Operations Management: Processes and Supply Chains (12th Edition) (What's New in Operations Management)
12th Edition
ISBN: 9780134741062
Author: Lee J. Krajewski, Manoj K. Malhotra, Larry P. Ritzman
Publisher: PEARSON
expand_more
expand_more
format_list_bulleted
Concept explainers
Textbook Question
Chapter 7, Problem 2P
The following information is known about a project to upgrade a point-of-sale system at Kids and Tots Apparel.
- Draw the network diagram for this project.
- Determine the critical path and project duration.
- Calculate the slack for each activity.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
The following is the data available for a project:
Activity
Predecessor
Expected Duration (Days)
A
-
12
B
A
9
C
B,E
3
D
-
10
E
D
6
F
E
3
G
-
2
H
G
9
I
E,H
2
Expected duration for the completion of the project. Calculate earliest and latest start and finish times for each activity.
Draw the network diagram for the project and determine the critical path
The table below show a set of activities of an IS project,its expected completion time (ET) and preceding activities.
Activity
Preceding
Activity
Expected
Time (ET)
A
-
7
B
A
9
C
A,B
5
D
C
17
E
C
12
F
C
7
G
D,E,F
10
H
D,G
7
Draw a network diagram for the IS project shown above.,and calculate its earliest completion time (TE), latest completion time (TL) and slack time (ST).
If the activity E took 16weeks instead of 12weeks to complete ,what impact will it have on the project duration?
The Industrial and Systems Engineering Department at Sun University is moving from its old building to a new building. The move must be completed within the 14-day period between semesters. A list of tasks (activities) has been prepared. The activities and precedence requirements are presented in the table below. Three time estimates (in days) are given for each activity: optimistic time, most likely time, and pessimistic time. (a) Perform a forward pass and backward pass through the network to determine the critical path, and the expected duration of the project (b) What completion time should the department specify in its proposal in order to be 85% sure that it will complete the project on time?
Activity
Activity description
Immediate predecessor
Optimistic time (days)
Most likely time (days)
Pessimistic time (days)
1
Initiate move
-
0
0
0
2
Prepare new building space
1
2
4
6
3
Pack faculty files and books
1
3
4
5
4…
Chapter 7 Solutions
Operations Management: Processes and Supply Chains (12th Edition) (What's New in Operations Management)
Ch. 7 - One of your colleagues comments that software is...Ch. 7 - Explain how to determine the slack for each...Ch. 7 - Define risk as it applies to projects. What are...Ch. 7 - Consider the following data for a project to...Ch. 7 - The following information is known about a project...Ch. 7 - A project for improving a billing process has the...Ch. 7 - Prob. 4PCh. 7 - Prob. 5PCh. 7 - Consider the following information for a project...Ch. 7 - Consider the following data for a project to...
Ch. 7 - Paul Silver, owner of Sculptures International,...Ch. 7 - Prob. 9PCh. 7 - The following information concerns a project to...Ch. 7 - Consider a project to produce custom door moldings...Ch. 7 - Table 7.5 contains information about au...Ch. 7 - The Advanced Tech Company has a project to design...Ch. 7 - Prob. 14PCh. 7 - Table 7.8 contains data for the installation of...Ch. 7 - The diagram in Figure 7.12 was developed for the...Ch. 7 - Prob. 17PCh. 7 - Prob. 18PCh. 7 - You are the project manager of the software...Ch. 7 - Jordanne King, the project manager for Webjets...Ch. 7 - Recently, you were assigned to manage a project to...Ch. 7 - In Solved Problem 2, estimate the probability that...Ch. 7 - The director of continuing education at Bluebird...Ch. 7 - Gabrielle Kramer, owner of Pet Paradise, is...Ch. 7 - The project manager of Good Public Relations...Ch. 7 - Consider the office renovation project data in...Ch. 7 - Activity B and activity K are critical activities....Ch. 7 - Prob. 2AMECh. 7 - Prob. 3AMECh. 7 - Prob. 4AMECh. 7 - Prob. 5AMECh. 7 - Assess the four categories of a risk-management...Ch. 7 - Prob. 2VCCh. 7 - Assume you are Denise Tower and have...Ch. 7 - Prob. 1CCh. 7 - Prob. 2CCh. 7 - Prob. 3CCh. 7 - Prob. 4C
Additional Business Textbook Solutions
Find more solutions based on key concepts
Real options and its types. Introduction: The net present value is the variation between present cash inflows v...
Gitman: Principl Manageri Finance_15 (15th Edition) (What's New in Finance)
Fundamental and Enhancing Characteristics. Identify whether the following items are fundamental characteristics...
Intermediate Accounting (2nd Edition)
1-1. Define marketing and outline the steps in the marketing process. (AASCB: Communication)
Marketing: An Introduction (13th Edition)
E6-14 Using accounting vocabulary
Learning Objective 1, 2
Match the accounting terms with the corresponding d...
Horngren's Accounting (12th Edition)
10-10 What challenges do managers face in managing global teams? How should those challenges be handled?
Fundamentals of Management (10th Edition)
How is activity-based costing useful for pricing decisions?
Horngren's Cost Accounting: A Managerial Emphasis (16th Edition)
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- Construct a Gantt chart and project network for the following set of activities, compute the length of each path in the network, and indicate the critical path:arrow_forwardThe table below show a set of activities of an IS project,its expected completion time (ET) and preceding activities. Activity Preceding Activity Expected Time (ET) A - 7 B A 9 C A,B 5 D C 17 E C 12 F C 7 G D,E,F 10 H D,G 7 Construct a network diagram ,and calculate its earliest completion time (TE), latest completion time (TL) and slack time (ST). If the activity E took 16weeks instead of 12weeks to complete ,what impact will it have on the project duration?arrow_forwardA project network is shown below, with three time estimates (Optimistic Time-Most Likely Time-Pessimistic Time (in days)) for each activity in the network. a. Compute the expected time for each activity in the project network. b. Identify and list all possible paths in the project network. Compute the expected duration for each path in the project network. c. Identify the critical path(s) in the project network. What is the expected project completion time? d. Compute the variance of each activity on the critical path(s). e. Determine the project variance and project standard deviation. Use the PERT analysis results in 2(c) and 2(e) to answer questions (f), (g), (h), and (i) below:f. What is the probability that the project can be completed within 22 days of its start? g. What is the probability that the project can be completed within 16 days of its start? h. Determine the project deadline that gives this project a 78% chance of on-time completion. i. Determine the project deadline…arrow_forward
- The Farmer's American Bank of Leesburg is planning to install a new computerized accounts system. Bank management has determined the activities required to complete the project, the precedence relationships of the activities, and activity time estimates, as shown in the following table. Use POM- QM to analyze this project. According to the result of POM-QM, the expected project completion time is (type number only, no text) Activity a b C d C f 8 k Activity Description Position recruiting System development System training Equipment training Manual system test Preliminary system changeover Computer-personnel interface Equipment modification Equipment testing System debugging and installation Equipment changeover Activity Predecessor a a b, c b, c d, e d, e h f.g a 5 3 4 5 I 1 3 Time Estimates (weeks) 1 1 2 5 m 8 12 7 8 I 4 6 2.5 1. 2 8 b 17 15 10 23 1 13 9 7 1 2 11arrow_forwardMake a list of the tasks that is necessary for Management Trainee Officer job in private banks. Develop a table showing each task, its duration, and preceding event(s). Develop a Network diagram for these tasks. Highlight the critical path on your Network diagram and find out slack of all activities.arrow_forwardThe table below represents a IS project set of activities, its expected completion time (weeks) and preceding activities. Activity Expected Time (weeks) Preceding activities A 5 None B 4 None C 10 A D 8 B E 14 B F 6 C, D G 7 D, E, F H 3 F, G Draw a network diagram for the IS project shown above. For each activity, calculate its earliest completion time (TE) and latest completion time (TL). Label TE and TL on the network diagram. Calculate the slack time for each activity.arrow_forward
- Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before a training program of this nature could be conducted. The activities, immediate predecessors,and times appear in the accompanying table: a) Develop an AON network for this problem.b) What is the critical path?c) What is the total project completion time?d) What is the slack time for each individual activity?arrow_forwardA political campaign manager must coordinate several activities to be prepared for an upcoming election. The following table describes the relationships among the activities that need to be completed, as well as the estimated times. Activity Immediate Predecessors Time (Weeks) A - 4 B - 6 C A 3 D A 4 E B, C 8 F B 7 G D,E 2 H F 1 Develop a project network for this problem. Determine the ES, EF, LS, LF, and slack time for each activity. Also determine the total project completion time and the critical path(s).arrow_forward. Given the following network with activity times in weeks, determine the earliest start and finish times, latest start and finish times, and slack for each activity. Indicate the critical path and the project duration. photo attached- Calculate and insert ALL missing Earliest Start or Earliest Finish at each Activity. Calculate and insert ALL missing Latest Start and Latest Finish at each Activity. Calculate missing Slack at Every Activity on the network Diagram. List of all possible paths & Total Slacks from Start to finish for each path. *Which activities are on the critical path? What is the total slack along the critical path.arrow_forward
- The following CPM network has estimates of the normal time in weeks listed for the activities: A(7) B(4) Node A B C D E F G C(2) D(5) F(2) Early Early Start Finish E(4) 1. Identify the critical path and show your answer. Please compute the early start, early finish, late start, late finish time for each node (activities) and Write your answer in the following table. (You may type your answer in a table in MS Word and then paste in the answer box below. Late Start Late Finish G (6) 2. What is the length of time to complete the project? 3. Which activities have slack, and how much?arrow_forwardA group of developers is building a new shopping center. A consultant for the developers has constructed the following project network and assigned activity times, in weeks. Determine the earliest and latest activity times, activity slack, critical path, and duration for the project.arrow_forwardDraw the Network Diagram, determine the critical path and draw Gantt chart for project scheduling for the following two problems Problem1. Activity Predeccsor Duration(hours) Lag Time(hours) A - 2 0 B A 4 5 C B 3 3 D B 5 0 E D, C 2 0 Problem 2. Activity Predeccsor Duration(months) A - 2 B A 1 C A 3 D B, C 1 E D 2 F D…arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY