Resolve Problem 4.19 with α = .1 and β =.8. Using MSE, determine which smoothing constants provide a better
To determine: Compute MSE using the given smoothing constants and find the better forecasting smoothing constants using trend-adjusted exponential smoothing method.
Introduction: A sequence of data points in successive order is known as time series. Time series forecasting is the prediction based on past events which are at uniform time interval. Moving average method and trend projections are two of the time series methods which use weights to prioritize past data.
Answer to Problem 20P
On comparing MSE from two smoothing constants (refer to equations (1) and (2)), it can be inferred that smoothing constant with α=0.1 and β=0.8 provides better forecast because it minimizes the error.
Explanation of Solution
Given information:
Time period | Month | Income ($ in thousands) |
1 | February | 70 |
2 | March | 68.5 |
3 | April | 64.8 |
4 | May | 71.7 |
5 | June | 71.3 |
6 | July | 72.8 |
Formula to calculate the MSE &forecasted demand
Where,
Calculation of FIT and MSE usingα=0.1 andβ=0.2:
Time period | Month | Income ($ in thousands) | Ft ($ in thousands) | Tt | FIT | Error | Sq. Error |
1 | February | 70 | 65 | 0 | 65 | 5 | 25 |
2 | March | 68.5 | 65.500 | 0.100 | 65.600 | 2.9 | 8.41 |
3 | April | 64.8 | 65.890 | 0.158 | 66.048 | -1.25 | 1.56 |
4 | May | 71.7 | 65.923 | 0.133 | 66.056 | 5.64 | 31.85 |
5 | June | 71.3 | 66.621 | 0.246 | 66.867 | 4.43 | 19.66 |
6 | July | 72.8 | 67.310 | 0.335 | 67.644 | 5.16 | 26.58 |
Total | 113.05 | ||||||
MSE | 18.84 |
Table 1
Excel worksheet:
Calculation of FIT for February:
To calculate FIT for February, compute F1 and T1. The forecast F1 is $ 65 and trend T1 is 0. The sum of both values gives FIT, which is equal to $ 65.
Calculation of FIT for March:
To calculate FIT for February, compute F2 and T2. The forecast F2 is $ 65.5 and trend T2 is 0.1. The sum of both values gives FIT, which is equal to $ 65.60.
Calculation of FIT for April:
To calculate FIT for March, compute F3 and T3. The forecast F3 is $ 65.890 and trend T3 is 0.158. The sum of both values gives FIT, which is equal to $ 66.048.
Calculation of FIT for May:
To calculate FIT for May, compute F4 and T4. The forecast F4 is $ 65.923 and trend T4 is 0.133. The sum of both values gives FIT, which is equal to $ 66.056.
Calculation of FIT for June:
To calculate FIT for June, compute F5 and T5. The forecast F5 is $ 66.621 and trend T5 is 0.246. The sum of both values gives FIT, which is equal to $ 66.867.
Calculation of FIT for July:
To calculate FIT for July, compute F6 and T6. The forecast F6 is $ 67.310 and trend T6 is 0.335. The sum of both values gives FIT, which is equal to $ 67.644.
Calculation of MSE:
MSE is obtained by dividing the summation value of the square of the difference between actual and forecasted sales with the number of years n; n=6.
Table 1provides the values for square of the difference between actual and forecasted sales.
MSE using α=0.1 and β=0.2 is 18.84.
Calculation of FIT and MSE using α=0.1 and β=0.8:
Time period | Month | Income ($ in thousands) | Ft ($ in thousands) | Tt | FIT | Error | Sq. Error |
1 | February | 70 | 65 | 0 | 65 | 5 | 25 |
2 | March | 68.5 | 65.500 | 0.400 | 65.900 | 2.6 | 6.76 |
3 | April | 64.8 | 66.160 | 0.608 | 66.768 | -1.968 | 3.87 |
4 | May | 71.7 | 66.571 | 0.451 | 67.022 | 4.678 | 21.89 |
5 | June | 71.3 | 67.490 | 0.825 | 68.314 | 2.986 | 8.91 |
6 | July | 72.8 | 68.613 | 1.064 | 69.677 | 3.123 | 9.76 |
Total | 76.19 | ||||||
MSE | 12.70 |
Table 2
Excel worksheet:
Calculation of FIT for February:
To calculate FIT for February, compute F1 and T1. The forecast F1 is $ 65 and trend T1 is 0. The sum of both values gives FIT, which is equal to $ 65.
Calculation of FIT for March:
To calculate FIT for February, compute F2 and T2. The forecast F2 is $ 65.5 and trend T2 is 0.4. The sum of both values gives FIT, which is equal to $ 65.90.
Calculation of FIT for April:
To calculate FIT for March, compute F3 and T3. The forecast F3 is $ 66.160 and trend T3 is 0.608. The sum of both values gives FIT, which is equal to $ 66.786.
Calculation of FIT for May:
To calculate FIT for May, compute F4 and T4. The forecast F4 is $66.571 and trend T4 is 0.451. The sum of both values gives FIT, which is equal to $ 67.022.
Calculation of FIT for June:
To calculate FIT for June, compute F5 and T5. The forecast F5 is $ 67.490 and trend T5 is 0.825. The sum of both values gives FIT, which is equal to $ 68.314.
Calculation of FIT for July:
To calculate FIT for July, compute F6 and T6. The forecast F6 is $ 68.613 and trend T6 is 1.064. The sum of both values gives FIT, which is equal to $ 69.677.
Calculation of MSE:
MSE is obtained by dividing the summation value of the square of the difference between actual and forecasted sales with the number of years n=6.
Table 2provides the values for square of the difference between actual and forecasted sales.
MSE using α=0.1 and β=0.8 is 12.70.
On comparing MSE from two smoothing constants (refer to equations(1)&(2)), it can be inferred that smoothing constant with α=0.1 and β=0.8 provides better forecast because it minimizes the error.
Want to see more full solutions like this?
Chapter 4 Solutions
EBK PRINCIPLES OF OPERATIONS MANAGEMENT
- I need to forecast using a 3-Period-Moving-Average-Monthly forecasting model which I did but then I need to use my forecast numbers to generate a Master Production Schedule (MPS) I have to Start with actual sales (my own test data numbers) for August-2022 Oct-2022 i need to create MPS to supply demand starting November-2022 April 2023 I just added numbers without applying formulas to the mps on the right side of the spreadsheet because I do not know how to do it. The second image is the example of what it should look like. Thank You.arrow_forwardSolve the following Question 1. How do volume and variety affect the process selection and layout types? Discuss 2. How is the human resource aspect important to operation function? Discuss 3. Discuss the supply network design and its impact on the overall performance of the organization.arrow_forwardHelp with question?arrow_forward
- What are some good examples of bullet points on a resume for a Christian Elementary School?arrow_forwardWhat is an example of a cover letter for a Christian School Long-Term Substitute Teaching position?arrow_forwardThe supply chain is a conventional notion, but organizations are only really interested in making products that they can sell to customers. Provided they have reliable supplies of materials and reasonable transport for finished products, logistics is irrelevant. Do you think this is true? If yes, explain, and if no, clearly explain as well.arrow_forward
- working as a program operations managerarrow_forward12 X1, X230 1 x =0x2 write the Following linear Programming model by 1- general Form Canonical Forms Canonical formY 2- Standard Form Max Z=35X+ 4 X 2 +6 X3 ST. X+2X2-5x3 = 40 3X, + 6X2 + 7x 3 = 30 7x, +lox2 x3 = 50 X3 X 2 X 3 <0arrow_forwarda/ a Minimum cost assign each worker for one job at Jobs J1 12 33 WI 2 4 6 W2 5 W3 5 33 6 7arrow_forward
- وبة واضافة هذه القيمة الى القيم Ex: Assign each job for each worker at minimum total Cost عمل لكل عامل وبأقل كلفة ممكنة obs الأعمال Workors العمال J1 J2 J3 J4 W₁ 15 13 14 12 W2 11 12 15 13 W3 13 12 10 11 W4 15 17 14 16arrow_forwardThe average completion time (flow time) for the sequence developed using the FCFS rule = 11.75 days (round your response to two decimal places). The percentage utilization for the sequence developed using the FCFS rule = 42.55 % (enter your response as a percentage rounded to two decimal places). b) Using the SPT (shortest processing time) decision rule for sequencing the jobs, the order is (to resolve a tie, use the order in which the jobs were received): An Alabama lumberyard has four jobs on order, as shown in the following table. Today is day 205 on the yard's schedule. In what sequence would the jobs be ranked according to the decision rules on the left: Job Due Date A 212 B 209 C 208 D 210 Duration (days) 6 3 3 8 Sequence 1 Job B 2 3 4 A D The average tardiness (job lateness) for the sequence developed using the SPT rule = 5.00 days (round your response to two decimal places). The average completion time (flow time) for the sequence developed using the SPT rule = 10.25 days…arrow_forwardWith the aid of examples, fully discuss any five (5) political tactics used in organisations.arrow_forward
- Contemporary MarketingMarketingISBN:9780357033777Author:Louis E. Boone, David L. KurtzPublisher:Cengage LearningMarketingMarketingISBN:9780357033791Author:Pride, William MPublisher:South Western Educational PublishingPurchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage Learning