Expert Solution & Answer
Chapter 4, Problem 6E
Explanation of Solution
Project Management
1. Introduction
1.1. Project Name
1.2. Project Description
2. Project’s Organizational Chart
2.1. Project Manager
2.2. Key Team Members
2.3. Organization Chart
2.4. Project Responsibilities
3. Management Objectives
3.1. Project Deliverables
3.2. Project Controls
3.3. Project Staffing
3.4. Risk Management
3...
Expert Solution & Answer
Trending nowThis is a popular solution!
Students have asked these similar questions
Overview
This project involves a case study based on a fictional company, Healthy Home Care, Inc. You’ll assume the role of office manager, who is responsible for creating the literature for a Welcome Package. The promotional documents will be printed and placed in a folder to be mailed to the director of a senior center. For this project, you’ll complete four documents for the package:
A cover letter discussing your partnership with a senior center
A fact sheet highlighting the services and amenities you offer
A flier promoting the next wellness clinic
A pre-registration form
Instructions
Create the following documents. Your score will be based on the rubric found in the scoring guidelines.
Create and Edit a Cover Letter
The Welcome Package includes a letter to the director of a senior center.
Start Word and create a new document.
Change the style of the blank paragraph to No Spacing.
Type the text shown below, pressing Enter to place one blank line where indicated, four blank…
Instructions
Create a first draft of a work breakdown structure (WBS) from the following scenario. Make assumptions as needed based on the section about project planning considerations and constraints in this chapter. In your WBS, describe the skill sets required for the tasks you have planned.
Sequential Label and Supply (SLS) has a problem with employees surfing the Web to access material the company deems inappropriate for a professional environment. Therefore, SLS wants to insert a filtering device in the company Internet connection that blocks certain Web locations and content. According to the vendor, the filter is a hardware appliance that costs $18,000 and requires 150 hours to install and configure. Technical support for the filter costs 18 percent of the purchase price and includes a training allowance for the year. A software component that runs on the administrator’s desktop computer is needed to administer the filter; this component costs $550. A monthly…
Explain and develop an outline (major headings and subheadings only) for a project
management plan to create a Web site for your class, and then fill in the details for the
introduction or overview section. Assume that this Web site would include a home
page with links to a syllabus for the class, lecture notes or other instructional
information, links to the Web site for this textbook, links to other Web sites with
project management information, and links to personal pages for each member of
your class and future classes. Also, include a bulletin board and chat room feature
where students and the instructor can exchange information. Assume that your
instructor is the project's sponsor, you are the project manager, your classmates are
your project team, and you have three months to complete the project.
Chapter 4 Solutions
Information Technology Project Management
Ch. 4 - Describe project integration management. How does...Ch. 4 - Prob. 2DQCh. 4 - Summarize key work involved in each of the six...Ch. 4 - Prob. 4DQCh. 4 - Discuss the importance of following a...Ch. 4 - Which of the following processes is not part of...Ch. 4 - Prob. 2QQCh. 4 - Prob. 3QQCh. 4 - A new government law requires an organization to...Ch. 4 - Prob. 5QQ
Ch. 4 - Prob. 6QQCh. 4 - Prob. 7QQCh. 4 - Prob. 8QQCh. 4 - Prob. 9QQCh. 4 - What tool and technique is used for all processes...Ch. 4 - Write a short paper based on the chapters opening...Ch. 4 - Prob. 2ECh. 4 - Prob. 3ECh. 4 - Prob. 4ECh. 4 - Prob. 5ECh. 4 - Prob. 6ECh. 4 - Prob. 7ECh. 4 - Prob. 8ECh. 4 - Read the report “2015 Pulse of the Profession®:...Ch. 4 - Prob. 10ECh. 4 - Prob. 1TCh. 4 - Prob. 2TCh. 4 - Prob. 3TCh. 4 - Prob. 4TCh. 4 - Prob. 6T
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, computer-science and related others by exploring similar questions and additional content below.Similar questions
