Table 7.5 contains information about au environmental cleanup project in the township of Hiles. Shorten the project 3 weeks by finding the minimum—cost
Want to see the full answer?
Check out a sample textbook solutionChapter 7 Solutions
Operations Management: Processes And Supply Chains (12th Edition) (what's New In Operations Management)
Additional Business Textbook Solutions
Principles of Operations Management: Sustainability and Supply Chain Management (10th Edition)
Loose-leaf for Operations Management (The Mcgraw-hill Series in Operations and Decision Sciences)
OPERATIONS MANAGEMENT IN THE SUPPLY CHAIN: DECISIONS & CASES (Mcgraw-hill Series Operations and Decision Sciences)
Business in Action (8th Edition)
Operations and Supply Chain Management 9th edition
- The table below contains information about an environmental clean-up project in the township of Hiles. Shorten the project three weeks by finding the minimum-cost schedule. Assume that project indirect costs and penalty costs are negligible. Identify activities to crash while minimizing the additional crash costs. Normal Time Crash Time Cost to Crash Immediate Activity (weeks) (weeks) ($ per week) Predecessor(s) А 5 4 200 None В 9 8. 300 None C 4 200 А 4 2 250 A 3 3 В F 3 С, D G 3 1 150 D, E 7 350 F 4 4 G Fill in the table below with the activity times after crashing to show the resulting schedule. (Enter your responses as whole numbers.) Time according to schedule (weeks) Time according to schedule (weeks) Activity Activity A В G C H Earrow_forwardConnect HW Q1arrow_forwardThe following table shows the various activities of the development of a new product in your organization. Activity Event Immediate Predecessor(s) Estimates of Activity Duration (Weeks) Optimistic (To) Most Likely (Tm) Pessimistic (Tp) Average (Te) 1 A - 2 3 4 ? 3 2 B A 1 2 3 2 3 C A 1 2.05 4 2.2 4 D B 4 5 6 5 5 E B 3 4 5 4 6 F C 2 3 4 3 7 G D 1.2 2 4 2.2 8 H E,F, G 3 4 6 4.167 9 I H 3 4 5 4 10 J I 2 1 3 1.5 Questions: Draw the PERT network from the given data. (arrow_forward
- 3.8 Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a num- ber of activities that must be completed before a training program of this nature could be conducted. The activities, immediate pre- decessors, and times appear in the accompanying table: a) DrawtheappropriateAONPERTdiagramforJ.C.Howard’s management team. b) Find the critical path. c) What is the project completion time? • • 3.11 The following is a table of activities associated with a project at Rafay Ishfaq’s software firm in Chicago, their dura- tions, and what activities each must precede: ACTIVITY DURATION (WEEKS) PRECEDES A (start) 1 B, C B 1 E C 4 F E 2 F F (end) 2 — ACTIVITY IMMEDIATE PREDECESSOR(S) TIME (DAYS) A — 2 B — 5 C — 1 D B…arrow_forwardIn project management why is float important?arrow_forwardWhat is the minimum cost of crashing the following project at Sawaya Robotics by 4 days? NORMAL CRASH TIME (DAYS) TIME (DAYS) 9 7 7 6 5 4 6 4 9 6 ACTIVITY Design (A) Wiring (B) Chip install (C) Software (D) Testing (E) The minimum cost of crashing the following project at Sawaya Robotics by. 4 days is $ NORMAL COST 200 800 600 1,100 1,200 CRASH COST 300 875 675 1,300 1,875 IMMEDIATE PREDECESSOR(S) (enter your response as a whole number). A, B Carrow_forward
- The table below contains information about an environmental clean-up project in the township of Hiles. Shorten the project three weeks by finding the minimum-cost schedule. Assume that project indirect costs and penalty costs are negligible. Identify activities to crash while minimizing the additional crash costs. . Normal Time Crash Time Cost to Crash Immediate Activity (weeks) (weeks) Predecessor(s) (S per week) 300 A 4 None None B 4 50 C 6. 300 250 A E 1 B. C.D D, E 4 200 H. 4 2 200 2. Fill in the table below with the activity times after crashing to show the resulting schedule. (Enter your responses as whole numbers.) 777arrow_forwardQ3.When we start a project how we know this project or program is feasible for our future? Explain with help of diagramarrow_forwardEarned Value Analysis of the project supported by cost Performance Index and Schedule Performance Index readings. Comment on the progress of each activity and overall health of the project. Activity BCWS ACWP 1- Percentage Completion 80% Rs. 30,000 Rs. 25,000 2- Percentage Completion 40% Rs. 60,000 Rs. 80,000 3- Percentage Completion 100% Rs. 80,000 Rs. 78,000 Cumulative Rs. 170,000 Rs. 183,000arrow_forward
- What is the answer and solution?arrow_forwarda. Introduction PPE GLOVEb. Objective of Project/Manufacturing Processc. History of Company/Product (PPE GLOVE)arrow_forwardRoger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a num- ber of activities that must be completed before a training program of this nature could be conducted. The activities, immediate pre-decessors, and times appear in the accompanying table: A—2 B—5 C—1 D B 10 E A, D 3 FC6 G E, F 8 A) Develop an AON network for this problem.b) What is the critical path?c) What is the total project completion time? Please answer A B C and show workarrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.