Operations Management
Operations Management
13th Edition
ISBN: 9781259667473
Author: William J Stevenson
Publisher: McGraw-Hill Education
bartleby

Concept explainers

bartleby

Videos

Textbook Question
Book Icon
Chapter 6, Problem 6P

Twelve tasks, with times and precedence requirements as shown in the following table, are 10 be assigned to workstations using a cycle time of 1.5 minutes. Two heuristic rules will be tried: (1) greatest positional weight, and (2) most following tasks. In each case, the tiebreaker will be shortest processing time.

Chapter 6, Problem 6P, Twelve tasks, with times and precedence requirements as shown in the following table, are 10 be

a. Draw the precedence diagram for this line.

b. Assign tasks to stations under each of the two rules.

c. Compute the percentage of idle tune fox each rule.

a)

Expert Solution
Check Mark
Summary Introduction

To draw: The precedence diagram.

Answer to Problem 6P

Precedence diagram:

Operations Management, Chapter 6, Problem 6P , additional homework tip  1

Explanation of Solution

Given information:

Task Duration (minutes) Immediate (Predecessor)
a 0.1 Nil
b 0.2 a
c 0.9 b
d 0.6 c
e 0.1 Nil
f 0.2 d, e
g 0.4 f
h 0.1 g
i 0.2 h
j 0.7 i
k 0.3 j
l 0.2 k

Cycle time = 1.5 minutes

Precedence diagram:

Operations Management, Chapter 6, Problem 6P , additional homework tip  2

The precedence diagram is drawn circles and arrows. The tasks are represented in circles and weights for each task are represented outside the circle. The arrows are represented to show which task is preceding the other task and so on.

b)

1)

Expert Solution
Check Mark
Summary Introduction

To assign: Tasks on the basis of greatest positional weight.

Explanation of Solution

Given information:

Task Duration (minutes) Immediate (Predecessor)
a 0.1 Nil
b 0.2 a
c 0.9 b
d 0.6 c
e 0.1 Nil
f 0.2 d, e
g 0.4 f
h 0.1 g
i 0.2 h
j 0.7 i
k 0.3 j
l 0.2 k

Cycle time = 1.5 minutes

The number of following tasks, calculation of positional weight, processing time for each task is shown below.

Task Following tasks Number of following tasks Calculation of positional weight Positional weight Processing time
a b, c, d, f, g, h, i, j, k, l 10 0.1 + 0.2 + 0.9 + 0.6 + 0.2 + 0.4 + 0.1 + 0.2 + 0.7+ 0.3 + 0.2 3.9 0.1
b c, d, f, g, h, i, j, k, l 9 0.2 + 0.9 + 0.6 + 0.2 + 0.4 + 0.1 + 0.2 + 0.7+ 0.3 + 0.2 3.8 0.2
c d, f, g, h, i, j, k, l 8 0.9 + 0.6 + 0.2 + 0.4 + 0.1 + 0.2 + 0.7+ 0.3 + 0.2 3.6 0.9
d f, g, h, i, j, k, l 7 0.6 + 0.2 + 0.4 + 0.1 + 0.2 + 0.7+ 0.3 + 0.2 2.7 0.6
e f, g, h, i, j, k, l 7 0.1 + 0.2 + 0.4 + 0.1 + 0.2 + 0.7+ 0.3 + 0.2 2.2 0.1
f g, h, i, j, k, l 6 0.2 + 0.4 + 0.1 + 0.2 + 0.7+ 0.3 + 0.2 2.1 0.2
g h, i, j, k, l 5 0.4 + 0.1 + 0.2 + 0.7+ 0.3 + 0.2 1.9 0.4
h i, j, k, l 4 0.1 + 0.2 + 0.7+ 0.3 + 0.2 1.5 0.1
i j, k, l 3 0.2 + 0.7+ 0.3 + 0.2 1.4 0.2
j k, l 2 0.7+ 0.3 + 0.2 1.2 0.7
k l 1 0.3 + 0.2 0.5 0.3
l Nil 0 0.2 0.2 0.2

Assigning tasks to workstations:

