Operations Management: Processes And Supply Chains (12th Edition) (what's New In Operations Management)
12th Edition
ISBN: 9780134742205
Author: Lee J. Krajewski, Manoj K. Malhotra, Larry P. Ritzman
Publisher: PEARSON
expand_more
expand_more
format_list_bulleted
Concept explainers
Textbook Question
Chapter 7, Problem 3P
A project for improving a billing process has the following precedence relationships and activity times.
- Draw the network diagram.
- Calculate the slack for each activity. Which activities are on the critical path?
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
The table below show a set of activities of an IS project,its expected completion time (ET) and preceding activities.
Activity
Preceding
Activity
Expected
Time (ET)
A
-
7
B
A
9
C
A,B
5
D
C
17
E
C
12
F
C
7
G
D,E,F
10
H
D,G
7
Draw a network diagram for the IS project shown above.,and calculate its earliest completion time (TE), latest completion time (TL) and slack time (ST).
If the activity E took 16weeks instead of 12weeks to complete ,what impact will it have on the project duration?
how to draw the path and how to compute the critical path and slack time? Please provide step by step solution.
The following is the data available for a project:
Activity
Predecessor
Expected Duration (Days)
A
-
12
B
A
9
C
B,E
3
D
-
10
E
D
6
F
E
3
G
-
2
H
G
9
I
E,H
2
Expected duration for the completion of the project. Calculate earliest and latest start and finish times for each activity.
Draw the network diagram for the project and determine the critical path
Chapter 7 Solutions
Operations Management: Processes And Supply Chains (12th Edition) (what's New In Operations Management)
Ch. 7 - One of your colleagues comments that software is...Ch. 7 - Explain how to determine the slack for each...Ch. 7 - Define risk as it applies to projects. What are...Ch. 7 - Consider the following data for a project to...Ch. 7 - The following information is known about a project...Ch. 7 - A project for improving a billing process has the...Ch. 7 - Prob. 4PCh. 7 - Prob. 5PCh. 7 - Consider the following information for a project...Ch. 7 - Consider the following data for a project to...
Ch. 7 - Paul Silver, owner of Sculptures International,...Ch. 7 - Prob. 9PCh. 7 - The following information concerns a project to...Ch. 7 - Consider a project to produce custom door moldings...Ch. 7 - Table 7.5 contains information about au...Ch. 7 - The Advanced Tech Company has a project to design...Ch. 7 - Prob. 14PCh. 7 - Table 7.8 contains data for the installation of...Ch. 7 - The diagram in Figure 7.12 was developed for the...Ch. 7 - Prob. 17PCh. 7 - Prob. 18PCh. 7 - You are the project manager of the software...Ch. 7 - Jordanne King, the project manager for Webjets...Ch. 7 - Recently, you were assigned to manage a project to...Ch. 7 - In Solved Problem 2, estimate the probability that...Ch. 7 - The director of continuing education at Bluebird...Ch. 7 - Gabrielle Kramer, owner of Pet Paradise, is...Ch. 7 - The project manager of Good Public Relations...Ch. 7 - Consider the office renovation project data in...Ch. 7 - Activity B and activity K are critical activities....Ch. 7 - Prob. 2AMECh. 7 - Prob. 3AMECh. 7 - Prob. 4AMECh. 7 - Prob. 5AMECh. 7 - Assess the four categories of a risk-management...Ch. 7 - Prob. 2VCCh. 7 - Assume you are Denise Tower and have...Ch. 7 - Prob. 1CCh. 7 - Prob. 2CCh. 7 - Prob. 3CCh. 7 - Prob. 4C
Additional Business Textbook Solutions
Find more solutions based on key concepts
The flowchart for the process at the local car wash. Introduction: Flowchart: A flowchart is a visualrepresenta...
Principles Of Operations Management
2. In what circumstances might a market-pull approach or a technology-push approach to new-product design be th...
OPERATIONS MANAGEMENT IN THE SUPPLY CHAIN: DECISIONS & CASES (Mcgraw-hill Series Operations and Decision Sciences)
There is a huge demand in the United States and elsewhere for affordable women’s clothing. Low-cost clothing re...
Operations Management
There is a huge demand in the United States and elsewhere for affordable women’s clothing. Low-cost clothing re...
Loose-leaf for Operations Management (The Mcgraw-hill Series in Operations and Decision Sciences)
2. Identify four people who have contributed to the theory and techniques of operations management.
Operations Management
What is precedent, and how does it affect common law?