- 3. For the FWS group project, the primary reader is your instructor. In future, you may need to prepare projects with different levels of readers. What do you need to consider about the readers when preparing these different kinds of projects? 4. Describe, with examples, where you would prepare a document using the plain style and another kind of document in which you would need to use the persuasive style.arrow_forwardmpletion Status: A Moving to another question will save this response. Question 6 add accuracy to a project when used with CASE tools. Model Physical design Logical design Conceptual design A Moving to another question will save this response.arrow_forwardQuestion 9 nag.Full explain this question and text typing work only We should answer our question within 2 hours takes more time then we will reduce Rating Dont ignore this linearrow_forward
- Assignment Two: Web Process and Project management: Project Risks Student Name: ID: Look at the table below, which are concerned with WEB Project Risks. In here, you are going to consider project risks that you might encounter, or wish to avoid, in developing 3-tier Banking Application. Assume that the development is being done by a Simi-established team, which has done this sort of development before (some are new). Answer the following questions: Characteristics Descriptions (Risks) Content · Lack of understand the structuring of content. · No explicit define about the standard of project qualities. Navigation ·Difficult to navigate and finds problems. · Too large volume of information contains. Presentation · Difficult in operate and simplicity. · Lack of the aesthetic used in content Social Context · Difficult in define content and functional requirement. · Hard to term possible threaten from competitors Technical Context · Complexity of…arrow_forward3arrow_forwardCreate a Work Breakdown Structure in Renovating lecture rooms in your campus . Your WBS must include up to thethird level and must demonstrate dividing work up to multiple work items. A graphic chart format must be used.arrow_forward
- Question: You are recommending that the team make use of the Adaptive Approach to the SDLC. How can this approach be applied to the TAMS project?arrow_forwardTask Requirements: Word Count: 300-400 • Formatting Style: MLA (for more information click here) Structure: Essay *** Any sources must be properly cited according to the formatting style assigned Description: Create in 1 page an IT communication strategy that can be applied in a workplace in order to avowing conflict management.arrow_forwardPlease describe a project you would manage using the Spiral Model or the V Model, including its nature and why you choose that management style.arrow_forward
- The aim of this assignment is for you to apply higher order thinking skills to showcase your ability to reach the outcomes of this study unit. This assignment is project based. This means that you'll receive some minimum requirements for developing your own application. You'll need to come up with a concept, design the graphical user interface, and write the code. 2. Project_SU3_1 MINIMUM REQUIREMENTS MARK INPUT Three (3) variables in total 1 One (1) constant variable 1 PROCESSING One (1) nested decision structure (including else statements) 3 OUTPUT Format output accordingly 1 CONTROLS Appropriate controls used for input and output 1 One (1) container (GroupBox or Panel) OTHER Apply simple exception handling Neat and organised appearance Compile and Run 1 TOTAL 10arrow_forwardCreate a first draft of a work breakdown structure (WBS) from the following scenario. Make assumptions as needed based on the section about project planning considerations and constraints in Chapter 10. In your WBS, describe the skill sets required for the tasks you have planned. Scenario: Sequential Label and Supply (SLS) has a problem with employees surfing the Web to access material the company deems inappropriate for a professional environment. Therefore, SLS wants to insert a filtering device in the company Internet connection that blocks certain web locations and content. According to the vendor, the filter is a hardware appliance that costs $18,000 and requires 150 hours to install and configure. Technical support for the filter costs 18 percent of the purchase price and includes a training allowance for the year. A software component that runs on the administrator’s desktop computer is needed to administer the filter; this component costs $550 per month. A monthly subscription…arrow_forwardCreate a topic proposal for an web-based attendance tracker. Questions: 1. Reasons for the choice of project 2. Project Context 3. Importance of Study 4. Target Users/Beneficiary 5. Project Time Table (Gnatt chart)arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Information Technology Project ManagementComputer ScienceISBN:9781337101356Author:Kathy SchwalbePublisher:Cengage Learning
Information Technology Project Management
Computer Science
ISBN:9781337101356
Author:Kathy Schwalbe
Publisher:Cengage Learning