Workstation number Eligible task Assigned task Task time Unassigned cycle time Reason
1.5
1 a, e a 0.1 1.4 Task 'a' has highest positional weight
b, e b 0.2 1.2 Task 'b' has highest positional weight
c, e c 0.9 0.3 Task 'c' has highest positional weight
d, e e 0.1 0.2 Task 'e' is the only eligible task available
d None 0.2 (Idle time) The task time is greater than the unassigned cycle time.
1.5
2 d d 0.6 0.9 Task 'd' is the only eligible task available
f f 0.2 0.7 Task 'f' is the only eligible task available
g g 0.4 0.3 Task 'g' is the only eligible task available
h h 0.1 0.2 Task 'h' is the only eligible task available
i i 0.2 0 Task 'i' is the only eligible task available
1.5
3 j j 0.7 0.8 Task 'j' is the only eligible task available
k k 0.3 0.5 Task 'k' is the only eligible task available
l l 0.2 0.3 Task 'l' is the only eligible task available
0.3 (Idle time) All tasks completed

Overview of tasks assignment:

Workstation Assigned tasks Total cycle time used Idle time
1 a, b, c, e 1.3 0.2
2 d, f, g, h, i 1.5 0
3 j, k, l 1.2 0.3

2)

Expert Solution
Check Mark
Summary Introduction

To assign: Tasks on the basis of most following tasks.

Explanation of Solution

Given information:

Task Duration (minutes) Immediate (Predecessor)
a 0.1 Nil
b 0.2 a
c 0.9 b
d 0.6 c
e 0.1 Nil
f 0.2 d, e
g 0.4 f
h 0.1 g
i 0.2 h
j 0.7 i
k 0.3 j
l 0.2 k

Cycle time = 1.5 minutes

The number of following tasks, calculation of positional weight, processing time for each task is shown below.

Task Following tasks Number of following tasks Calculation of positional weight Positional weight Processing time
a b, c, d, f, g, h, i, j, k, l 10 0.1 + 0.2 + 0.9 + 0.6 + 0.2 + 0.4 + 0.1 + 0.2 + 0.7+ 0.3 + 0.2 3.9 0.1
b c, d, f, g, h, i, j, k, l 9 0.2 + 0.9 + 0.6 + 0.2 + 0.4 + 0.1 + 0.2 + 0.7+ 0.3 + 0.2 3.8 0.2
c d, f, g, h, i, j, k, l 8 0.9 + 0.6 + 0.2 + 0.4 + 0.1 + 0.2 + 0.7+ 0.3 + 0.2 3.6 0.9
d f, g, h, i, j, k, l 7 0.6 + 0.2 + 0.4 + 0.1 + 0.2 + 0.7+ 0.3 + 0.2 2.7 0.6
e f, g, h, i, j, k, l 7 0.1 + 0.2 + 0.4 + 0.1 + 0.2 + 0.7+ 0.3 + 0.2 2.2 0.1
f g, h, i, j, k, l 6 0.2 + 0.4 + 0.1 + 0.2 + 0.7+ 0.3 + 0.2 2.1 0.2
g h, i, j, k, l 5 0.4 + 0.1 + 0.2 + 0.7+ 0.3 + 0.2 1.9 0.4
h i, j, k, l 4 0.1 + 0.2 + 0.7+ 0.3 + 0.2 1.5 0.1
i j, k, l 3 0.2 + 0.7+ 0.3 + 0.2 1.4 0.2
j k, l 2 0.7+ 0.3 + 0.2 1.2 0.7
k l 1 0.3 + 0.2 0.5 0.3
l Nil 0 0.2 0.2 0.2

Assigning tasks to workstations:

Workstation number Eligible task Assigned task Task time Unassigned cycle time Reason
1.5
1 a, e a 0.1 1.4 Task 'a' has the most following tasks
b, e b 0.2 1.2 Task 'b' has the most following tasks
c, e c 0.9 0.3 Task 'c' has the most following tasks
d, e e 0.1 0.2 Task 'e' is the only eligible task available
d None 0.2 (Idle time) The task time is greater than the unassigned cycle time.
1.5
2 d d 0.6 0.9 Task 'd' is the only eligible task available
f f 0.2 0.7 Task 'f' is the only eligible task available
g g 0.4 0.3 Task 'g' is the only eligible task available
h h 0.1 0.2 Task 'h' is the only eligible task available
i i 0.2 0 Task 'i' is the only eligible task available
1.5
3 j j 0.7 0.8 Task 'j' is the only eligible task available
k k 0.3 0.5 Task 'k' is the only eligible task available
l l 0.2 0.3 Task 'l' is the only eligible task available
0.3 (Idle time) All tasks completed

Overview of tasks assignment:

Workstation Assigned tasks Total cycle time used Idle time
1 a, b, c, e 1.3 0.2
2 d, f, g, h, i 1.5 0
3 j, k, l 1.2 0.3

c)

Expert Solution
Check Mark
Summary Introduction

To determine: The percentage of idle time.

