
a)
To determine: The standard time for the operation.
Introduction: Time study is the basis that helps set the standard time; it would time a sample of the performance of the worker.
a)

Answer to Problem 30P
Thestandard time is calculated as 85.56 minutes.
Explanation of Solution
Given information:
Fatigue factor is given as 10% and personal-time factor is 10%. Accuracy rate is ±5%. The observed time and performance rating for each element is given as follows:
Element | Performance rating | Observation (minutes) | ||||||
1 | 2 | 3 | 4 | 5 | 6 | 7 | ||
Select correct mufflers | 110% | 4 | 5 | 4 | 6 | 4 | 15a | 4 |
Remove old muffler | 90% | 6 | 8 | 7 | 6 | 7 | 6 | 7 |
Weld/install new muffler | 105% | 15 | 14 | 15 | 12 | 15 | 16 | 13 |
Check/inspect work | 100% | 3 | 4 | 24a | 5 | 4 | 3 | 18a |
Complete paperwork | 130% | 5 | 6 | 8 | - | 7 | 6 | 7 |
a refers to the fact that the employee has lengthy conversations with the boss (not job-related)
Formulae to calculate standard time:
Calculate normal time:
Element | Performance rating | Observation (minutes) | Average time | Normal time | ||||||
1 | 2 | 3 | 4 | 5 | 6 | 7 | ||||
Select correct mufflers | 110% | 4 | 5 | 4 | 6 | 4 | 15a | 4 | 4.50 | 4.95 |
Remove old muffler | 90% | 6 | 8 | 7 | 6 | 7 | 6 | 7 | 6.71 | 6.04 |
Weld/install new muffler | 105% | 15 | 14 | 14 | 12 | 15 | 16 | 13 | 14.14 | 14.85 |
Check/inspect work | 100% | 3 | 4 | 24a | 5 | 4 | 3 | 18a | 3.80 | 3.80 |
Complete paperwork | 130% | 5 | 6 | 8 | - | 7 | 6 | 7 | 6.50 | 8.45 |
Excel worksheet:
Calculate the average time to select correct mufflers:
The average time is calculated by taking an average of the observation given, which is the summation of 4, 5, 4, 6, 4, and 4 and dividing the result by 6. Hence, the average is 4.5 minutes.
Note: The observation with (Xa) should not be considered while calculating the average time.
Calculate the average time to remove the old muffler:
The average time is calculated by taking an average of the observation given, which is the summation of 6, 8, 7, 6, 7, 6, and 7 and dividing the result by 7. Hence, the average is 6.71 minutes.
Calculate the average time to weld or install a new muffler:
The average time is calculated by taking an average of the observation given, which is the summation of 15, 14, 14, 12, 15, 16, and 13 and dividing the result by 7. Hence, the average is 14.14 minutes.
Calculate the average time to check or inspect work:
The average time is calculated by taking an average of the observation given, which is the summation of 3, 4, 5, 4, and 3 and dividing the result by 5. Hence, the average is 3.80 minutes.
Note: The observation with (Xa) should not be considered while calculating the average time.
Calculate the average time to complete paperwork:
The average time is calculated by taking an average of the observation given, which is the summation of 5, 6, 8, 7, 6, and 7 and dividing the result by 6. Hence, the average is 6.50 minutes.
Calculate the normal time to select correct mufflers:
The normal time is calculated by multiplying the average time and performance rating. Average time is calculated as 4.50 minutes and performance rating is given as 110%. Hence, the normal time is 4.95 minutes.
Calculate the normal time to remove the old muffler:
The normal time is calculated by multiplying the average time and performance rating. Average time is calculated as 6.71 minutes and performance rating is given as 90%. Hence, the normal time is 6.04 minutes.
Calculate the normal time to weld or install a new muffler:
The normal time is calculated by multiplying the average time and performance rating. Average time is calculated as 14.14 minutes and performance rating is given as 105%. Hence, the normal time is 14.85 minutes.
Calculate the normal time to check or inspect work:
The normal time is calculated by multiplying the average time and performance rating. Average time is calculated as 3.80 minutes and performance rating is given as 100%. Hence, the normal time is 3.80 minutes.
Calculate the normal time to complete paperwork:
The normal time is calculated by multiplying the average time and performance rating. Average time is calculated as 6.50 minutes and performance rating is given as 130%. Hence, the normal time is 8.45 minutes.
Calculate the total normal time:
The normal time is calculated by multiplying the average time and performance rating. Average time is calculated as 6.50 minutes and performance rating is given as 130%. Hence, the normal time is 8.45 minutes.
Normal time is calculated by adding the normal time to select correct mufflers, remove the old muffler, weld or install a new muffler, check or inspect work, and to complete paperwork.
Hence, the total normal time is 38.09 minutes.
Calculate the standard time:
The standard time is calculated by dividing the normal time with the value attained by subtracting the allowance factor from 1. Normal time is calculated as 38.09 minutes and allowance factor is calculated as the sum of fatigue factor, which is 10% and personal time factor, which is 10%.
Hence, the standard time is 47.6 minutes.
b)
To determine: The number of
Introduction: Thesample size is required to determine the number of observations that are necessary to find the true cycle time.
b)

Answer to Problem 30P
Thesample size to select correct mufflers is 53, to remove the old muffler is 20, to weld or install a new muffler is 14, to check or inspect work is 75, and to complete paperwork is 40 samples.
Explanation of Solution
Given information:
Confidence level is 95% and accuracy is ±5%.
Element | Performance rating | Observation (minutes) | ||||||
1 | 2 | 3 | 4 | 5 | 6 | 7 | ||
Select correct mufflers | 110% | 4 | 5 | 4 | 6 | 4 | 15a | 4 |
Remove old muffler | 90% | 6 | 8 | 7 | 6 | 7 | 6 | 7 |
Weld/install new muffler | 105% | 15 | 14 | 15 | 12 | 15 | 16 | 13 |
Check/inspect work | 100% | 3 | 4 | 24a | 5 | 4 | 3 | 18a |
Complete paperwork | 130% | 5 | 6 | 8 | - | 7 | 6 | 7 |
a refers to the fact that the employee has lengthy conversation with the boss (not job-related)
Formulae to determine the required number of observation:
n refers to number of observations required
z refers to the table value for confidence level
s refers to standard deviation
h refers to accuracy level
Determine the proper number of observations required:
Element | Performance rating | Observation (minutes) | Average time | s | Sample | ||||||
1 | 2 | 3 | 4 | 5 | 6 | 7 | |||||
Select correct mufflers | 110% | 4 | 5 | 4 | 6 | 4 | 15a | 4 | 4.50 | 0.836 | 53.1 |
Remove old muffler | 90% | 6 | 8 | 7 | 6 | 7 | 6 | 7 | 6.71 | 0.755 | 19.5 |
Weld/install new muffler | 105% | 15 | 14 | 14 | 12 | 15 | 16 | 13 | 14.14 | 1.345 | 13.9 |
Check/inspect work | 100% | 3 | 4 | 24a | 5 | 4 | 3 | 18a | 3.80 | 0.836 | 74.5 |
Complete paperwork | 130% | 5 | 6 | 8 | - | 7 | 6 | 7 | 6.50 | 1.048 | 40.0 |
Excel worksheet:
Calculate the standard deviation to select correct mufflers:
The standard deviation can be calculated by dividing two values. The first value can be calculated by adding the square of the value attained by subtracting the mean observed value from each observation. The second value can be attained by subtracting 1 from the number of samples and the result should be square rooted. Standard deviation to select correct mufflers is 0.836.
Calculate standard deviation to remove old muffler:
The standard deviation can be calculated by dividing two values. The first value can be calculated by adding the square of the value attained by subtracting the mean observed value from each observation. The second value can be attained by subtracting 1 from the number of samples and the result should be square rooted. Standard deviation to remove old muffler is 0.755.
Calculate standard deviation to weld or install new muffler:
The standard deviation can be calculated by dividing two values. The first value can be calculated by adding the square of the value attained by subtracting the mean observed value from each observation. The second value can be attained by subtracting 1 from the number of samples and the result should be square rooted. Standard deviation to weld or install new muffler is 1.345.
Calculate standard deviation to check or inspect work:
The standard deviation can be calculated by dividing two values. The first value can be calculated by adding the square of the value attained by subtracting the mean observed value from each observation. The second value can be attained by subtracting 1 from the number of samples and the result should be square rooted. Standard deviation to check or inspect work is 0.836.
Calculate standard deviation to complete paperwork:
The standard deviation can be calculated by dividing two values. The first value can be calculated by adding the square of the value attained by subtracting the mean observed value from each observation. The second value can be attained by subtracting 1 from the number of samples and the result should be square rooted. Standard deviation to check or inspect work is 1.048.
Calculate the sample size to select correct mufflers:
It is calculated by multiplying the z value of 1.96, the standard deviation that is given as 0.836, and dividing the resultant with the multiple of the accuracy level and the average observed time that is given as 0.05 and 4.5, respectively. Hence, the required number of observations is 53 samples.
Calculate the sample size to remove the old muffler:
It is calculated by multiplying the z value of 1.96, the standard deviation that is given as 0.755, and dividing the resultant with the multiple of the accuracy level and the average observed time that is given as 0.05 and 6.71, respectively. Hence, the required number of observations is 20 samples.
Calculate the sample size to weld or install a new muffler:
It is calculated by multiplying the z value of 1.96, the standard deviation that is given as 1.345, and dividing the resultant with the multiple of the accuracy level and the average observed time that is given as 0.05 and 14.14, respectively. Hence, the required number of observations is 14 samples.
Calculate the sample size to check or inspect work:
It is calculated by multiplying the z value of 1.96, the standard deviation that is given as 0.836, and dividing the resultant with the multiple of the accuracy level and the average observed time that is given as 0.05 and 3.8, respectively. Hence, the required number of observations is 75 samples.
Calculate the sample size to complete paperwork:
It is calculated by multiplying the z value of 1.96, the standard deviation that is given as 1.048, and dividing the resultant with the multiple of the accuracy level and the average observed time that is given as 0.05 and 6.5, respectively. Hence, the required number of observations is 40 samples.
Hence, the standard time for the process is 47.6 minutes. The sample size to select correct mufflers are 53, to remove the old muffler is 20, weld or install a new muffler is 14, to check or inspect work is 75 samples, and to complete paperwork is 40 samples.
Want to see more full solutions like this?
Chapter 10 Solutions
Principles Of Operations Management
- With your experience and research, discuss;(a) what type of “Leadership Style” is used in communications services (Digicel Group Limited)?(b) whether the style used is successful or not and why. Justify your position with relevant citation and references ( Rubic is attached to guide the essay ) NOTE: NO AI RESPONSES PLEASEarrow_forwardby the end of 2013, the IPL port was operational and the naphtha was flowing to the Himachal Fertilizer Corporation (HFC) plant in Central India after being granted the port contract in Summer 2012. The plant was located in an industrial area that had several pipelines in the general geographic area including a crude oil pipeline leading to a refinery, and a pipeline carrying pesticides to be processed and redistributed to local farms in the area. In July 2014, Ajay Patel, the logistics general manager received notification that there were some minor leaks along the pipeline that were being fixed. Workers in the area had experienced sudden headaches and lightheadedness and the company immediately moved to investigate the leak and address faulty seams that had eroded and weakened. The flow of naphtha was temporarily stopped for 72 hours so two portions of the pipeline could be removed, and the eroded portions replaced. Patel put enormous pressure on the repair team to get the repair…arrow_forwardin the MABE: learning to be multinational case report, what is the reccomended course of action?arrow_forward
- In the MABE case report what would be the reccomened course of action?arrow_forwardQuestion 6. An electrical engineering company is designing two types of solar panel systems: Standard Panels (S) and High-Efficiency Panels (H). The company has certain constraints regarding the hours of labor and material available for production each week. Each Standard Panel requires 4 hours of labor and 2 units of material and each High-Efficiency Panel requires 3 hours of labor and 5 units of material. The company has a maximum of 60 hours of labor and 40 units of material available per week. The profit from each Standard Panel is GH¢80, and the profit from each High-Efficiency Panel is GH¢100. The company wants to determine how many of each type of panel to produce in order to maximize profit. i) Solve this LPP by using graphical analysis ii) What will be the slack at the optimal solution point? Show calculation.arrow_forwardqusestion 6. An electrical engineering company is designing two types of solar panel systems: Standard Panels (S) and High-Efficiency Panels (H). The company has certain constraints regarding the hours of labor and material available for production each week. Each Standard Panel requires 4 hours of labor and 2 units of material and each High-Efficiency Panel requires 3 hours of labor and 5 units of material. The company has a maximum of 60 hours of labor and 40 units of material available per week. The profit from each Standard Panel is GH¢80, and the profit from each High-Efficiency Panel is GH¢100. The company wants to determine how many of each type of panel to produce in order to maximize profit. i. Formulate a linear programming model of the problem for the company. ii Convert the linear programming model formulated in (a) to a standard form.arrow_forward
- G ווח >>> Mind Tap Cengage Learning 1- CENGAGE MINDTAP Chapter 09 Excel Activity: Exponential Smoothing Question 1 3.33/10 e Submit 自 A ng.cengage.com C Excel Online Student Work G A retail store records customer demand during each sales period. 1. What is the f... Q Search this course ? ✓ Co Excel Online Tutorial Excel Online Activity: Exponential Smoothing A-Z A retail store records customer demand during each sales period. The data has been collected in the Microsoft Excel Online file below. Use the Microsoft Excel Online file below to develop the single exponential smoothing forecast and answer the following questions. Office Video X Open spreadsheet Questions 1. What is the forecast for the 13th period based on the single exponential smoothing? Round your answer to two decimal places. 25.10 2. What is the MSE for the single exponential smoothing forecast? Round your answer to two decimal places. 21.88 Activity Frame ? 3. Choose the correct graph for the single exponential…arrow_forwardNot use ai pleasearrow_forwardItems removed from the work area (5S) were taken to a storage area called ___________. Choose from: SORT, STORD, KNUJ, STUFF, FUDG SORT STORD KNUJ STUFF FUDGarrow_forward
- Could you please help explain How was the poor strategic decisions lead to economic downturns of Circuit City Company? What are the sequences of key events and problems that contribute to its collapse. Could you please explain each one them and give the examples If Circuit City would apply Lean Six Sigma. would it helped prevent businesses from collapsed?? How Qualitative and quantitative Research Methodology in Case Study Research would affect Circuit City?arrow_forwardApple is a global technology company renowned for its innovation and design. To create its products, Apple has established a world class global supply chain to bring their products to market. What strategies is Apple using to source and manufacture its products? How does Apple view its responsibility to its suppliers and those who build its products?arrow_forwardCritical Path Method (CPM) is an important Project Management Tool that has wide industry application in modern day Project Management. By using an example of the project of your choice, critically examine the practical application of CPM as a Project Management Tool.arrow_forward
- Foundations of Business (MindTap Course List)MarketingISBN:9781337386920Author:William M. Pride, Robert J. Hughes, Jack R. KapoorPublisher:Cengage LearningFoundations of Business - Standalone book (MindTa...MarketingISBN:9781285193946Author:William M. Pride, Robert J. Hughes, Jack R. KapoorPublisher:Cengage Learning
- Understanding Management (MindTap Course List)ManagementISBN:9781305502215Author:Richard L. Daft, Dorothy MarcicPublisher:Cengage Learning


