Information Technology Project Management
9th Edition
ISBN: 9781337101356
Author: Kathy Schwalbe
Publisher: Cengage Learning
expand_more
expand_more
format_list_bulleted
Expert Solution & Answer
Chapter 4, Problem 4E
Explanation of Solution
Spreadsheet to display NPV, ROI, and year:
Investment in the project:
NPV (Net Present Value) = $28,600
ROI (Return On Invest...
Expert Solution & Answer
Trending nowThis is a popular solution!
Students have asked these similar questions
Explanation In the first example, your initial amount of money is $200, which enable you to invest in the first, second, fourth and fifth project that needs only $200 each. By establishing these four projects apart, the investor will have $200*4 (profit) +$200 (initial basic) = $1000. This amount of money will enable the establishment the 3rd project that needs $500 of investment to gain $200 of profit. Finally, to calculate the overall profit, you have collected $1200, where $200 of them are the initial basic and hence the profit is $1200 - $200 = $1000.
In the second example, your initial amount of money is $150, which enable you to invest in the 3rd project only. By doing so, your budget will increases to $200 and hence be able to invest in the 1st project to again increase your budget to $290. However, this is not enough to invest in the 3rd project. Finally, you collected $290, where $150 of them are the initial basic and hence the profit is $290 - $150 = $140.
""" I want…
Use Critical Path Method to estimate in how many weeks the project below will be submitted and find the critical path.
(Choose 2 answers weeks and critical path)
Activity
A: Prepare initial design
B: Identify new potential clients
C: Develop prospectus for tenants A
D: Prepare final design
E: Obtain planning permission
F: Obtain finance from bank
G: Select contractor
H: Construction
I: Finalize tenant contracts
dependent
time
8
D
3
D
4
6, F
В, С, Е
I, H
17
13
J: Tenants move in
Critical path : A-D-E-F-H-J
O Critical path: A-C-E-F H-J
35 weeks
29 Weeks
Critical path : A-G-E-F-H-J
34 Weeks
Determine the output and input variables for cost estimates using the bottom-up and top-down approaches.
Chapter 4 Solutions
Information Technology Project Management
Ch. 4 - Describe project integration management. How does...Ch. 4 - Prob. 2DQCh. 4 - Summarize key work involved in each of the six...Ch. 4 - Prob. 4DQCh. 4 - Discuss the importance of following a...Ch. 4 - Which of the following processes is not part of...Ch. 4 - Prob. 2QQCh. 4 - Prob. 3QQCh. 4 - A new government law requires an organization to...Ch. 4 - Prob. 5QQ
Ch. 4 - Prob. 6QQCh. 4 - Prob. 7QQCh. 4 - Prob. 8QQCh. 4 - Prob. 9QQCh. 4 - What tool and technique is used for all processes...Ch. 4 - Write a short paper based on the chapters opening...Ch. 4 - Prob. 2ECh. 4 - Prob. 3ECh. 4 - Prob. 4ECh. 4 - Prob. 5ECh. 4 - Prob. 6ECh. 4 - Prob. 7ECh. 4 - Prob. 8ECh. 4 - Read the report “2015 Pulse of the Profession®:...Ch. 4 - Prob. 10ECh. 4 - Prob. 1TCh. 4 - Prob. 2TCh. 4 - Prob. 3TCh. 4 - Prob. 4TCh. 4 - Prob. 6T
Knowledge Booster
Similar questions
- Table that fulfills the function of relating each project requirement to the deliverable that satisfies it. a.BCG Matrix b.Project Requirements Traceability Matrix c.Traceability Matrixarrow_forwardQuestion One (1) You participated in an evaluation of proposals for consulting services. At the end of the Technical Evaluation which required a minimum of 70 points, you got the following results: CONSULTANTS KANYIHAMPA MUSANGILA Technical Score 75.17 76.17 Amount USD475,000.00 USD625,000.00 The lowest evaluated financial proposal (Fm) is given the maximum financial score of 100. The formula for determining the financial score is as follows: SF = 100 x Fm /F in which SF is the financial score, Fm is the lowest price and F is the price of the proposal under consideration. The weights given to the Technical and Financial proposals are 80 and 20 respectively. Calculate for each consultant below (a – c): Weighted Technical score. Financial score Combined weighted Technical and weighted Financial score Indicate the best evaluated bidder and their pointsarrow_forwardAngel Consulting is considering 8 projects. Each project has a cost and an associated return. The budget at Angel is $580. Angel would like to choose the set of projects that maximize the total project return. This data below is provided in the workbook that accompanies this quiz. Project 1 2 3 4 5 6 7 8 Cost $130 $100 $165 $180 $225 $190 $140 $185 Return $205 $225 $350 $285 $400 $325 $265 $375 Which of the following are true for Angel Consulting's project choice problem? O When executing the Greedy Solution Heuristic for this problem, the first project selected is project 5. O When executing the Greedy Solution Heuristic for this problem, the second project selected is project 3. O Exactly two answers are correct. O The Greedy Solution Heuristic completely ignores the project costs and only looks at the project returns. O The solution found using the Greedy Solution Heuristic for this problem will have 3 projects.arrow_forward
- Please do it in excelarrow_forwardTo cut the number of projects, the steering committee used a weighting scheme that reflected the airline’s priorities, which were: fly safe, generate revenue, reduce costs, and customer service. The weighting scheme easily weeded out the fluff.” 1.Use a weighted scoring model to help the committee choose between two projects: Booking System Upgrade and Cabin Crew Retraining. The relative weights for each criterion and the assessment of each project for these criteria are shown in the following table. Which project would you choose and why?arrow_forwardConsider the following project activities: Activity Name A B C D E F G Activity Name A B C D E F G Immediate Predecessor (list number/ name, separated by ',') Answer Activity Time 6 9 12 8 9 Fill the given table with the required data and draw the network diagram for the above project activities to find the critical path. 6 5 Project Completion Time = The Critical Path is= A A, B D C, E E Normal Time 6 Days 9 12 8 9 6 5 Earliest Earliest Latest Latest Slack Start Finish Start Finish (LS) (EF) (ES) (LF) (LS-ES)arrow_forward