Answer to Problem 6P

The percentage of idle time is 11.11%.

Explanation of Solution

Formula to calculate percentage of idle time:

Idle time=Total idle timeNumber of workstations×Cycle time×100

Calculation of percentage of idle time:

The solutions for most following tasks rule and highest positional weight is same. Hence, the percentage of idle time will also be the same.

Idle time=0.2+0.0+0.33×1.5×100=0.54.5×100=0.1111×100=11.11%

The percentage of idle time is 11.11%.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
Since the end of World War II, globalization has steadily increased with rapid expansion around the turn of the 21st century. What are some of the forces driving globalization and international business? What are some of the challenges of engaging in international business compared to doing business in your home country?
PS.53 Brother I.D. Ricks is a faculty member at BYU-Idaho whose grandchildren live in Oklahoma and California. He and his wife would like to visit their grandchildren at least once a year in these states. They currently have one vehicle with well over 100,000 miles on it, so they want to buy a newer vehicle with fewer miles and that gets better gas mileage. They are considering two options: (1) a new subcompact car that would cost $18,750 to purchase or (2) a used sedan that would cost $12,750.They anticipate that the new subcompact would get 37 miles per gallon (combined highway and around town driving) while the sedan would get 26 miles per gallon. Based on their road tripping history they expect to drive 13,000 miles per year. For the purposes of their analysis they are assuming that gas will cost $2.93 per gallon.Question: How many miles would the Ricks need to drive before the cost of these two options would be the same? (Display your answer to the nearest whole number.) (Hint:…
Choose one major approach to job design, and then discuss how best that approach can be utilized in either your current or previous employer, including a discussion of its strengths and weaknesses.

Chapter 6 Solutions

Operations Management

Ch. 6.5 - Prob. 1.1RQCh. 6.5 - Prob. 1.2RQCh. 6 - Explain the importance of process selection in...Ch. 6 - Briefly describe the five process types, and...Ch. 6 - Prob. 3DRQCh. 6 - Briefly describe computer-assisted approaches to...Ch. 6 - What is a flexible manufacturing system, and under...Ch. 6 - Prob. 6DRQCh. 6 - Why might the choice of equipment that provides...Ch. 6 - Prob. 8DRQCh. 6 - Prob. 9DRQCh. 6 - Briefly describe the two main layout types.Ch. 6 - Prob. 11DRQCh. 6 - Prob. 12DRQCh. 6 - What is the goal of Line balancing? What happens...Ch. 6 - Why are routing and scheduling continual problems...Ch. 6 - Prob. 15DRQCh. 6 - Prob. 16DRQCh. 6 - The City Transportation Planning Committee must...Ch. 6 - Identify the fixed-path and variable-path...Ch. 6 - Prob. 19DRQCh. 6 - Prob. 20DRQCh. 6 - Prob. 21DRQCh. 6 - Prob. 22DRQCh. 6 - What is cellular manufacturing? What are its main...Ch. 6 - Prob. 24DRQCh. 6 - Prob. 25DRQCh. 6 - Prob. 1TSCh. 6 - What trade-offs are involved when deciding how...Ch. 6 - Who needs to be involved in process selection?Ch. 6 - Prob. 4TSCh. 6 - Prob. 5TSCh. 6 - Prob. 1CTECh. 6 - Prob. 2CTECh. 6 - What are the risks of automating a production...Ch. 6 - Consider an assembly line such as the burrito...Ch. 6 - Prob. 1PCh. 6 - A manager wants to assign tasks to workstations as...Ch. 6 - A manager wants to assign tasks to workstations as...Ch. 6 - A producer of inkjet printer is planning to add a...Ch. 6 - As part of a major plant renovation project, the...Ch. 6 - Twelve tasks, with times and precedence...Ch. 6 - For the given set of tasks, do the following: a....Ch. 6 - A shop works a 400-minute day. The manager of the...Ch. 6 - Arrange six departments into a 2 3 grid so that...Ch. 6 - Using the information given in the preceding...Ch. 6 - Using the information in the following grid,...Ch. 6 - Arrange the eight departments shown in the...Ch. 6 - Arrange the departments so they satisfy the...Ch. 6 - a. Determine the placement of departments fix a...Ch. 6 - Prob. 15PCh. 6 - Develop a process layout that will minimize the...Ch. 6 - Prob. 17PCh. 6 - Rebalance the assembly line in Problem 7. This...
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Text book image
Principles of Management
Management
ISBN:9780998625768
Author:OpenStax
Publisher:OpenStax College
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY