Leaky process pumps. Quality (February 2008) presented a problem that actually occurred at a company that produces process pumps for a variety of industries. The company recently introduced a new pump model and immediately began receiving customer complaints about “leaky pumps.” There were no complaints about the old pump model. For each of the first 13 weeks of production of the new pump, quality-control inspectors tested 500 randomly selected pumps for leaks. The results of the leak tests are summarized by week in the accompanying table. Construct an appropriate control chart for the data. What does the chart indicate about the stability of the process?

  Week Number Tested Number with Leaks
  1 500 36
  2 500 28
  3 500 24
  4 500 26
  5 500 20
  6 500 56
  7 500 26
  8 500 28
  9 500 31
  10 500 26
  11 500 34
  12 500 26
  13 500 32
Blurred answer
Students have asked these similar questions
Unit 5 Lab   Background: Between the years of 1997 and 2003, the World Health Organization collected data on head circumference, arm circumference, and other body measurements for 8440 children from Brazil, Ghana, India, Norway, Oman and the USA. All of the children were healthy and breastfed by mothers who did not smoke. Children in the sample lived in socioeconomic conditions favorable to normal physical growth. Variables such as parental education level and income level were used to exclude children whose growth was “environmentally constrained”; however, low-weight full term babies were included if their mothers met socioeconomic and nutritional criteria. In short, the study design attempted to include healthy children from a wide range of ethnic and cultural groups whose home environments reasonably assured the conditions for healthy physical growth.   This data was used to produce growth charts that are part of every pediatrician’s toolkit for monitoring a child’s overall…
In this assignment, you will calculate the relative risk, attributable risk, and number needed to treat for a contrived clinical research study. In the study, researchers want to determine whether a new drug will reduce the risk of blood clotting in patients who have been diagnosed with blood clots in the past. 2,000 participants were selected for the study. 1,000 participants were given the new drug, and 1,000 participants were given a placebo. After 5 years, the number of participants from each group who had developed a blood clot were recorded. The data is shown in the table below. 1. Calculate the RR, ARR, and NNT for the data. 2. Briefly interpret each value in your own words.   Blood clot No blood clot Total New drug 21 979   Placebo 45 955   Total
The recommendations of respected wine critics have a substantial effect on the price of wine. Vintages that earn higher ratings command higher prices and spark surges in demand. These data are a random sample of ratings of wines selected from an online Web site from the 2000 and 2001 vintages. Complete parts (a) through (d). Click the icon to view the table of wine rating, price, and vintage. Yes, all the conditions are satisfied. B. No, the 2000 data contains outliers. No, the 2001 data is too skewed. D. No, the sampling procedure was not identified and it cannot be condluded that this is a simple random survey. No, the variances are drastically different. (b) Find the 95% confidence interval for the difference in average ratings in these two vintages. Does one of the years look better than the other? The 95% confidence interval for P2000 - P2001 is ( – 1.0. 1.7). (Round to one decimal place as needed.) Does one of the years look better than the other? O A. Yes, 2000 looks better…

Chapter 13 Solutions

Statistics for Business and Economics (13th Edition)

Ch. 13.4 - The data in the following table were collected for...Ch. 13.4 - Prob. 13.12ACBCh. 13.4 - Active pharmaceutical ingredient. During the...Ch. 13.4 - Detecting gender-related employment disparities....Ch. 13.4 - Pain levels of ICU patients. Various interventions...Ch. 13.4 - Quality control for irrigation data. Most farmers...Ch. 13.4 - Improving public health waiting times. Statistical...Ch. 13.4 - Cereal box manufacturing. A machine at K-Company...Ch. 13.4 - Detecting under-reported emissions. The...Ch. 13.4 - 13 20 Selecting the best wafer-slicing machine....Ch. 13.4 - Chunky data. BPI Consulting, a leading provider of...Ch. 13.4 - Military aircraft bolts. A precision parts...Ch. 13.5 - What characteristic of a process is an R-chart...Ch. 13.5 - Prob. 13.24LMCh. 13.5 - Use Table IX on page 13-74 to find the values of...Ch. 13.5 - Construct and interpret an R-chart for the data in...Ch. 13.5 - Construct and interpret an R-chart for the data in...Ch. 13.5 - Construct and interpret an R-chart and an x -chart...Ch. 13.5 - Weight of packed frozen scallops. In Quality...Ch. 13.5 - Detecting gender-related employment disparities....Ch. 13.5 - Pain levels of ICU patients. Refer to the Research...Ch. 13.5 - Quality control for irrigation data. Refer to...Ch. 13.5 - Lowering the thickness of an expensive blow-molded...Ch. 13.5 - Cola bottle filling process. A soft-drink bottling...Ch. 13.5 - Chunky data. Refer to Exercise 13.21e (p. 13-40)...Ch. 13.5 - Replacement times for lost ATM cards. In an effort...Ch. 13.5 - Military aircraft bolts. Refer to the...Ch. 13.5 - Precision of scale weight measurements. The...Ch. 13.6 - What characteristic of a process is a p-chart...Ch. 13.6 - In each of the following cases, use the sample...Ch. 13.6 - The proportion of defective items generated by a...Ch. 13.6 - To construct a p-chart for a manufacturing...Ch. 13.6 - To construct a p-chart, 20 samples of size 150...Ch. 13.6 - Academic failure rates in Nigeria. The quality...Ch. 13.6 - Monitoring surgery complications. An article on...Ch. 13.6 - Rental car call center study. A worldwide rental...Ch. 13.6 - Defective micron chips. A manufacturer produces...Ch. 13.6 - Hand break cable defects. In Control Engineering...Ch. 13.6 - Monitoring newspaper typesetters. Accurate...Ch. 13.6 - Quality of rewritable CDs. A Japanese compact disc...Ch. 13.6 - Leaky process pumps. Quality (February 2008)...Ch. 13.6 - Rubber company lire tests. Goodstone Tire Rubber...Ch. 13.7 - Explain why it is inappropriate to conduct a...Ch. 13.7 - Explain the difference between process spread and...Ch. 13.7 - Describe two different ways to assess the...Ch. 13.7 - Why is it recommended to use and interpret Cp in...Ch. 13.7 - For a process that is in control and follows a...Ch. 13.7 - Find the specification spread for each of the...Ch. 13.7 - Find (or estimate) the process spread for each of...Ch. 13.7 - Find the value of Cp for each of the following...Ch. 13.7 - Upper specification limit of a process. An...Ch. 13.7 - Capability of an in-control process. A process is...Ch. 13.7 - Water use at a thermal power plant. Thermal power...Ch. 13.7 - Cereal box filling process. Refer to the data on...Ch. 13.7 - Military aircraft bolts. Refer to Exercise 13.22...Ch. 13.7 - Bioreactor production of antibodies. Benchtop...Ch. 13.7 - Driver gear bore holes. During the manufacture of...Ch. 13.7 - Lowering the thickness of an expensive blow-molded...Ch. 13 - Define quality and list its important dimensions.Ch. 13 - What is a process? Give an example of an...Ch. 13 - What is a system? Give an example of a system with...Ch. 13 - Describe the six major sources of process...Ch. 13 - Suppose all the output of a process over the last...Ch. 13 - Processes that are in control are predictable;...Ch. 13 - Compare and contrast special and common causes...Ch. 13 - Explain the difference between control limits and...Ch. 13 - Should control charts be used to monitor a process...Ch. 13 - Under what circumstances is it appropriate to use...Ch. 13 - A process is under control and follows a normal...Ch. 13 - Weight of a product. Consider the time series data...Ch. 13 - Lengths of pencils. The length measurements of 20...Ch. 13 - Applying pattern-analysis rules. Use the...Ch. 13 - Defective plastic mold. A company that...Ch. 13 - Robotics clamp gap width. Control chart...Ch. 13 - Package sorting time. AirExpress. an overnight...Ch. 13 - Waiting times of airline passengers. Officials at...Ch. 13 - Defects in graphite shafts. Over the last year, a...Ch. 13 - New iron-making process. Mining Engineering...Ch. 13 - CPU of a computer chip. The central processing...Ch. 13 - Bayfield Mud Company case. The text Quantitative...
Knowledge Booster
Background pattern image
Statistics
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, statistics and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Functions and Change: A Modeling Approach to Coll...
Algebra
ISBN:9781337111348
Author:Bruce Crauder, Benny Evans, Alan Noell
Publisher:Cengage Learning
Text book image
Glencoe Algebra 1, Student Edition, 9780079039897...
Algebra
ISBN:9780079039897
Author:Carter
Publisher:McGraw Hill
Hypothesis Testing using Confidence Interval Approach; Author: BUM2413 Applied Statistics UMP;https://www.youtube.com/watch?v=Hq1l3e9pLyY;License: Standard YouTube License, CC-BY
Hypothesis Testing - Difference of Two Means - Student's -Distribution & Normal Distribution; Author: The Organic Chemistry Tutor;https://www.youtube.com/watch?v=UcZwyzwWU7o;License: Standard Youtube License