Question
Chapter 7, Problem 4P
A.
Summary Introduction
Interpretation:The network diagram is to be drawn.
Concept Introduction: Network diagram is a graphical representation of tasks in symbols and lines for easy understanding. The networking technique is a method for planning, programming and controlling of work in progress. It is helpful for effective management. It helps the management for decisions.
B.
Summary Introduction
Interpretation:The critical path is to be detected.
Concept Introduction: Critical path is a method used to evaluate the project. It is used when the activity times are deterministic. It is the longest path in the network. It defines the minimum time required for completion of the project.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Draw the Network Diagram, determine the critical path and draw Gantt chart for project scheduling for the following two problems
Problem1.
Activity Predeccsor Duration(hours) Lag Time(hours)
A - 2 0
B A 4 5
C B 3 3
D B 5 0
E D, C 2 0
Problem 2.
Activity Predeccsor Duration(months)
A - 2
B A 1
C A 3
D B, C 1
E D 2
F D…
The Mobicom Corporation is in the design phase of a system project. The project manager wants to develop a network analysis diagram to plan the activities of designing the system outputs. The activities are as follows.
ACTIVITY
PRECEDING
TIME[WEEKS]
A
-----
5
B
----
6
C
----
4
D
A,B
7
E
C
8
F
C,D
10
G
D
8
Required
Draw a network diagram for the design phase
Make a list of the tasks that is necessary to build a duplex house (around 3000 sft) for you. Develop a table showing each task, its duration, preceding event(s), and expected duration. Develop a Network diagram for these tasks. Highlight the critical path on your Network diagram and find out slack of all activities.
Chapter 7 Solutions
Operations Management: Processes And Supply Chains (12th Edition) (what's New In Operations Management)
Ch. 7 - One of your colleagues comments that software is...Ch. 7 - Explain how to determine the slack for each...Ch. 7 - Define risk as it applies to projects. What are...Ch. 7 - Consider the following data for a project to...Ch. 7 - The following information is known about a project...Ch. 7 - A project for improving a billing process has the...Ch. 7 - Prob. 4PCh. 7 - Prob. 5PCh. 7 - Consider the following information for a project...Ch. 7 - Consider the following data for a project to...
Ch. 7 - Paul Silver, owner of Sculptures International,...Ch. 7 - Prob. 9PCh. 7 - The following information concerns a project to...Ch. 7 - Consider a project to produce custom door moldings...Ch. 7 - Table 7.5 contains information about au...Ch. 7 - The Advanced Tech Company has a project to design...Ch. 7 - Prob. 14PCh. 7 - Table 7.8 contains data for the installation of...Ch. 7 - The diagram in Figure 7.12 was developed for the...Ch. 7 - Prob. 17PCh. 7 - Prob. 18PCh. 7 - You are the project manager of the software...Ch. 7 - Jordanne King, the project manager for Webjets...Ch. 7 - Recently, you were assigned to manage a project to...Ch. 7 - In Solved Problem 2, estimate the probability that...Ch. 7 - The director of continuing education at Bluebird...Ch. 7 - Gabrielle Kramer, owner of Pet Paradise, is...Ch. 7 - The project manager of Good Public Relations...Ch. 7 - Consider the office renovation project data in...Ch. 7 - Activity B and activity K are critical activities....Ch. 7 - Prob. 2AMECh. 7 - Prob. 3AMECh. 7 - Prob. 4AMECh. 7 - Prob. 5AMECh. 7 - Assess the four categories of a risk-management...Ch. 7 - Prob. 2VCCh. 7 - Assume you are Denise Tower and have...Ch. 7 - Prob. 1CCh. 7 - Prob. 2CCh. 7 - Prob. 3CCh. 7 - Prob. 4C
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- A farm owner is going to erect a maintenance building with a connecting electrical generator and water tank. The activities, activity descriptions, and estimated durations are given in the following table: Activity Activity Description Excavate Erect building Install generator Install tank Install maintenance equipment Connect generator and tank to building Paint finish Check out facility Activity Predecessor b, c, d b e, f a. Draw a complete network for the above problem. b. Determine the critical path and the expected completion time. c. Show a table of detailed activity schedule. Activity Duration (weeks) 2 6 4 3 2arrow_forwardPlease explain how to solve this chart in terms of engineering project managment How can I draw the network diagrams?How can I list the network paths?How can I determine the critical paths? How can I determine the float for each activity?arrow_forwardThe following is the data available for a project: Activity Predecessor Expected Duration (Days) A - 12 B A 9 C B,E 3 D - 10 E D 6 F E 3 G - 2 H G 9 I E,H 2 Expected duration for the completion of the project. Calculate earliest and latest start and finish times for each activity. Draw the network diagram for the project and determine the critical patharrow_forward
