Recently, you were assigned to manage a project to remodel the seminar room for your company. You have constructed a network diagram depicting the various activities in the project (Figure 7.13). In addition, you have asked your team to estimate the amount of time that they would expect each of the activities to take. Their responses are shown in the following table.
- What is the expected completion time of the project?
- What is the probability of completing the project in 21 days or less?
- What is the probability of completing the project in 17 days or less?
Trending nowThis is a popular solution!
Chapter 7 Solutions
Operations Management: Processes and Supply Chains (12th Edition) (What's New in Operations Management)
Additional Business Textbook Solutions
Principles of Operations Management: Sustainability and Supply Chain Management (10th Edition)
Business in Action (8th Edition)
OPERATIONS MANAGEMENT IN THE SUPPLY CHAIN: DECISIONS & CASES (Mcgraw-hill Series Operations and Decision Sciences)
Business in Action
Operations Management
Operations Management, Binder Ready Version: An Integrated Approach
- Following are the three time estimates for a task in a project: optimistic completion time = 2 weeks most likely completion time = 4 weeks pessimistic completion time = 7 weeks Compute the expected time for the task.arrow_forwardPlease helparrow_forwardThree activities are candidates for crashing on a project network for a large computer installation (all are, of course, critical) Activity details are in the following table: a) Activity that should be orashed first to reduce the project duration by 1 day is b) Activity that should be crashed next to reduce the project duration by one additional day is c) Total cost of crashing the project by 2 days = S (Enter your response as an integer) Normal Activity Time (days) A B C 7 4 11 Crash Normal Time (days) Cost $8,000 $1,200 $4,200 6 2 9 Total Cost with Crashing Immediate Predecessor(s) $6,500 $3,000 $6.200 A Barrow_forward
- Project Management involves the management of labour, material and plants, and equipment. Time management however demands the analysis of factors prevailing on the project.Discuss four (4) factors that affect the times it will take to complete the projectarrow_forwardMarket Fresh Foods is looking to develop a new strategic plan. Jay Jones has been developing a project plan and has identified the following tasks, precedence relations, and normal task durations. tasks predecessors task duration start 0 A start 40 B A 34 C A 31 D A 38 E A 28 F C,D 18 G B,F 13 H E,G 22 end H 0 Jay has studied project management at the University of Portland and knows that the starting and ending time of any task may be determined from the information in the table using the critical path method. Assume the following notation when answering the questions below: Metric Description ES Early start time for task EF Early finsh time for task LS Late start time for task LF Late finsh time for task TS Total slack for task FS Free slack for task IS Independent slack for task SS safety slack for task Please provide the CPM result for each of the following metrics: ES_{end} = LF_{D} = FS_{D} = TS_{G} = IS_{G} =arrow_forwardFor this assignment, you will design a risk management plan for a project titled “prolonged waiting times for patients in a large outpatient hospital” that will include the following elements: Risk Register/Matrix (list of at least 5 (five) risks along with the associated impact and probability scores along with risk score) Contingency plan (list of any risks you will plan for in advance along with what triggers the contingency). Be sure to include any information useful to stakeholders on the rationale for the creation of these elements as well as any outside references supporting the risk management plan.arrow_forward
- please answer within 30 minutesarrow_forwardUsing project management software to explore the effects of various scenarios on the project is called: projection sorting what-if analysis filteringarrow_forwardManagement & Science University (MSU) have appointed you as a project manager to conduct a Joint Application Design (JAD) session with members from various departments. As a project manager, you are required to develop a specific schedule for the tasks listed below. The estimated task duration for each shown in parentheses. First, you must contact and brief the participants and explain their responsibilities (1 day). Then you must obtain approval from their department managers (3 days). After you have obtained the approval, you can begin the two tasks where you can prepare the agenda for the JAD session (7 days) and arrange the meeting room (2 days) When the agenda is ready, you can start two more concurrent tasks which are preparing the information packets (4 days) and to create visual aids (8 days). When the meeting room is arranged and information packets are ready, you can send out an email to all participants (1 day). Finally, after the e-mail is sent to participants and the…arrow_forward
- You are in charge of a project at the local community center. The center needs to remodel one of the rooms in time for the start of a new program. Delays in the project mean that the center must rent other space at a nearby church at additional cost. Time and cost data for your project are contained in the table. Your interest is in minimizing the cost of the project to the community center. a. Using the normal times for each activity, what is the earliest date you can complete the project? b. Suppose the variable overhead costs are $50 per day for your project. Also, suppose that the center must pay$40 per day for a temporary room on day 15 or beyond. Find the minimum-cost project schedule.arrow_forwardThe activities necessary for the completion of a project are listed in the table below (Time in weeks). You are asked to complete the project 1 week ahead of time. You should crash Activity ________. This will incur an additional cost of $_________ .arrow_forwardBelow is a project listed in a table with: activity, predecessor, and duration. Activity A B с D E F G H Predecessor none A A с B B D, E, F G Fill in the chart below by filling in: early start (ES), early finish (EF), ☐late start (LS), A late finish (LF), duration (D), and float (F). Then, answer the questions based on the chart. Hint: You can use the Word tools to fill in the chart, or you can draw the chart by hand, then photograph or scan your graph to submit it. 1. Fill in the chart below. B Duration (weeks) C 5 3 8 13 7 9 10 7 - D E F G Harrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.