- The projected number of defects submitted, resolved, and remaining open inthe first four weeks of a test project are given in the upper half of Table 13.18.The actual numbers of submitted and resolved defects are shown in the lowerhalf of the table. Calculate the actual number of open defects?arrow_forwardA company specializing in custom-engineered equipment is planning to submit a proposal to the National 5. Aeronautics and Space Administration (NASA) to build an assembled component for a new space station that NASA plans to launch into orbit. The winning proposal will be selected on the basis of both cost and timely delivery. Also, there will be a penalty clause in the NASA contract for late delivery. The company has developed the schedule of activities that are required to produce the assembled component. The activities and precedence requirements are presented in the table below. Three time estimates (in weeks) are given for each activity: optimistic time, most likely time, and pessimistic time. (a) What completion time should the company specify in its proposal in order to be 85% sure that it will complete the project on time? ij Activity Immediate predecessor Optimistic time (weeks) a b d. h b e, d d e,f f,g h, i a a a 15 8 10 20 17 4 10 Most likely time (weeks) 24 16 10 14 26 23…arrow_forwardUse the following business rules to create a Crow’s Foot ERD. Write all appropriate connectivities and cardinalities in the ERD. a. A department employs many employees, but each employee is employed by one department. b. Some employees, known as “rovers,” are not assigned to any department. c. A division operates many departments, but each department is operated by one division. d. An employee may be assigned many projects, and a project may have many employees assigned to it. e. A project must have at least one employee assigned to it. f. One of the employees manages each department, and each department is managed by only one employee. g. One of the employees runs each division, and each division is run by only one employee. Given these data requirements, design a logical/relational data model for this company. Use Microsoft Visio for your diagrams. You can add substantial detail to your data model by including sample attributes for each of the entities. Specify primary and foreign…arrow_forward
- Computer Science Rewrite this brief section. Create a table that illustrates the data. INTRODUCTION: The University of Wisconsin–Stout has experienced a series of large budget cuts in recent years. The athletic department has been granted an estimated budget of $250,000 for updates of current facilities. For a new floor installation to be feasible, the total cost must not reach over $250,000. FIGURES: According to Connors Flooring, the total installation cost of a maple sports floor is $81,300 with over 38 years of life expectancy. This is based on a 10,000-square-foot floor. The Maple Floor Manufacturers Association has concluded that wood floors also require regular cleaning, sanding, lines repainted, and floor refinishing approxi- mately every three years. This is a cost of approximately $8,000.00 per three years, equaling $2,666.00 p/year. With a 38 year life expectancy, the total for cleaning, sanding, painting, etc. = 101,308. CONCLUSION: The total cost of the floor is under…arrow_forwardDraw a project triangle that shows the relationship among project cost, scope, and timearrow_forwardAssignment Choose one of the following system (ATM, pharmacy, food ordering system, or library) Each student should perform the following tasks in his/her project: 1- Identify the problem, objectives, and methodology to be used 2- Determine the functional and non- functional requirements. Also, determine the type of collecting the requirements 3- Select suitable Model 4- Draw use case and Sequence Diagramarrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Information Technology Project ManagementComputer ScienceISBN:9781285452340Author:Kathy SchwalbePublisher:Cengage LearningInformation Technology Project ManagementComputer ScienceISBN:9781337101356Author:Kathy SchwalbePublisher:Cengage LearningOperations Research : Applications and AlgorithmsComputer ScienceISBN:9780534380588Author:Wayne L. WinstonPublisher:Brooks Cole
- Principles of Information Systems (MindTap Course...Computer ScienceISBN:9781305971776Author:Ralph Stair, George ReynoldsPublisher:Cengage LearningPrinciples of Information Security (MindTap Cours...Computer ScienceISBN:9781337102063Author:Michael E. Whitman, Herbert J. MattordPublisher:Cengage Learning
Information Technology Project Management
Computer Science
ISBN:9781285452340
Author:Kathy Schwalbe
Publisher:Cengage Learning
Information Technology Project Management
Computer Science
ISBN:9781337101356
Author:Kathy Schwalbe
Publisher:Cengage Learning
Operations Research : Applications and Algorithms
Computer Science
ISBN:9780534380588
Author:Wayne L. Winston
Publisher:Brooks Cole
Principles of Information Systems (MindTap Course...
Computer Science
ISBN:9781305971776
Author:Ralph Stair, George Reynolds
Publisher:Cengage Learning
Principles of Information Security (MindTap Cours...
Computer Science
ISBN:9781337102063
Author:Michael E. Whitman, Herbert J. Mattord
Publisher:Cengage Learning