Business in Action
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- REQUIRED: Prepare the PERT Network for the US Tea project What is the critical path and its expected time in weeks? What is the shortest path and its slack time in weeks?arrow_forwardThe following CPM/PERT network represents a small project with 4 activities labelled A through D. The activity times (in days) are provided in the table. Activity Time 21 8. 12 There's a diagram in the associated PDF file that you can print out and use to answer the following questions. The available slack (S) for Activity C is 57.33 A, B.arrow_forwardProject Management Homework-Project Crashing Use the following scenario and data to answer all related questions. A community neighborhood association decided to add a swimming pool to the community activity center. The project is divided into the activities listed in the following table. The activity times and costs, both normal and crashed, are given. To finish the project before the summer season starts, the neighborhood has to make time and cost tradeoffs. If the project needs to be finished in 20 weeks, you are required to formulate a linear programming model to decide about how much to crash for each activity. Activity Immediate Predecesso Normal Gs) Cost (5) Cost (5) Crashed Normal Crashed A 4 2 800 1400 B A 5 2 3000 4200 C 6 4 2500 2800 D A, C 7 5 1600 2200 E B, C 5 2 1200 2100 F D 4 3 1300 2100 G E, F 5 3 8200 9000 To answer the following questions, you may want to use the last column of the following table to compute the cost of crashing an activity by one week. Immediate…arrow_forward
- A project consists of eight activities. The activity completion times and the precedence relationships are as follows: Activity Completion Immediate predecessor activities time (weeks) A 50 70 C 60 D 30 A E 40 B,C F 20 G 60 A.D E,F H 50 I G,H Draw the project network diagram using the Activity-On-Node (AON) method for this project and calculate the Early Start (ES), Early Finish (EF), Late Start (LS), Late Finish (LF) and Slack (SL) for each activity.arrow_forwardThe project information of the project Automated Warehouse Order Picking System is presented as following. Draw a project network for this project. Compute the early and late activity times and the slack times. Identify the critical path. How many days will the project take? ID A B C D E F G H 80 130 85 95 Activity Define requirements Assign team Design hardware Code software Build & test hardware Develop patent request Test software Integrate systems Predecessor None A A B C C D E (F-S, lag 20d),F,G Time (days) 5 сл сл 5 20 20 10⁰ 15 15 40arrow_forwardThe director of continuing education at Bluebird University just approved the planning for a sales training seminar. Her administrative assistant identified the various activities that must be done and their relationships to each other, as shown in the following table: Click the icon to view the activities. Because of the uncertainty in planning the new course, the assistant also has supplied the following time estimates for each activity: Click the icon to view the time estimates. The director wants i conduct the seminar 45 working days from now. What is the probability that everything will be ready in time? Refer to the standard normal tathe. (Make sure to round all intermediate calculations for and variance to two decimal places) The probability that the seminar will be ready in time is (Enter your response rounded to four decimal places)arrow_forward
- The project information of the project Automated Warehouse Order Picking System is presented as following. Draw a project network for this project. Compute the early and late activity times and the slack times. Identify the critical path. How many days will the project take? ID ABC D E F G H 120 90 70 80 Activity Define requirements Assign team Design hardware Code software Build & test hardware Develop patent request Test software Integrate systems Predecessor None A A B C C D E,F,G Time (days) 5 5 15 15 15 20 15 30arrow_forwardMake a list of the tasks that is necessary for Management Trainee Officer job in private banks. Develop a table showing each task, its duration, and preceding event(s). Develop a Network diagram for these tasks. Highlight the critical path on your Network diagram and find out slack of all activities.arrow_forwardDave Fletcher was able to determine the activity times for constructing his laser scanning machine. Fletcher would like to determine ES, EF, LS, LF, and slack for each activity. The total project completion time and the critical path should also be determined. Here are the activity times: O Activity Time (weeks) Immediate Predecessor(s) Activity Time (weeks) Immediate Predecessor(s) E F A B C D Dave's earliest start (ES) and earliest finish (EF) are: 5 8 00 2 2 Activity HOT G ES Н EF 5 5 5 10 7 B B C, E D.Farrow_forward
- Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before a training program of this nature could be conducted. The activities, immediate predecessors, and times appear in the accompanying table: a. the critical activities for the leadership training program development project are: _____ b. the project length for the leadership training program development project= __ days. c. Slack time for each of the activities is: Activity: Slack time: A ______ B ______ C ______ D ______ E ______ F ______ G ______arrow_forwardBelow is a network diagram that represents a university revamp project. The project manager analyzes this project using the critical path (CP) method. Activity durations are indicated on the networkarrow_forwardGiven the network plan that follows, compute the early, late, and slack times. What is the project duration? Using any approach you wish (e.g., trial and error), develop a loading chart for resources, Electrical Engineers (EE), and resource, Mechanical Engineers (ME). Assume only one of each resource exists. Given your resource schedule, compute the early, late, and slack times for your project. Which activities are now CRITICAL? What is the project duration now?arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY