Summary Introduction

Interpretation: The number of week’s activity ‘A’ can be delayed, until it becomes an activity in the critical path and the consequences of activity ‘A’ becoming critical are to be determined.

Concept Introduction: The longest time period that a particular activity in a project could be delayed without making an impact on its completion date is known as activity slack. This, in other words mean that activities in the critical path cannot have slack as they cannot be delayed. Slack details of activities are useful as they can be used to identify activities that require close attention.

Blurred answer
Students have asked these similar questions
Development of Version 2.0 of a particular accounting software product is being considered by Jose Noguera's technology firm in Baton Rouge. The activities necessary for the completion of this project are listed in the following table: Total Cost Normal Time Crash Time Normal with Immediate Activity (weeks) (weeks) Cost Crashing Predecessor(s) $2,200 $2,100 $2,900 $2,900 A 4 3 1 C 3 3 $500 $500 $2,500 $1,000 $3,200 $2,800 $1,375 $4,600 $2,100 8. E 6. 3 G 4 $1,600 D, E a) Based on the given information regarding the activities for the project, the project length = weeks. %3D b) The total cost required for completing this project on normal time = $ %3D c) For reducing the duration of the project by one week, the activity that should be crashed first is activity The cost of the project based on the first activity selected for crashing will increase by $ d) The maximum weeks by which the project can be reduced by crashing = weeks. %3D Total cost of crashing the project to minimum (or…
The CEO of Carol O'Lights Manufacturing, produces custom-built relay devices for auto makers.  The most recent project undertaken by Ms. O'Lights requires 11 different activities. The activities necessary to build an experimental relay model and related data are given in the following table.   What is the Late Start on Activity C? What is the slack on Activity C? What is the slack on Activity B? What is the critical path? What is the Early Finish on Activity H?
If Activity C has an expected time estimate of 8 days, which of the following statements is TRUE? * The activity time estimates for Activity C are: 1, 7, and 19 days Activity C can be delayed for a maximum of 5 days Activity C should not be delayed The activity time estimates for Activity C are: 2, 4, and 9 days

Chapter 7 Solutions

Operations Management: Processes and Supply Chains (12th Edition) (What's New in Operations Management)

Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Text book image
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Text book image
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Text book image
Business in Action
Operations Management
ISBN:9780135198100
Author:BOVEE
Publisher:PEARSON CO
Text book image
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Text book image
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY