 7 Solutions
Operations Management: Processes and Supply Chains (12th Edition) (What's New in Operations Management)
Ch. 7 - One of your colleagues comments that software is...Ch. 7 - Explain how to determine the slack for each...Ch. 7 - Define risk as it applies to projects. What are...Ch. 7 - Consider the following data for a project to...Ch. 7 - The following information is known about a project...Ch. 7 - A project for improving a billing process has the...Ch. 7 - Prob. 4PCh. 7 - Prob. 5PCh. 7 - Consider the following information for a project...Ch. 7 - Consider the following data for a project to...
Ch. 7 - Paul Silver, owner of Sculptures International,...Ch. 7 - Prob. 9PCh. 7 - The following information concerns a project to...Ch. 7 - Consider a project to produce custom door moldings...Ch. 7 - Table 7.5 contains information about au...Ch. 7 - The Advanced Tech Company has a project to design...Ch. 7 - Prob. 14PCh. 7 - Table 7.8 contains data for the installation of...Ch. 7 - The diagram in Figure 7.12 was developed for the...Ch. 7 - Prob. 17PCh. 7 - Prob. 18PCh. 7 - You are the project manager of the software...Ch. 7 - Jordanne King, the project manager for Webjets...Ch. 7 - Recently, you were assigned to manage a project to...Ch. 7 - In Solved Problem 2, estimate the probability that...Ch. 7 - The director of continuing education at Bluebird...Ch. 7 - Gabrielle Kramer, owner of Pet Paradise, is...Ch. 7 - The project manager of Good Public Relations...Ch. 7 - Consider the office renovation project data in...Ch. 7 - Activity B and activity K are critical activities....Ch. 7 - Prob. 2AMECh. 7 - Prob. 3AMECh. 7 - Prob. 4AMECh. 7 - Prob. 5AMECh. 7 - Assess the four categories of a risk-management...Ch. 7 - Prob. 2VCCh. 7 - Assume you are Denise Tower and have...Ch. 7 - Prob. 1CCh. 7 - Prob. 2CCh. 7 - Prob. 3CCh. 7 - Prob. 4C
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- For Activity A, B, C, D, E, F, Garrow_forwardPreceding Activity Crashed Cost per week $600 $700 $400 Activity Normal Completion Time (week) Crashed Completion time (week) A 7 5 B 12 10 A 8 2 $800 $300 $500 E C, D 5 4 F E 9 8 D. F 10 10 i. Draw the network diagram linking all the activities in a way that it shows if there exist any preceding activity/activities before starting each of the mentioned activities in the above table, ii. Showing the earliest start time, the earliest finish time, the latest start time and the latest finish time of each of the activities in the project determine the completion time of the project and the critical path. ii. Find the slack time (delay time) of each of the activities, the critical and the non-critical activities. Find the minimum possible completion time of the project by considering the crashed completion times and the minimal total cost of that crashing the project. iv. Need proper handwritten answers. Thank you!arrow_forwardAn activity on a PERT network has these time estimates: optimistic = 2, most likely = 3, and pessimistic = 6. What is its expected activity time and variance? 3.67; 1 O 4.33; 1 O 3.33; 0.44 O 4; 0.44arrow_forward
- A competitor of Kozar International Inc. has begun marketing a new, instant-developing film project. Kozar has had a similar product under study in its research and development (R&D) department but has not yet been able to begin production. Because of the competitor’s action, top managers have asked for a speedup of R&D activities so that Kozar can produce and market instant film at the earliest possible date. The predecessor information and activity time estimates in months are as follows: Draw the Project Networkarrow_forwardA competitor of Kozar International Inc. has begun marketing a new, instant-developing film project. Kozar has had a similar product under study in its research and development (R&D) department but has not yet been able to begin production. Because of the competitor’s action, top managers have asked for a speedup of R&D activities so that Kozar can produce and market instant film at the earliest possible date. The predecessor information and activity time estimates in months are as follows: Develop an activity schedule for this project using early and late start and finish times, compute activity slack time and define the critical activities.arrow_forwardA competitor of Kozar International Inc. has begun marketing a new, instant-developing film project. Kozar has had a similar product under study in its research and development (R&D) department but has not yet been able to begin production. Because of the competitor’s action, top managers have asked for a speedup of R&D activities so that Kozar can produce and market instant film at the earliest possible date. The predecessor information and activity time estimates in months are as follows: A: Draw the Project Network B: Develop an activity schedule for this project using early and late start and finish times, compute activity slack time, and define the critical activities.arrow_forward
- Describe the Evaluation and Review Technique (PERT) for network planning and scheduling?arrow_forwardThe table below contains data for the installation of new equipment in a manufacturing process for a steel corporation. Your company is responsible for the installation project. Indirect costs are $6,000 per week, and a penalty cost of $10,000 per week will be incurred by your company for every week the project is delayed beyond week 15. Activity Immediate Predecessor(s) Normal Time (weeks) Crash Time (weeks) Normal Cost ($) Crash Cost ($) A None 2 1 7,000 10,000 B None 2 2 3,000 3,000 C A 3 1 12,000 40,000 D B 3 2 12,000 28,000 E C 1 1 8,000 8,000 F D, E 5 3 5,000 15,000 G E 3 2 9,000 18,000 H F, G 8 6 14,000 32,000 Construct a network diagram for the project. What are the project completion time and the total cost under normal conditions? What is the shortest time duration for this project regardless of cost? What is the resulting total cost? What is the…arrow_forwardPROJECT A Project A is a planning, design and implementation infrastructure development project (about GHS 15 million in value and expected to take about three years from the start of planning to completion), which is well advanced in its planning component. While the project is progressing well in terms of time, cost and quality, there are a number of sustainability and stakeholder management issues with it. This project is being undertaken in an environmentally sensitive area in which leave several property owners who are quite concerned with the impact of the project on their environment. They are concerned that a thorough environmental risk assessment has not been undertaken with respect to the long-term impact on the sensitive bushland area in which they live. They are also concerned that completion of the project, through providing the basis for significant property development and destruction of bushland, will forever change the social fabric of their region. They have formed a…arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY