a)
To determine: The standard time for the operation.
Introduction: Time study is the basis that helps set the standard time; it would time a sample of the performance of the worker.
a)
Answer to Problem 30P
Thestandard time is calculated as 85.56 minutes.
Explanation of Solution
Given information:
Fatigue factor is given as 10% and personal-time factor is 10%. Accuracy rate is ±5%. The observed time and performance rating for each element is given as follows:
Element | Performance rating | Observation (minutes) | ||||||
1 | 2 | 3 | 4 | 5 | 6 | 7 | ||
Select correct mufflers | 110% | 4 | 5 | 4 | 6 | 4 | 15a | 4 |
Remove old muffler | 90% | 6 | 8 | 7 | 6 | 7 | 6 | 7 |
Weld/install new muffler | 105% | 15 | 14 | 15 | 12 | 15 | 16 | 13 |
Check/inspect work | 100% | 3 | 4 | 24a | 5 | 4 | 3 | 18a |
Complete paperwork | 130% | 5 | 6 | 8 | - | 7 | 6 | 7 |
a refers to the fact that the employee has lengthy conversations with the boss (not job-related)
Formulae to calculate standard time:
Calculate normal time:
Element | Performance rating | Observation (minutes) | Average time | Normal time | ||||||
1 | 2 | 3 | 4 | 5 | 6 | 7 | ||||
Select correct mufflers | 110% | 4 | 5 | 4 | 6 | 4 | 15a | 4 | 4.50 | 4.95 |
Remove old muffler | 90% | 6 | 8 | 7 | 6 | 7 | 6 | 7 | 6.71 | 6.04 |
Weld/install new muffler | 105% | 15 | 14 | 14 | 12 | 15 | 16 | 13 | 14.14 | 14.85 |
Check/inspect work | 100% | 3 | 4 | 24a | 5 | 4 | 3 | 18a | 3.80 | 3.80 |
Complete paperwork | 130% | 5 | 6 | 8 | - | 7 | 6 | 7 | 6.50 | 8.45 |
Excel worksheet:
Calculate the average time to select correct mufflers:
The average time is calculated by taking an average of the observation given, which is the summation of 4, 5, 4, 6, 4, and 4 and dividing the result by 6. Hence, the average is 4.5 minutes.
Note: The observation with (Xa) should not be considered while calculating the average time.
Calculate the average time to remove the old muffler:
The average time is calculated by taking an average of the observation given, which is the summation of 6, 8, 7, 6, 7, 6, and 7 and dividing the result by 7. Hence, the average is 6.71 minutes.
Calculate the average time to weld or install a new muffler:
The average time is calculated by taking an average of the observation given, which is the summation of 15, 14, 14, 12, 15, 16, and 13 and dividing the result by 7. Hence, the average is 14.14 minutes.
Calculate the average time to check or inspect work:
The average time is calculated by taking an average of the observation given, which is the summation of 3, 4, 5, 4, and 3 and dividing the result by 5. Hence, the average is 3.80 minutes.
Note: The observation with (Xa) should not be considered while calculating the average time.
Calculate the average time to complete paperwork:
The average time is calculated by taking an average of the observation given, which is the summation of 5, 6, 8, 7, 6, and 7 and dividing the result by 6. Hence, the average is 6.50 minutes.
Calculate the normal time to select correct mufflers:
The normal time is calculated by multiplying the average time and performance rating. Average time is calculated as 4.50 minutes and performance rating is given as 110%. Hence, the normal time is 4.95 minutes.
Calculate the normal time to remove the old muffler:
The normal time is calculated by multiplying the average time and performance rating. Average time is calculated as 6.71 minutes and performance rating is given as 90%. Hence, the normal time is 6.04 minutes.
Calculate the normal time to weld or install a new muffler:
The normal time is calculated by multiplying the average time and performance rating. Average time is calculated as 14.14 minutes and performance rating is given as 105%. Hence, the normal time is 14.85 minutes.
Calculate the normal time to check or inspect work:
The normal time is calculated by multiplying the average time and performance rating. Average time is calculated as 3.80 minutes and performance rating is given as 100%. Hence, the normal time is 3.80 minutes.
Calculate the normal time to complete paperwork:
The normal time is calculated by multiplying the average time and performance rating. Average time is calculated as 6.50 minutes and performance rating is given as 130%. Hence, the normal time is 8.45 minutes.
Calculate the total normal time:
The normal time is calculated by multiplying the average time and performance rating. Average time is calculated as 6.50 minutes and performance rating is given as 130%. Hence, the normal time is 8.45 minutes.
Normal time is calculated by adding the normal time to select correct mufflers, remove the old muffler, weld or install a new muffler, check or inspect work, and to complete paperwork.
Hence, the total normal time is 38.09 minutes.
Calculate the standard time:
The standard time is calculated by dividing the normal time with the value attained by subtracting the allowance factor from 1. Normal time is calculated as 38.09 minutes and allowance factor is calculated as the sum of fatigue factor, which is 10% and personal time factor, which is 10%.
Hence, the standard time is 47.6 minutes.
b)
To determine: The number of
Introduction: Thesample size is required to determine the number of observations that are necessary to find the true cycle time.
b)
Answer to Problem 30P
Thesample size to select correct mufflers is 53, to remove the old muffler is 20, to weld or install a new muffler is 14, to check or inspect work is 75, and to complete paperwork is 40 samples.
Explanation of Solution
Given information:
Confidence level is 95% and accuracy is ±5%.
Element | Performance rating | Observation (minutes) | ||||||
1 | 2 | 3 | 4 | 5 | 6 | 7 | ||
Select correct mufflers | 110% | 4 | 5 | 4 | 6 | 4 | 15a | 4 |
Remove old muffler | 90% | 6 | 8 | 7 | 6 | 7 | 6 | 7 |
Weld/install new muffler | 105% | 15 | 14 | 15 | 12 | 15 | 16 | 13 |
Check/inspect work | 100% | 3 | 4 | 24a | 5 | 4 | 3 | 18a |
Complete paperwork | 130% | 5 | 6 | 8 | - | 7 | 6 | 7 |
a refers to the fact that the employee has lengthy conversation with the boss (not job-related)
Formulae to determine the required number of observation:
n refers to number of observations required
z refers to the table value for confidence level
s refers to standard deviation
h refers to accuracy level
Determine the proper number of observations required:
Element | Performance rating | Observation (minutes) | Average time | s | Sample | ||||||
1 | 2 | 3 | 4 | 5 | 6 | 7 | |||||
Select correct mufflers | 110% | 4 | 5 | 4 | 6 | 4 | 15a | 4 | 4.50 | 0.836 | 53.1 |
Remove old muffler | 90% | 6 | 8 | 7 | 6 | 7 | 6 | 7 | 6.71 | 0.755 | 19.5 |
Weld/install new muffler | 105% | 15 | 14 | 14 | 12 | 15 | 16 | 13 | 14.14 | 1.345 | 13.9 |
Check/inspect work | 100% | 3 | 4 | 24a | 5 | 4 | 3 | 18a | 3.80 | 0.836 | 74.5 |
Complete paperwork | 130% | 5 | 6 | 8 | - | 7 | 6 | 7 | 6.50 | 1.048 | 40.0 |
Excel worksheet:
Calculate the standard deviation to select correct mufflers:
The standard deviation can be calculated by dividing two values. The first value can be calculated by adding the square of the value attained by subtracting the mean observed value from each observation. The second value can be attained by subtracting 1 from the number of samples and the result should be square rooted. Standard deviation to select correct mufflers is 0.836.
Calculate standard deviation to remove old muffler:
The standard deviation can be calculated by dividing two values. The first value can be calculated by adding the square of the value attained by subtracting the mean observed value from each observation. The second value can be attained by subtracting 1 from the number of samples and the result should be square rooted. Standard deviation to remove old muffler is 0.755.
Calculate standard deviation to weld or install new muffler:
The standard deviation can be calculated by dividing two values. The first value can be calculated by adding the square of the value attained by subtracting the mean observed value from each observation. The second value can be attained by subtracting 1 from the number of samples and the result should be square rooted. Standard deviation to weld or install new muffler is 1.345.
Calculate standard deviation to check or inspect work:
The standard deviation can be calculated by dividing two values. The first value can be calculated by adding the square of the value attained by subtracting the mean observed value from each observation. The second value can be attained by subtracting 1 from the number of samples and the result should be square rooted. Standard deviation to check or inspect work is 0.836.
Calculate standard deviation to complete paperwork:
The standard deviation can be calculated by dividing two values. The first value can be calculated by adding the square of the value attained by subtracting the mean observed value from each observation. The second value can be attained by subtracting 1 from the number of samples and the result should be square rooted. Standard deviation to check or inspect work is 1.048.
Calculate the sample size to select correct mufflers:
It is calculated by multiplying the z value of 1.96, the standard deviation that is given as 0.836, and dividing the resultant with the multiple of the accuracy level and the average observed time that is given as 0.05 and 4.5, respectively. Hence, the required number of observations is 53 samples.
Calculate the sample size to remove the old muffler:
It is calculated by multiplying the z value of 1.96, the standard deviation that is given as 0.755, and dividing the resultant with the multiple of the accuracy level and the average observed time that is given as 0.05 and 6.71, respectively. Hence, the required number of observations is 20 samples.
Calculate the sample size to weld or install a new muffler:
It is calculated by multiplying the z value of 1.96, the standard deviation that is given as 1.345, and dividing the resultant with the multiple of the accuracy level and the average observed time that is given as 0.05 and 14.14, respectively. Hence, the required number of observations is 14 samples.
Calculate the sample size to check or inspect work:
It is calculated by multiplying the z value of 1.96, the standard deviation that is given as 0.836, and dividing the resultant with the multiple of the accuracy level and the average observed time that is given as 0.05 and 3.8, respectively. Hence, the required number of observations is 75 samples.
Calculate the sample size to complete paperwork:
It is calculated by multiplying the z value of 1.96, the standard deviation that is given as 1.048, and dividing the resultant with the multiple of the accuracy level and the average observed time that is given as 0.05 and 6.5, respectively. Hence, the required number of observations is 40 samples.
Hence, the standard time for the process is 47.6 minutes. The sample size to select correct mufflers are 53, to remove the old muffler is 20, weld or install a new muffler is 14, to check or inspect work is 75 samples, and to complete paperwork is 40 samples.
Want to see more full solutions like this?
Chapter 10 Solutions
Principles Of Operations Management
- EXPLAIN Human Resource Information System (HRIS)arrow_forwardRead the mini-case study below and answer the following questions.With an enormous amount of data stored in databases and data warehouses, it is increasinglyimportant to develop powerful tools for analysis of such data and mining interestingknowledge from it. Data mining is a process of inferring knowledge from such huge data. Themain problem related to the retrieval of information from the World Wide Web is theenormous number of unstructured documents and resources, i.e., the difficulty of locating andtracking appropriate sources.Briefly explain any five (5) types of information you can get from data mining.arrow_forwardProblem 1: Practice Problems Chapter 6 Managing Quality The accounts receivable department has documented the following defects over a 30-day period: Category Frequency Invoice amount does not agree with the check amount 108 Invoice not on record (not found) 24 No formal invoice issued Check (payment) not received on time 18 30 Check not signed 8 Invoice number and invoice referenced do not agree 12 What techniques would you use and what conclusions can you draw about defects in the accounts receivable department? Problem 2: Prepare a flow chart for purchasing a Big Mac at the drive-through window at McDonalds. Problem 3: Draw a fishbone chart detailing reasons why a part might not be correctly machined.arrow_forward
- Problem 5: Development of a new deluxe version of a particular software product is being considered. The activities necessary for the completion of this project are listed in the table below along with their costs and completion times in weeks. Activity Normal Crash Normal Crash Immediate Time Time Cost Cost Predecessor A 4 3 2,000 2,600 B 2 1 2,200 2,800 A C 3 3 500 500 A D 8 4 2,300 2,600 A E 6 3 900 1,200 B, D F 3 2 3,000 4,200 C, E G 4 2 1,400 2,000 F a. What is the project expected completion date? b. What is the total cost required for completing this project on normal time? c. If you wish to reduce the time required to complete this project by 1 week, which activity should be crashed, and how much will this increase the total cost?arrow_forwardI need answer typing clear urjent no chatgpt used pls i will give 5 Upvotes.with diagramarrow_forwardnot use ai pleasearrow_forward
- provide scholarly reseach and references for the following 1. explain operational risks and examples of such risk faced by management at financial institutions 2. discuss the importance of establishing an effective risk management policy at financial institutions to manage operational risk, giving example of a risk management strategy used by financial institutions to mitigate such risk. 3. what is the rold of the core principles of effective bank supervision as it relates to operational risk, in the effective management of financial institutions.arrow_forwardPlease show all units, work, and steps needed to solve this problem I need answer typing clear urjent no chatgpt used pls i will give 5 Upvotes.arrow_forwardIM.82 A distributor of industrial equipment purchases specialized compressors for use in air conditioners. The regular price is $50, however, the manufacturer of this compressor offers quantity discounts per the following discount schedule: Option Plan Quantity Discount A 1 - 299 0% B 300 - 1,199 0.50% C 1,200+ 1.50% The distributor pays $56 each time it places an order with the manufacturer. Holding costs are negligible (none) but they do earn 10% annual interest on all cash balances (meaning there will be a financial opportunity cost when they put cash into inventory). Annual demand is expected to be 10,750 units. When there is no quantity discount (Option Plan A, the first row of the schedule listed above), what is the adjusted order quantity? (Display your answer to the nearest whole number.) 491 Based on your answer to the previous question, and based on the annual demand as stated above, what will be the annual ordering costs? (Display your answer to the…arrow_forward
- Excel Please. The workload of many areas of banking operations varies considerably based on time of day. A variable capacity can be achieved effectively by employing part-time personnel. Because part-timers are not entitled to all the fringe benefits, they are often more economical than full-time employees. Other considerations, however, may limit the extent to which part-time people can be hired in a given department. The problem is to find an optimal workforce schedule that would meet personnel requirements at any given time and also be economical. Some of the factors affecting personnel assignments are listed here: The bank is open from 9:00am to 7:00pm. Full-time employees work for 8 hours (1 hour for lunch included) per day. They do not necessarily have to start their shift when the bank opens. Part-time employees work for at least 4 hours per day, but less than 8 hours per day and do not get a lunch break. By corporate policy, total part-time personnel hours is limited…arrow_forwardIM.84 An outdoor equipment manufacturer sells a rugged water bottle to complement its product line. They sell this item to a variety of sporting goods stores and other retailers. The manufacturer offers quantity discounts per the following discount schedule: Option Plan Quantity Price A 1 - 2,399 $5.50 B 2,400 - 3,999 $5.20 C 4,000+ $4.50 A large big-box retailer expects to sell 9,700 units this year. This retailer estimates that it incurs an internal administrative cost of $225 each time it places an order with the manufacturer. Holding cost for the retailer is $55 per case per year. (There are 40 units or water bottles per case.) Based on this information, and not taking into account any quantity discount offers, what is the calculated EOQ (in units)? (Display your answer to the nearest whole number.) Number Based on this information, sort each quantity discount plan from left to right by dragging the MOST preferred option plan to the left, and the LEAST preferred…arrow_forwardIn less than 150 words, what is an example of what your reflection of core values means to you and your work: Commitment, Perseverance, Community, Service, Pride?arrow_forward
- Foundations of Business (MindTap Course List)MarketingISBN:9781337386920Author:William M. Pride, Robert J. Hughes, Jack R. KapoorPublisher:Cengage LearningFoundations of Business - Standalone book (MindTa...MarketingISBN:9781285193946Author:William M. Pride, Robert J. Hughes, Jack R. KapoorPublisher:Cengage Learning
- Understanding Management (MindTap Course List)ManagementISBN:9781305502215Author:Richard L. Daft, Dorothy MarcicPublisher:Cengage Learning