- The following CPM network has estimates of the normal time in weeks listed for the activities: A(7) B(4) Node A B C D E F G C(2) D(5) F(2) Early Early Start Finish E(4) 1. Identify the critical path and show your answer. Please compute the early start, early finish, late start, late finish time for each node (activities) and Write your answer in the following table. (You may type your answer in a table in MS Word and then paste in the answer box below. Late Start Late Finish G (6) 2. What is the length of time to complete the project? 3. Which activities have slack, and how much?arrow_forwardThe director of continuing education at Bluebird University just approved the planning for a sales training seminar. Her administra assistant identified the various activities that must be done and their relationships to each other, as shown in the following table: Click the icon to view the activities. Because of the uncertainty in planning the new course, the assistant also has supplied the following time estimates for each acti Click the icon to view the time estimates. The director wants to conduct the seminar 46 working days from now. What is the probability that everything will be ready in time the standard normal table. (Make sure to round all intermediate calculations for t, and variance to two decimal places) The probability that the seminar will be ready in time is 0.8643]. (Enter your response rounded to four decimal places.)arrow_forwardMake a list of the tasks that is necessary for Management Trainee Officer job in private banks. Develop a table showing each task, its duration, and preceding event(s). Develop a Network diagram for these tasks. Highlight the critical path on your Network diagram and find out slack of all activities.arrow_forward
- The Student Affairs Department at UCC has developed a sequence of activities for the University’s Sports Day. The Director has published the activities as shown in the table. All students are expected to participate and all activities are expected to be completed. The activities and immediate predecessors appear in the following table. Develop a network for this problem. ACTIVITY IMMEDIATE PREDECESSOR A -- B -- C -- D B E A, D F C G E, F Copy the following table in your answer booklet. Determine the values for the gray spaces hence complete the copied table. Activity Completion Times Early Start Early Finish Late Start Late Finish Slack On Critical Path A 2 B 5 C 1 D 3 E 2 F 6 G 8 CRITICAL…arrow_forwardb) – Draw the Activity-on-Node (AON) diagram using the following representation for every node: Activity Description Expected Time ES EF LS LF Slack C.) Complete the following table, determine the expected time of completion assuming that the project starts at week 0 (zero) and identify the critical path for this project. Demonstrate all your calculations. On Critical Path? Activity Activity Description ES EF LS LF Slack Yes or No Locate new facilities 2 Order furniture Interview prospective staff Hire and train staff 3 4. Remodel facilities Receive and set up furniture Move in and start up 6 7 a) Complete the following table, calculate the project variance and project standard deviation. Demonstrate all your calculations.arrow_forwardProblem 1 Solve the scheduling data for the following project and compute the relevant information; include the information on your network; (Draw the network and implement the Critical Path Method (CPM); Precedence diagramming to determine the critical path (CP) and all of the relevant information for the project). Feel free to use any of these two node designs (Use ES for the first activity = 0) Highlight the overall duration of the project with the critical path ES Activities EF Activity ES Duration LS Cr. Duration TF EF FF TE LF LS FF LF Activities' label Duration Predecessors A 3 A FF B FF/2 В 2 C 3 D C E 2 B/1 F 3 Е, D Continue into the next page for problem 2 →arrow_forward
- In the cpm network diagram given below: a-Find the critical path and show it on the diagram. b-(2-3) Determine the floats of its activity.arrow_forwardThe following represent activities in a major construction project. Draw the network to represent this project. Activity Immediate Predecessor A - B - C A D B E B F C, E G D H F, Garrow_forwardThe table below show a set of activities of an IS project,its expected completion time (ET) and preceding activities. Activity Preceding Activity Expected Time (ET) A - 7 B A 9 C A,B 5 D C 17 E C 12 F C 7 G D,E,F 10 H D,G 7 Draw a network diagram for the IS project shown above.,and calculate its earliest completion time (TE), latest completion time (TL) and slack time (ST). If the activity E took 16weeks instead of 12weeks to complete ,what impact will it have on the project duration?arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY